TOTAL TIME (min) : O 355 25 2 0 D 70

Model No:
Title: Spur Gears
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-2014
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D - DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1. Collect tool set * 30
2. Collect MS rod * 15
3. Mark length needed * 5
4. Rod to rod cutting machine * 30
5. Cutting of rod * 45
6. Facing * 10
7. Drilling * 40
8. Turning * 120
9. Checking dimension * 5
10. To horizontal milling machine * 2
11. Setting the machine * 10
12. Gear cutting * 120
13. Boring * 20














TOTAL TIME (min) : O 335 25 2 0 D 70



Model No:
Title: Spur Gears
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-2014
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1. Collect tool set * 30
2. Collect MS rod * 15
3. Mark length needed * 5
4. Rod to rod cutting machine * 30
5. Cutting of rod * 45
6. Facing * 10
7. Drilling * 40
8. Turning * 120
9. Checking dimension * 5
10. To horizontal milling machine * 2
11. Setting the machine * 10
12. Gear cutting * 120















TOTAL TIME (min) : O 132 12 5 0 D 40



Model No:
Title: Shafts
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated: 21-4-2014
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collect tool set * 30
2 Collect ms rod * 5
3 Mark required dimension * 5
4 to fitting shop * 3
5 Fixing in the benchwise * 2
6 Collect hacksaw * 10
7 Rod cutting * 40
8 To lathe * 2
9 Turning * 90
10 Dimension checking * 2
















TOTAL TIME (min) : O 105 20 65 0 D30




Model No:
Title: Framework
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-2014
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collecting plywood and wooden columns * 60
2 Collect tool set * 30
3 Marking required dimension * 15
4 To carpentry * 2
5 Cutting using jigsaw * 30
6 Checking dimension * 5
7 To drilling machine * 3
8 Drilling * 20
9 Filing * 15
10 Fitting bearing * 40














TOTAL TIME (min) : O 125 15 3 0 D30



Model No:
Title: Wooden Columns
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-14
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collect tool set * 30
2 Collect wooden planks * 10
3 Plaining of surface * 10
4 Marking of dimension * 5
5 Cutting into desired shapes * 75
6 To drilling machine * 3
7 Drilling * 30
8 Making slot * 10

















TOTAL TIME (min) : O 40 7 8 0 D30









Model No:
Title: Slotted lever
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-14
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D - DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collect tool set * 30
2 Collect ms rod * 5
3 Mark dimension * 2
4 To rod cutting maching * 2
5 Cutting * 20
6 To Drilling machine * 2
7 Drilling * 15
8 To fitting * 2
9 To welding centre * 2
10 Welding * 5










TOTAL TIME (min) : O 152 5 30 0 D 0




Model No:
Title:Assembly
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-14
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D - DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collect nails and L-clamp * 30
2 Fixing shaft in plywood * 10
3 Welding gear to shaft * 12
4 Mark dimensions * 5
5 Fixing clamps * 20
6 Welding crank to shaft * 15
7 Assembling quick return components * 20
8 Hammering * 10
9 Fixing handle * 5
10 Painting * 60














TOTAL TIME (min) : O 125 15 3 0 D 30




Model No:
Title: Transporter link
Figure No.

CENTRAL WORKSHOPS
PROCESS CHART
Type: Man/Machine
Charted by:
Dated:21-4-14
O -OPERATION - INSPECTION -TRANSPORT - STORAGE D DELAY
EVENT PERFORMED ON------IS UPTO SERIAL NO. .. SHEET NO..OF .
S.No. DESCRIPTION O D TIME (m)
1 Collect tool set * 30
2 Collect wooden planks * 10
3 Plaining of surface * 10
4 Marking of dimension * 5
5 Cutting into desired shapes * 75
6 To drilling machine * 3
7 Drilling * 30
8 Making slot * 10