Capacity Planning
Capacity Planning
Schedule
Understanding of capacity planning line factory section (attendance/efficiency) Operation breakdowns, independent and dependent processes, flow diagrams. Machine, equipment and manpower requirements. Line and production balancing. Production control Role of the supervisor
Factory capacity
500 operators working 48 hour week. Work content of 30 minutes per garment Therefore
Definitions
On Standard : Time the operator spends on measured work, earning standard minutes (SM).
Off Standard : Time the operator spends on un-measured work or measured work that is classified as off-standard.
SMV/SAM?
Standard Minute Value (S.M.V.) is the time allocated through work measurement for an operation to be completed at a 100 rating. (Basic Work Content) Standard Allocated (Allotted) Minute (S.A.M.) is an S.M.V. + any policy allowances added.
Definitions Operator Utilisation A measure of how well the supervisor manages to keep the operators on standard
= time on-standard x 100 time attended
Definitions Efficiency
A measure of how well the section/factory is run. SMs earned x 100 time attended. A measure of both the operator and the supervisor Incorporates elements of operator performance & utilisation into the single measure
total operator time attended x 100 total contracted time = attendance. Absence = 1/attendance
Measures factor/section/operator
Standard hours (minutes) produced. Operator performance Operator utilisation Section efficiency Off standard time Absence (attendance)
Measures Examples
Section = 20 operators working 9 hour/540 minute day 2 operators are absent all day Attendance = 18 x 540 x 100 20 x 540 = 9720 10800 = 90% (or) 10% absence
Measures Examples
An operator attends for 540 minutes Produces 1500 pieces @ SMV of 0.30 Waits 60 minutes for work Waits 20 minutes machine breakdown
Measures Examples
Sms produced = 1500 x 0.30 = 450. Time on-standard = 540 (60+20) = 460 minutes Performance = 450 x 100 460 = 97.8 or 98%
Measures Examples Operator Utilisation = 460 x 100 = 85.2% 540 Not acceptable ?
Measures Examples
Exercise
Section 1 Operator cont Att op. production SMV offStd Perf Uti min min Alison 540 540 1. 1000 0.37 30 Betty 540 480 2 1120 0.30 charlie 540 0 3 0 0.26 Dorothy 540 540 4 950 0.23 3 350 0.26 75 Ethel 540 540 5 1070 0.45 15 Freda 540 540 6 1250 0.40 30 Gail 540 540 7 1200 0.21 3 880 0.26 Heather 540 540 8 600 0.85 30 Irma 540 540 8 600 0.85 45 June 540 540 9 1275 0.38 30 Totals Eff
Exercise
Section 1
Operator cont. Att op production SMV OffStd Perf Uti Eff mins Alison 540 540 1. 1000 0.37 30 72.5 94 68.5 Betty 540 480 2 1120 0.30 70 100 70 charlie 540 0 3 0 0.26 Dorothy 540 540 4 950 0.23 66.5 86 57.3 3 350 0.26 75 Ethel 540 540 5 1070 0.45 15 91.7 97 89.2 Freda 540 540 6 1250 0.40 30 98 94 92.5 Gail 540 540 7 1200 0.21 89 100 89 3 880 0.26 Heather 540 540 8 600 0.85 30 100 94 94.4 Irma 540 540 8 600 0.85 45 103 92 94.4 June 540 540 9 1275 0.38 30 95 94 89.7 Totals 5400 4800 3.22 255 87.6 94.7 83
Exercise
Attendance = 4800/5400 = 89% total sms earned = 3982.30
Capacity planning
Factory Department Section Machine Skill Restricting or defining factor
Capacity planning
What is the starting point? How many garments can a section produce? How many operators/machines do we need to produce a given number of garments? Same calculation just reversed!
Information!!
Labour content (SMVs/SAMs/Std. hrs) Available operators Contracted hours Absenteeism levels Efficiency levels
Capacity planning Information Information Information Obvious but where does it come from? How accurate is it?
Capacity planning
Under the same conditions how many people are need to produced 70000 garments per week.?
70000 x 0.417 = 29190 standard hours required. Each operator will produce 39 hours @ 85% efficiency = 39 x 85% = 33.15 std. hrs/week
Capacity planning
29190 standard hours required. Each operator will produce 33.15 std. hrs/week Number of operators = 29190 33.15 = 880.54 people. + Absence of 8% = 880.54 +8%.= 951
Capacity planning
Capacity planning is only as accurate as the information it is based upon!
Capacity planning
Limiting factors People X Machines? Department?
Capacity planning-machines
Auto pocket set machine S.M.V. 0.60 Efficiency = 95% 15 machines available 8.50 hour day How many garments can they supply to sections?
Capacity planning-machines
15 machines x 8.50 hours = 127.50 hours/day. @95% efficiency std. hrs produced = 121.13 hrs SMV = 0.60 = 100 per hour at standard Output = 100 x 121.13 = 12113 garments Absence ignored as decision taken to ensure absence cover (15 machines + 8* absence = 17 operators. 1 spare shared with pressing
Capacity planning-machines
Capacity must be increased to 25000 per day. Each machine does 100 x 95% = 95 per hour. 25000/95 = 263.15 hours. In 8.5 hour day = 31 machines However machines cost $75000 each and have a six month delivery lead time. Try again!!!
Capacity planning-machines
Each machine will produce 95 per hour worked. 25000/95 = 263.15 hours 263.15 hours / 15 machines = 17.54 per machine per day 2 shifts
Capacity planning
Limiting factors People X Machines X Department?
Capacity planning-spreading
50000 garments x 0.90 metres = 45000 metres to be cut each week. Each metre Smv = 0.1584 therefore 45000 x 0.1584 = 0.1584 x 45000 60 = 118.80 std.hrs required @ 90% efficiency = 132 operated hours./ 3machines = 44 hour week
Capacity planning-spreading
24000 garments x 0.90 metres = 21600 metres to be cut each week. Each metre Smv = 0.1584 therefore 21600 x 0.1584 = 0.1584 x 21600 60 = 61.60 std.hrs required @ 90% efficiency = 68.40 operated hours./ 3machines = 22.80 hour week