AUB FAHED AL SALEM Printed 1/28/2014

1 Laying of Cable N/A


2 Connecting of Cable to Branch N/A
3 Arrival of Power to branch N/A
4 Meggar Testing Pending By Contractor
5 MEW Rotation Test N/A
6 Earthing Pending By Contractor
7 Panels & DB`s Pending By Contractor
8 Internal Lights Approved
9 Emergency & Night Lights Approved
10 Teller Lights Approved
11 External Lights Approved
12 Normal Power Approved
13 UPS Power Approved
14 Photocell Pending Installation pending
15 System Links Approved
16 Fire Alarm Pending Tested but to finish the comments
17 Data System Pending By Contractor
18 LV System Cable Testing Approved
19 HVAC System Approved
20 HVAC System - Summer In Summer Testing during Summer
21 Exhaust System N/A
22 Hot & Cold Water Approved
23 Fire Fighting Approved
24 Furniture Exact Location Approved
25 Autodoor Approved
26 Rolling Shutter Approved
27 Doors & Closers Approved
28 Vault Doors Approved
29 Waterproofing Approved
Toilet area only. Guarranttee to be
submitted
30 Shaft Waterproofing N/A
31 Elevator AUB
32 Elevator Load Test By Third Party AUB
33 Water Tank N/A
34 Irrigation System N/A
35 UPS Pending
Awaiting operating the branch (for
guarantee)
36 ATM AUB
37 Plasmas & DVD`s AUB
38 Generator N/A
39 ATS N/A
40 CCTV System AUB
41 Acc & Int Alarm AUB
42 PABX System AUB
43 Q-Matic AUB
44 Music AUB
45 Satellite TV N/A
46 Video Intercom AUB
47 Safe Deposit Lockers Pending End of February
48 KFBD Final Inspection Approved
49 MEW Compliance Letter N/A
50 KFB Compliance Letter N/A
TESTING & COMMISSIONING
SN # System Status Remarks
Fahed Al Salem Branch Handover AUB/ OHA