ID Task Mode Task Name Duration Start Finish

1 Pekerjaan Jalan 180 days Mon 31/03/14Fri 26/09/14


2 Divisi 1 umum 34 days Mon 31/03/14Sat 03/05/14
3 Mobilisasi 4 days Mon 31/03/14Thu 03/04/14
4 Pembersihan 25 days Fri 04/04/14 Mon 28/04/14
5 Pengukuran termasuk
pemasangan Patok
12 days Fri 18/04/14 Tue 29/04/14
6 Kantor Lapangan 7 days Tue 08/04/14 Mon 14/04/14
7 Barak Pekerja/Bedeng 17 days Tue 15/04/14 Thu 01/05/14
8 Kantin 2 days Tue 08/04/14 Wed 09/04/14
9 Mushalah 2 days Thu 10/04/14 Fri 11/04/14
10 Bengkel 3 days Sat 12/04/14 Mon 14/04/14
11 Pengadaan Air, Listrik dan
Telepon
4 days Tue 01/04/14 Fri 04/04/14
12 Laboratorium Pengujian 3 days Tue 15/04/14 Thu 17/04/14
13 Papan Nama Proyek 1 day Mon 07/04/14Mon 07/04/14
14 Pagar Sementara Base
Camp
15 days Mon
07/04/14
Mon
21/04/14 15 Gudang 1 day Tue 22/04/14 Tue 22/04/14
16 Pos Keamanan 2 days Wed 23/04/14Thu 24/04/14
17 Demobilisasi 2 days Fri 02/05/14 Sat 03/05/14
18 Divisi 2 Pekerjaan Tanah 54 days Sun 04/05/14 Thu 26/06/14
19 Pengupasan Top Soil 7 days Sun 04/05/14 Sat 10/05/14
20 Pembuangan Top Soil 6 days Tue 06/05/14 Sun 11/05/14
21 Penggalian Tanah STA
0+00-0+400
7 days Fri 23/05/14 Thu 29/05/14
22 Penggalian Tanah STA
0+600-0+800
4 days Mon
19/05/14
Thu 22/05/14
23 Penggalian Tanah STA
1+800-2+200
7 days Mon
12/05/14
Sun 18/05/14
24 Pembuangan Tanah
Galian STA 0+00-0+400
6 days Sun 25/05/14 Fri 30/05/14
25 Pembuangan Tanah Galian
STA 0+600-0+800
3 days Wed
21/05/14
Fri 23/05/14
26 Pembuangan Tanah Galian
STA 1+800-2+200
6 days Wed
14/05/14
Mon
19/05/14 27 Penimbunan ,Perataan dan
Pemadatan Tanah STA
3 days Sat 24/05/14 Mon
26/05/14 28 Penimbunan ,Perataan dan
Pemadatan Tanah STA
13 days Fri 30/05/14 Wed
11/06/14 29 Penimbunan ,Perataan dan
Pemadatan Tanah STA
3 days Tue 27/05/14 Thu 29/05/14
30 Pembentukan Penampang
Jalan dan Pemadatan
10 days Thu 12/06/14 Sat 21/06/14
31 Pekerjaan Galian Talud 8 days Thu 12/06/14 Thu 19/06/14
32 Pengankutan dan
Pembuangan Tanah Galian
14 days Fri 13/06/14 Thu 26/06/14
33 Divisi 3 Drainase 39 days Sat 21/06/14 Tue 29/07/14
34 Pekerjaan Galian Tanah
Saluran U-ditch, Bak
7 days Sat 21/06/14 Fri 27/06/14
35 Pekerjaan Pengangkutan dan
Pembuangan tanah Galian
14 days Fri 27/06/14 Thu 10/07/14
36 Pekerjaan Pondasi
Saluran U-ditch, Bak
17 days Mon
23/06/14
Wed
09/07/14 37 Pemasangan Saluran
U-ditch dan Gorong-gorong
28 days Mon
30/06/14
Sun 27/07/14
38 Pekerjaan Sambungan
Gorong-Gorong
2 days Sun 27/07/14 Mon
28/07/14 39 Pekerjaan Timbunan
Tanah Sauran U-ditch, &
7 days Wed
23/07/14
Tue 29/07/14
40 Pekerjaan Bak
Penampung dan Jagaan
7 days Thu 10/07/14 Wed
16/07/14 41 Pemasangan Pemecah
Arus
7 days Thu 10/07/14 Wed
16/07/14 42 Divisi 4 Perkerasan 50 days Wed 30/07/14Wed 17/09/14
43 Pemasangan Bekisting
Lean Concrete (10cm) dan
7 days Wed
30/07/14
Tue 05/08/14
44 Pengecoran Lean Concrete 10 days Fri 01/08/14 Sun 10/08/14
45 Pemasangan Membran
Kedap Air untuk Beton
7 days Tue 05/08/14 Mon
11/08/14 46 Pembesian 14 days Tue 05/08/14 Mon 18/08/14
47 Pengecoran Perkerasan
Beton Semen termasuk
14 days Wed
06/08/14
Tue 19/08/14
48 Pembongkaran Bekisting
Perkerasan Lean concrate
5 days Thu 07/08/14 Mon
11/08/14 49 Pemotongan Sambungan
dan Pengisian bahan
14 days Thu 07/08/14 Wed
20/08/14 50 Curing 42 days Wed 06/08/14Tue 16/09/14
51 Cek Kekuatan Beton 1 day Wed 17/09/14Wed 17/09/14
52 Divisi 5 Perlengkapan
Jalan
21 days Fri 22/08/14 Thu 11/09/14
53 Marka Jalan Thermoplastik 7 days Fri 22/08/14 Thu 28/08/14
54 Pekerjaan Kerb Beton 14 days Fri 22/08/14 Thu 04/09/14
55 Pemasangan Paving Block 21 days Fri 22/08/14 Thu 11/09/14
56 Penanaman Rumput Talud 7 days Fri 22/08/14 Thu 28/08/14
57 Instalasi Lampu
Penerangan Jalan Umum
7 days Fri 29/08/14 Thu 04/09/14
58 Rambu-rambu Lalu Lintas 7 days Fri 29/08/14 Thu 04/09/14
59 Divisi 6 Finishing 9 days Thu 18/09/14 Fri 26/09/14
60 Pembersihan Akhir 9 days Thu 18/09/14 Fri 26/09/14
bulldozer d6d[900%];dump truck hd 325[300%];wheel loader [500%]
bulldozer d6d[800%]
wheel loader [500%];dump truck hd 325[300%]
bulldozer d6d[700%]
bulldozer d6d[600%]
bulldozer d6d[600%]
wheel loader [400%];dump truck hd 325[300%]
wheel loader [400%];dump truck hd 325[300%]
dump truck hd 325[300%];wheel loader [400%]
bulldozer d6d[400%];vibro roller
bulldozer d6d[1.100%];vibro roller
bulldozer d6d[400%];vibro roller
vibro roller[200%];motor grader[600%]
excavator[300%]
wheel loader [400%];bulldozer d6d[300%]
excavator[200%]
dump truck hd 325[300%];wheel loader [400%]
unique crane[200%]
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 Apr '14 05 May '14 12 May '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: projectx
Date: Wed 23/04/14
bulldozer d6d[900%];dump truck hd 325[300%];wheel loader [500%]
bulldozer d6d[800%]
wheel loader [500%];dump truck hd 325[300%]
bulldozer d6d[700%]
bulldozer d6d[600%]
bulldozer d6d[600%]
wheel loader [400%];dump truck hd 325[300%]
wheel loader [400%];dump truck hd 325[300%]
dump truck hd 325[300%];wheel loader [400%]
bulldozer d6d[400%];vibro roller
bulldozer d6d[1.100%];vibro roller
bulldozer d6d[400%];vibro roller
vibro roller[200%];motor grader[600%]
excavator[300%]
wheel loader [400%];bulldozer d6d[300%]
excavator[200%]
dump truck hd 325[300%];wheel loader [400%]
unique crane[200%]
truck mixer;concrete paver tanpa slip form
concrete paver dengan slip form;truck mixer
saw cutter
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
12 May '14 19 May '14 26 May '14 02 Jun '14 09 Jun '14 16 Jun '14 23 Jun '14 30 Jun '14 07 Jul '14 14 Jul '14 21 Jul '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: projectx
Date: Wed 23/04/14
bulldozer d6d[700%]
bulldozer d6d[600%]
bulldozer d6d[600%]
wheel loader [400%];dump truck hd 325[300%]
wheel loader [400%];dump truck hd 325[300%]
dump truck hd 325[300%];wheel loader [400%]
bulldozer d6d[400%];vibro roller
bulldozer d6d[1.100%];vibro roller
bulldozer d6d[400%];vibro roller
vibro roller[200%];motor grader[600%]
excavator[300%]
wheel loader [400%];bulldozer d6d[300%]
excavator[200%]
dump truck hd 325[300%];wheel loader [400%]
unique crane[200%]
truck mixer;concrete paver tanpa slip form
concrete paver dengan slip form;truck mixer
saw cutter
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
21 Jul '14 28 Jul '14 04 Aug '14 11 Aug '14 18 Aug '14 25 Aug '14 01 Sep '14 08 Sep '14 15 Sep '14 22 Sep '14 29 Sep '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: projectx
Date: Wed 23/04/14