May 17, 2014

AMCON & COMPANY INC.
Project Manager
Capitol Commons Project

Attention: ARCH. AMADOR D. REDONDO
Project Manager AMCON, CAPITOL COMMONS
Amcon & Company, Inc.

Thru: ENGR. CESAR GREGORIO
Construction Manager - AMCON, CAPITOL COMMONS
Amcon & Company, Inc.

Project: ESTANCIA MALL PROJECT
CP-3.2: General Architectural, Exterior Finishes and Finishing Works

Subject: REPORT FOR THE INSTALLATION OF LOUVERED DOORS (D10) OF UTILITY ROOMS

Sir,

We would like to inform your good office about our on-going installation of louvered
doors for utility rooms (AHU, Tel. Room, Water Metering, BOH, Garbage and Watertank
Room). As per original plan, the schedule of this door is 1.80m wide by 2.40m height
and was provided at site during our masonry works which is substantially completed
but the approved actual doors from the supplier (LEC STEEL) becomes wider (2.473m
wide by 2.444m height). From these changes, we are required to do chipping works on
both sides and provide new stiffener columns & beams which are affected in the
preparation of door opening. Please see the attached picture for reference.

Thank you.



Very Truly Yours,
ARDI Development & Construction Inc.


GLENN G. SARNE
Project Manager