www.inspectionforindustry.

com
Remark
Manuf. TPI Client
1 PreInspectionMeeting Spec. Spec. MOM H H H
2
ApprovalofMechanical
CalculationBooks
Datasheets,PO,Spec. API650,Spec. CalcualtionBook H H A
3
ApprovalofFabrication
Drawings
DWG,Spec. API650,Spec. DWG H H A
4
Reviewmilltest
certificatesofplates
DWG,Certificates ASMESECII Certificates H W R
5
Reviewmilltest
certificatesofpipe,flange,
etc.
DWG,Certificates ASMESECII,16.5 Certificates H W R
6
Reviewmilltest
certificatesofwelding
consumablematerial
WPS,Certificates ASMESECII Certificates H W R
7
Visual&Dimensional
Check
DWG,Spec. ASMESECII Report H W R
8 BottomPlates DWG,WPS,Spec. API650,Spec. Report H SW R
9 AnnularPlates DWG,WPS,Spec API650,Spec. Report H SW R
StorageTankInspectionandTestPlan
ActivityBy
No. InspectionandTestPlan ReferenceDocument AcceptanceCriteria VerifyingDocument
BeforManufacturing
Materials
DuringmanufacturingMarking,Cutting,BevelingandGrinding
www.inspectionforindustry.com
10 ShellCourses DWG,WPS,Spec API650,Spec. Report H SW R
11 RoofPlates DWG,WPS,Spec API650,Spec. Report H SW R
12 RoofStructures DWG,WPS,Spec API650,Spec. Report H SW R
13 WindGriders(Ifrequired) DWG,WPS,Spec API650,Spec. Report H SW R
14 TopAngles(ifrequired) DWG,WPS,Spec API650,Spec. Report H SW R
15 ReinforcementPads DWG,WPS,Spec API650,Spec. Report H SW R
16
ManholeNozzleNeck
(FromPlates)
DWG,WPS,Spec API650,Spec. Report H SW R
17
PipeForColumn(if
required)
DWG,WPS,Spec API650,Spec. Report H SW R
18 PipeForNozzles DWG,WPS,Spec API650,Spec. Report H SW R
19 InternalPipes DWG,WPS,Spec API650,Spec. Report H SW R
20
InternalorExternal
Supports
DWG,WPS,Spec API650,Spec. Report H SW R
21 Sumps DWG,WPS,Spec API650,Spec. Report H SW R
22
SpiralStairway&
Platforms
DWG,WPS,Spec API650,Spec. Report H SW R
23
Visual&Dimensional
CheckofLooseParts
DWG,WPS,Spec API650,Spec. Report H H R
24 ShellCourses DWG,Spec. API650,Spec. Report H W R
25 Sumps DWG,Spec. API650,Spec. Report H SW R
26 TopAngles DWG,Spec. API650,Spec. Report H W R
27
ManholeNozzleNeck
(FromPlates)
DWG,Spec. API650,Spec. Report H SW R
DuringmanufacturingFormingandRolling
www.inspectionforindustry.com
28
Visual&Dimensional
Check
DWG,Spec. API650,Spec. Report H H R
29
LevelnessofRing
Wall(ifapplicable)
DWG,Spec. API650,Spec. Report H H R
30 CenterPointandRadius DWG,Spec. API650,Spec. Report H H R
31 Flatness&Slope DWG,Spec. API650,Spec. Report H H R
32 Orientation DWG,Spec. API650,Spec. Report H H R
33
Anchor
bolts(Distance,
Projection,etc.)as
required
DWG,Spec. API650,Spec. Report H H R
34 WPS&PQR DWG,WPS,PQR,Spec ASMESECIX Report H R/A R
35
Welder/Welding
Operator
Qualification
DWG,WPS,WQT,Spec ASMESECIX Report H R/A R
36
NDTOperator
CertificateCheck
Certificates API650,Spec. Report H R/A R
37 Fitupofbottomplates DWG,WPS,Spec API650,Spec. Report H H R
38
Weldingsequence
implementation
DWG,WPS,Spec API650,Spec. Report H H R
39
Visualinspectionof
weldment
DWG,WPS,Spec API650,Spec. Report H H R
40
Vacuumboxtestof
bottomplates
Spec. API650,Spec. Report H H R
DuringManufacturingFoundation
DuringManufacturingWelding
www.inspectionforindustry.com
41
Annularplate
orientationcheck
DWG,Spec. API650,Spec. Report H H R
42
Fitup&weldingof
annularplate
DWG,WPS,Spec API650,Spec. Report H H R
43
NDTofannularplate
/VacuumTest(Ifrequired)
Spec. API650,Spec. Report H H R
44 FitupofShellPlate DWG,WPS,Spec API650,Spec. Report H H R
45 WeldingofShellPlate DWG,WPS,Spec API650,Spec. Report H H R
46 PWHT(ifRequired) WPS,Spec API650,Spec. Report H H R
47 NDTofShellPlate Spec. API650,Spec. Report H H R
48
OilTestofAnnularPlate
toshellPlate
Spec. API650,Spec. Report H H R
49
Fitup&welding
compressionring&roof
plate
DWG,WPS,Spec API650,Spec. Report H H R
50 Weldingofroofplates DWG,WPS,Spec API650,Spec. Report H H R
51 Airtestofroofplate Spec. API650,Spec. Report H H R
52
Airtestof
reinforcements
Spec. API650,Spec. Report H H R
53 Plumbness DWG,Spec. API650,Spec. Report H H R
54 Roundness DWG,Spec. API650,Spec. Report H H R
55 Peaking&Banding DWG,Spec. API650,Spec. Report H H R
DuringManufacturingDimentionalCheck
www.inspectionforindustry.com
56
NozzleElevation,
OrientationandProjection
DWG,Spec. API650,Spec. Report H H R
57
ManholeElevation,
OrientationandProjection
DWG,Spec. API650,Spec. Report H H R
58
Verificationof
TestPackage
Reports API650,Spec. Report H H R
59
Hydrotest(Water
level/Holdingtime)
Spec. API650,Spec. Report H H H
60
Settlementcheck
(Refertoapplicable
procedure)
DWG,Spec. API650,Spec. Report H H R
61 Waterdischarge Spec. API650,Spec. Report H W R
62 Cleaningcheck Spec. API650,Spec. Report H H R
63
Paintingmaterial
identification/check
Spec. API650,Spec. Report H H R
64
Weathercondition&
SurfacePreparation
(Blasting)
Spec. API650,Spec. Report H H R
65
PrimerLayerInspection
(IncludingDryThickness
check)
Spec. API650,Spec. Report H H R
66
Intermediate/FinalLayer
Inspection(Including
DryThicknesscheck)
Spec. API650,Spec. Report H H R
DuringManufacturingHydroStaticTest
DuringManufacturingPaintingActivities
DuringManufacturingCathodicProtectionandElectrical
www.inspectionforindustry.com
67
Checkofmaterialpriorto
installation
Spec. API650,Spec. Report H H R
68
InstallationofEarthing
Bosses
Spec. API650,Spec. Report H H R
69 AnodeInstallation Spec. API650,Spec. Report H H R
70
CheckofAnode&
conductor
Spec. API650,Spec. Report H H R
71
ChecktheBonding
ofUGPipe
Spec. API650,Spec. Report H H R
72 CableInstallation Spec. API650,Spec. Report H H R
73
ChecktheTestBox,
ReferenceElectrode
Spec. API650,Spec. Report H H R
74
installationofreference
electrodeincludingcable
Spec. API650,Spec. Report H H R
P.O:PurchaseOrder
MOM:MinuteofMeeting
Abbreviations:
H:HoldPoint=HoldontheproductiontillTPIInspectorperformsinspectionandsupervisetherequiredtest
W:WitnessPoint=ManufactureshallnotifyclientandTPIInspectorbutthereisnoholdontheproduction;
ClientcanwaivethisinspectionbasedonhisdiscretionandinformsTPIInspectoraccordingly.
R:DocumentReview=ReviewmeansReviewdocument,whichincludesofmaterialtestcertificates,WPS,PQR,NDTProceduresandetc.
A:Approval
SW:SpotWitness=foritemswithspotwitnessmanufactureshallnotifyTPIinspectorasfulfillingthemonitoring;
ForexampleonerandomvisitforwholeUTtestsoroneortwovisitsforwholesurfacepreparationworksforpainting.