MOM between GTEL and AGP for SCADA at AGP office RAK on 17

th
Feb13


Present :
AGP GTEL
1. CK Sharma 1. Mr. Iqbal
2. Jithendran 2. Mr. Yusuf
3. K. Suresh 3. Mr. Irfan

Gist of discussions are as follows
Description Action on
01 welcome AGP welcomed team from GTEL info
02 Delivery AGP asked to expedite delivery of project by start of
summer Period.
GTEL
03 Project schedule Project schedule is already prepared by GTEL and will be
given today
GTEL
04 Design First lot of Design documentation will be submitted by this
week

MTS : specs/Data sheets of MTS will be submitted by this
week

GTEL
05 Documentation Following documents are required by GTEL :
1. Plant lay out
2. 33kV Schematic Diag
3. 11kV Schematic Diag
4. CCR layout
5. Sepam specs of 11kV
6. 33kV schematic diag
7. 33kV switch gear details
8. 33kV IED details
9. Company logo
AGP will send soft copy by Tomorrow morning except 11kV
schematic. Hard copy of 11kV schematic will be handed
over today to GTEL
AGP
06 GTEL like to take up Site visit to Al Ghail power plant
today, which AGP is will facilitate

GTEL and AGP
07 Progress rev
Meetings
Regular progress review meeting will be at two weeks info
08 Contact points Organization chart from GTEL for the project will be
submitted by today.
GTEL informed that Project director is Mr. Iqbal and Mr.
Yusuf will be project manager
First point of contact will be Mr. Yusuf

Point of contact from AGP is CK Sharma, Jithendran and K.
Suresh

GTEL
09 GTEL asked to expedite Relay coordination and relay testing
and Parallel operation purchase orders.
AGP
10 AGP is going to appoint a Consultant for monitoring the
project , witnessing FAT, SAT and will certify progressive
payments
info