Professional Documents
Culture Documents
FIDIC Checklist Guidelines
FIDIC Checklist Guidelines
December 2006
PREFACE
It can be used
during preparation and review of contracts documents for construction works under JBIC ODA
loans.
Chapter 1 : Purpose of Check List
The purposes of the Check List are described in chapter 1 together with the background behind the
necessity of such a check list.
Chapter 2 : Distinctive Features of FIDIC Red Book
The general features and basic concepts of the FIDIC Red Book, which should be well understood
by writers of construction contracts under JBIC ODA loans, are set out in chapter 2.
Chapter 3 : Factors which create One Sided Contract
The factors which create contracts one sided are examined in chapter 3 by categorizing the effects
into 3 groups.
Chapter 4 : Commentary on the Check List
A commentary on the Check List is set out in chapter 4 as a guide to users.
risk distribution to a large extent and the risks allocated to the Contractor become excessively
high, the following problems may occur:(1)
(2)
(3)
(4)
Contract award to a bidder who fails or was not capable of estimating the risks properly
(5)
Poor construction quality and delay to the progress of the work due to lack of risk
contingency
(6)
Undermining the relationship of mutual trust and respect between the Employer and the
Contractor
(7)
(8)
(9)
These situations interfere with the smooth implementation of projects financed by Japanese
ODA loans and, as a result, may impose larger financial burdens on the Employer.
The Check List is prepared for the purpose of elimination of one sided provisions from the
contract.
Check List as a reference guide in preparation of bid documents under JBIC Loans in order to
allocate risks and liabilities fairly between contracting parties as well as to keep fairness of the
Engineer .
The Check List is drafted based on actual experience on pervious construction contracts financed
by Japanese ODA loans.
adopted in standard bidding documents for most multilateral development banks including
World Bank and Asian Development Bank3.
While JBIC is examining revision of the Sample Bidding Documents incorporating new FIDIC
Red Book 1999, the Engineers roles described hereinafter will remain unchanged in principle
except for the matters indicated in foot notes 3 and 4 on Page 4.
The FIDIC conditions of contract comprise Part 1: General Conditions of Contract and Part 2:
Conditions of Particular Application. Part II has the following functions:(1) to supplement and complete Sub-clause 1.1
2.1
5.1
14.1
14.3
68.2 in Part I
(2) to add particular provision required by local conditions such as characteristics of execution
agency, project, region and country, etc.
(3) to add to particular requirements or recommendations of the project financer
If the Part II additions, supplementations and or modification of Part I alter the basic balance of
the FIDIC Red Book the contract may become unfairly advantageous to the drafting party.
The basic concepts and framework of the FIDIC Red Book are summarized below:1) Design by Employer
FIDIC Red Book is suitable for Design-Bid-Build projects.
The first edition of FIDIC Red Book was issued in 1957 and it was drafted based on ICE conditions of contracts in
UK.
3 World Bank and Asian Development Bank issued Harmonized Edition of Sample Bidding Documents based on
FIDIC Red Book 1999 in May 2005. Both banks adopted FIDIC Red Book 1987 in their previous versions of Sample
Bidding Documents.
permanent work except for the works to be designed by Contractor in accordance with Clause
7.2, and the contractor executes the work according to those drawings and specifications
provided with the bid documents.
engineer appointed by the Employer and the design liability lies with the Employer
refer to
The
Engineer is not a contracting party but his duties and authority are stipulated in the contract and
the Engineer plays an essential role in the contract administration process.
Employer
(Construction
(Consultancy
Contract)
Agreement)
(Report, Notice,
Application)
Contractor
Engineer
(Supervision, Notice, Instruction,
The roles of the Engineer can be classified into three categories in administration of construction
contracts.
(1) Employers agent
The Engineer has three main functions in the administration of FIDIC Red Book based
construction contracts:Production of detailed design drawings under Sub-clauses 6 and 7
Issuance of instructions for variation of the works under Sub-clause 51
Review of plans and drawings submitted by the Contractor under Sub-clause 7.2
Carrying out project management services including time and cost management,
quality control, testing and inspection, safety and environmental management under
various Sub-clauses especially 36-39, 49 and 50
(2) Certifier
The Engineer issues various certificates certifying the quality of the Contractors
performance and payment therefor at the Engineer discretion. The Engineers certificates
have a strong binding effect on both the Employer and the Contractor.
Taking-over certificate under Sub-clause 48.1
Certification of work completion date under Sub-clause 62.1
Interim payment certificate under Sub-clause 60.2
Defect liability certificate under Sub-clause 62.1
Final payment certificate under Sub-clause 60.8
(3) Decision maker in claim and dispute settlement
The Contractor is entitled to submit claims, as set out in the FIDIC Red Book, to the
Engineer if the Contractor encounters events which are unforeseeable at the time of bidding
or are deviations from the contract provisions. The Engineer will evaluate such claims and
give his determination to the Employer and Contractor.
Engineers decision a dispute arises and such dispute can be referred to the Engineer for his
decision under Sub-clause 673.
The Engineer therefore has three distinct and different roles:1) As Employers agent,
2) As certifier, and
3) As decision maker in claim and dispute settlement
In carrying out the last two roles the Engineer is obliged to remain independent and to act
impartially as described in Sub-clause 2.64.
2.6 Engineer to Act Impartially
Wherever, under the Contract, the Engineer is required to exercise his discretion by:
(a)
3 Under FIDIC Red Book 1999, a dispute shall be referred to Dispute Adjudication Board (DAB) in accordance with Sub-clause
20.2.
4 Under FIDIC Red Book 1999, the Engineer shall make his determination fairly in accordance with Sub-clause 3.5.
(b)
(c)
determining value, or
(d)
otherwise taking action which may affect the rights and obligations of the Employer
or the Contractor
he shall exercise such discretion impartially within the terms of the Contract and having
regard to all the circumstances. Any such decision, opinion, consent, expression of
satisfaction, or approval, determination of value or action may be opened up, reviewed or
revised as provided in Clause 67.
It is usual to appoint consulting engineers as the Engineer under the contract with the Employer
in JBIC ODA loan projects.
nature and the limit to delegation of authority to the consultant, as well as he scope and the
nature of the responsibilities which the consultant is to assume shall be clearly defined in the
contract between the Borrower and the consultant.
3) Claim and Dispute Settlement Procedure
Construction work is susceptible to many external influences such as variable subsurface and,
metrological conditions as well as social, economic and environmental factors.
It is impossible
to eliminate all uncertainties from construction work and unforeseen events are likely to occur
during any lengthy construction period.
Under FIDIC Red Book, the Contractor has an entitlement to extensions of time for completion
of the work if he suffers delay from specified events and payment of qualifying additional cost
he incurs as a result of such events.
The payment to the Contractor is based on the actual quantities of work done at the unit prices
set out in the contract Bill of Quantities.
are provisional estimates of the work to be done. The actual work quantities are measured by the
Engineer in the presence of the Contractor. The Engineer certifies interim payment amounts,
usually monthly on the basis of the measurement of the work carried out during the relevant
period.
There are three potential factors which make any contract one sided as follows:(1)
(2)
(3)
All three factors can be introduced in the preparation of Conditions of Particular Application and
result in an enhanced risk to the Contractor.
Examining each of these factors in turn:1) Limitation of Contractors right
The entitlement to claim (if an unforeseeable event occurs, or when there is a deviation from the
contract provision not attributable to the Contractor) is one of the most important contractual
rights given to the Contractor.
Event
1
2
3
4
5
Sub-clause
Add.
Cost
*1
EoT*2
Process*3
6.4
12.2
17.1
20.3
27.1
etc.
31.2
36.5
38.2
40.2
42.2
49.3
12
50.1
13
Valuation of Variation
52.1
14
52.3
15
Delayed payment
60.10
16
65.3
65.5
18
69.4
19
70.1
20
Change to legislation
70.2
6
7
8
9
10
11
17
Notes:
*1 : Additional Cost
*2 : Extension of Time
*3 : The Engineer is central to the decision making process to determine the Contractors
entitlement to an extensions time and additional cost. The determination and analysis
is carried out in three categories Type A, B, and C as follows:Type A:
Type B:
Type C:
therefore
6. to pay the Contractor according to Sub-clause 60.10, etc.
7. to be responsible for the Employers risk items under Sub-clause 20.3, 20.4 and 21.3
8. to settle disputes amicably under Sub-clause 67.2
If any of the above items are excluded entirely or partially from the Employers obligations or if
such responsibilities are in all circumstances or even in certain specified circumstances
transferred to the Contractor then the Contractors contractual responsibilities would be
considered to be increased unreasonably.
3) Restriction of the Engineers authority
The Engineer is required to exercise his authority impartially in giving approval, consent,
certification and determination as described in Chapter 2.
Similarly, the Engineers authority may be diminished if words such as subject to prior approval
of the Employer are inserted in the independent clauses as listed in Chapter 3-1, in which the
Engineers authority is described.
Excessive use of Employers prior approval as a precondition for the exercise of the Engineers
authority may tend to bias the Engineers independent decision making ability and thereby
increase the one sided tendency of a contract.
As described in section 3-1) above, the Engineer shall make determinations about alleged claims
after due consultation with the Employer and the Contractor.
Employers views can be deemed to have been considered in the decision making process
undertaken by the Engineer.
4. Commentary on Checklist
To draft Conditions of Contract in accordance with FIDIC Red Book's fundamental
concepts and at the same time to avoid a one sided contract to be unreasonably
advantageous to the drafting party as listed above, the following commentary is provided
for to assist in the understanding and intention of the check list.
Check Point
FIDIC Clause
01
Whole
<Interpretation>
JBIC recommends that bidding documents are prepared based on Sample Bidding
Documents under JBIC ODA Loans (Civil Works) Nov.1999 (the JBIC Sample
Bidding Documents). The JBIC Sample Bidding Documents are based on FIDIC Red
Book 1987 (FIDIC Red Book) as the de facto standard for international civil
construction contracts. FIDIC Red Book is considered to be a fair balance of risk
between the Employer and the Contractor.
It is strongly recommended that bidding documents are prepared in line with the JBIC
Sample Bidding Documents. If local standard bidding documents are used instead of the
JBIC Sample Bidding Documents, the following problems have been encountered:
Examination of the specially drafted conditions of contract takes a great deal of
time as the clause numbers may not be consistent.
The provisions may deviate from usual international standard contractual
practice.
The contract document may not be complete.
Check Point
FIDIC Clause
02
Whole All
<Interpretation>
FIDIC Red Book consists of two parts; Part I Conditions of Contract, and Part II
Conditions of Particular Application. Part II is prepared:
10
To provide the necessary details left blank in Part I (for example clauses: 1.1,
2.1, 5.1, 14.1, 14.3, 68.2, etc.),
To provide information specific to the project, specific to the region and specific
to the country where the project is to be carried out, and
To provide information on terms required or recommended by the financing
bank (for example JBIC).
The Part I provisions have been improved through use on many projects and its
provisions reflect a standard policy that has a high degree of professionalism. Great care
is also necessary to coordinate Part I and Part II. Any rewriting may destroy the entire
balance of the provisions and introduce referencing errors. For example when Clause
20.4 "Employer's Risk" is changed, it is possible to create inconsistency with Clause
65.2 "Special Risks". Completion and checking the consistency of Part I and Part II
should only be undertaken by a specialist with the following necessary experience:
(1)
(2)
(3)
(4)
(5)
Check Point
FIDIC Clause
03
Whole
<Interpretation>
One of the main features of the FIDIC Red Book is that it provides for defined
decisions, and for the contract administration (described in Chapter 2) to be undertaken
fairly, by an independent engineer.
Some execution agencies in developing countries acting as Employers have a tradition
of providing an employee or related organisation to serve as the Engineer. In some other
countries the Employer also holds the post of the Engineer, and the Engineer then
appoints an independent consultant as the Engineers Representative. Even in this
situation, the Engineers Representative may face difficulty in remaining impartial,
unless a great deal of the power and authority of the Engineer is delegated completely to
him. Where it is usual that execution agencies are both the Employer and the Engineer it
11
is highly recommended that this procedure be changed and that such execution agencies
appoint an independent consultant to maintain the Engineers impartiality. Independence
of the Engineer is an integral part of the FIDIC Red Book philosophy.
Check Point
FIDIC Clause
04
Whole
<Interpretation>
The Design-Bid-Build method is the assumed method of executing any project under the
FIDIC
ed Book. The Employer designs the permanent works, and the bidding is done
based on that design. The Employer assumes the liability for defective design (for
example under clauses: 6.1, 6.4, 7.1, 7.2, and 8.1).
It would be a fundamental deviation from the JBIC Sample Bidding Documents and the
FIDIC Red Book to impose liability on the Contractor for defective design and
additional cost for construction due to the modified design. If the Design-Bid-Build
method is used then such text change should be avoided as it increases the Contractor's
risks too greatly.
Check Point
05
FIDIC Clause
2.1
<Interpretation>
Another feature of the FIDIC Red Book is that the Engineer is required to be impartial
in administering the contract as described in Clause 2.6 and Chapter 2. Clause 2.1(b)
specifies that if any Engineer's decision to approve, prove, determine or decide is subject
to the acquisition of specific prior approval from the Employer then such decisions shall
be set out in FIDIC Red Book Part II.
It is preferable to minimize the number of matters which need the prior approval of the
Employer. This encourages the Engineer to make impartial judgments in line with the
basic philosophy of the FIDIC Red Book. If there are many matters which need the prior
approval of the Employer then there is the possibility that the Employer's view will
excessively be reflected when the Engineer's exercises any discretion. Similarly when
the text of FIDIC Red Book Part I and II is changed in this fundamental issue then
12
FIDIC Red Book clause 1.5 specifies that any consent, approval, certificate or
determination shall not unreasonably be withheld or delayed. If the Employer's prior
approval is required then the Contractor may consider such approval procedures
represent an unjustifiable delay.
The FIDIC Guidelines for Preparation of Part II clauses do not indicate which
discretions should be subject to approval. To consider the circumstances under which
restraints may be placed on the Engineers authority it would be necessary to take into
account the factors specific to the country in which the works are to be carried out. The
JBIC Sample Bidding Documents recommend that the following five situations should
be subject to prior approval from the Employer:(a)
(b)
(c)
(d)
Check Point
06
FIDIC Clause
2.6
<Interpretation>
As stated in Checkpoint 5 the FIDIC Red Book imposes on the Engineer an obligation
to make impartial decisions when he has to exercise a discretion. From a broader point
of view when any Engineer follows the FIDIC Red Book requirements faithfully then
13
Check Point
07
FIDIC Clause
5.1
<Interpretation>
The JBIC Sample Bidding Documents recommend that English be nominated to be a
language of the Contract.
If the Conditions of Contract are made in two languages (e.g. English, French, or
Spanish plus language of the country where the Works are to be carried out or language
of the Employer's country) it is advisable to avoid specifying languages other than
English, French, and Spanish as the ruling language for interpretation in the event of
contradictions. This is advisable as all the stake holders in the Contract (the Employer,
the Contractor, the Engineer, and JBIC) can regard English, French, and Spanish as
neutral.
Check Point
08
FIDIC Clause
5.2
<Interpretation>
The priority of documents forming the contract recommended in the JBIC Sample
Bidding Documents is as follows:(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
Contract amendments such as "The document which describes the content in detail shall
be given priority over a more general document." should be avoided. Such provisions if
included regardless of the definition of priority, create uncertainty.
Additional provisions dealing with the priority of documents should be drafted carefully
so as not themselves, to create discrepancies and contradictions in the interpretation of
the priority provisions whether the additional provisions are in the Contract Agreement,
the Conditions, or the Letter of Acceptance.
Check Point
09
FIDIC Clause
6.4
<Interpretation>
Under the FIDIC Red Book, the Engineer has a duty to issue construction drawings at
the times set out in the construction time schedule submitted by the Contractor under
Clause 14.1. The Contractor then prepares detailed drawings based on the construction
drawings. The lead time for preparation of those drawings by the Contractor should be
agreed at the time of the Contract.
The Contractor suffers delay and / or incurs cost for waiting time in preparation of shop
drawings and / or a delay in the Works arises from delay by the Engineer in issuing the
construction drawings. Such delay and / or incurred cost are risks that the Contractor
cannot manage and should not be asked to take responsibility for.
As a matter of fairness to the Contractor it is necessary to avoid text changes which
restrict the Contractors right to claim for extensions of time and the additional cost
arising from delayed issue of drawings and instructions.
Check Point
10
FIDIC Clause
8.1
<Interpretation>
The JBIC Sample Bidding Documents recommend that the provision the Contractor
shall promptly notify the Employer and the Engineer of any error, omission, fault or
15
Check Point
FIDIC Clause
11
10.2
<Interpretation>
FIDIC Red Book Clause 62.1 provides for the validity of the performance security to
expire on the issuance of the Defects Liability Certificate. The performance security
document shall be returned to the Contractor within 14 days of the issuance of the
Defects Liability Certificate.
FIDIC Red Book Clause 61.1 provides that the Contract shall only be regarded as
complete upon issuance of the Defects Liability Certificate in accordance with Clause
62.1. The Contractors contractual obligations are at an end upon the issuance of this
Certificate. Any text change that excessively expands the Contractor's obligation by
requesting a performance security to remain valid beyond that date keeps the
Contractors obligation alive unfairly.
Check Point
FIDIC Clause
12
11.1
<Interpretation>
Any text change or additional provision which makes the Contractor assume all the
responsibilities for the inaccuracy and / or insufficiency in information given by the
Employer deviates from the FIDIC Red Book and imposes an excessive and unfair
responsibility on the Contractor.
In case of inaccuracy of the site data, a claim can be submitted by the Contractor under
Clause 12.2. Even if there is a text change attempting to limit this right the Employer
may still be held responsible as the drafter of the tender / contract documents. If such a
claim develops into arbitration, an award could go against the Employer. An arbitration
16
tribunal could decide that a bidder had insufficient time to investigate and verify the site
data provided by the Employer and it would have been necessary and reasonable for the
Contractor to have relied on the accuracy of the site data to calculate the tender price.
The JBIC Sample Bidding Documents recommend adding a new Clause 11.2. This new
clause allows the bidders to access data provided elsewhere in the Contract. This
provision is helpful as it permits the bidders to understand site conditions in more detail.
The critical factor is to select a proper contractor at an appropriate price by providing a
thorough understanding of the site situation at the time of the tender.
Check Point
FIDIC Clause
13
12.2
<Interpretation>
No Contractor can manage risks arising from physical obstructions or conditions which
an experienced contractor could not reasonably have foreseen. Imposing a risk on a
Contractor which he cannot manage may lead the bid evaluator to select a bidder
without the maturity and / or experience to reflect such a risk in the price. In these
circumstances there is a high possibility of spoiling another very suitable bidder who has
properly reflected the risk in his tender price.
Any text change which restricts or limits the Contractors right to claim for extension of
time and additional cost shall be avoided to prevent from disadvantage for both the
Employer and the Contractor.
If there is a text change to the effect that the Engineer requires the Employer's prior
permission to exercise his discretion in relation to extension of time and additional cost,
the Engineers fair decision may be affected greatly by the Employer's views. Any such
text change should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
14
14.3
<Interpretation>
FIDIC Red Book Clause 60 sets out the payment procedure which is invariably to be
payment according to work progress. However, payment by some executing agencies /
Employers is limited by an annual government budget. This limit is stipulated in the
Contract. In such cases payment can only be made within the limit of the budget
regardless of the amount due according to the FIDIC Red Book work progress
procedures.
The construction time schedule is prepared by the Contractor in accordance with their
own construction methods. A cash flow plan is established referring to this construction
time schedule. Any text change by which the Employer limits the Contractors cash flow
plan should not be made.
Check Point
FIDIC Clause
15
17.1
<Interpretation>
Any text change to make the Contractor assume responsibility for the accuracy of the
original points, lines and levels given to the Contractor by the Engineer changes the
procedure stipulated in FIDIC Red Book Clause 17.1. Such a change imposes too much
risk on the Contractor and any such text changes should be avoided as being unfair and
against FIDIC Red Book principles.
Check Point
FIDIC Clause
16
20.3 & Loss or Damage Due to Employer Risks and other related
others issues
<Interpretation>
FIDIC Red Book Clause 21.2 provides that insurance shall be in the joint names of the
Contractor and the Employer. Such insurance shall include all the Employers risks
except the Special Risks stipulated in Clause 65. Any loss or damage not insured or not
recovered from the insurers, pursuant to Clause 21.3, shall be borne by the Employer or
the Contractor in accordance with their respective responsibility set out under the FIDIC
Red Book or at law. Any amount not recovered from the insurers is described
18
as Excess and/or "Deductibles. Any insurable event not covered by the policy for any
reasons is described as an "Exclusion.
Any text changes which transfers the Employers risks to the Contractor increases the
Contractors obligation and would mean that the Contractor is required to bear any loss
and or damage not recovered from the insurer.
If a text change is made to delete an exclusion from FIDIC Red Book Clause 21.4 and
such event occurs then the Contractors responsibility will have been unreasonably
enlarged. It is necessary to avoid such text changes that move those normally excluded
risks to the Contractor. Those risks cannot be managed and are not insurable at normal
premiums.
Check Point
FIDIC Clause
17
27.1
<Interpretation>
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise Engineer's discretion in relation to extension of time and
additional cost caused by removal of obstruction by fossils, the Engineers ability to
make a fair decision may be affected by the Employer's views. Any such text changes
should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
18
30.3
<Interpretation>
Any text change to FIDIC Clause 30.3 which imposes the Employers liability to
compensate for damage to roads and bridges on the Contractor regardless of the law and
the regulations, forces the Contractor to bear a risk that he cannot manage. Any such text
changes should be avoided as being against FIDIC Red Book principles and unfair.
19
Check Point
FIDIC Clause
19
31.2
<Interpretation>
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to additional cost, the Engineers fair
decision may be affected greatly by the Employer's views. Any such text changes should
be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
20
36.5
<Interpretation>
Any text change to FIDIC Red Book which removes the Contractors entitlement to a
claim for extension of time and additional cost for the tests not provided for in the
Contract may lead to restriction on the Contractors rights. Such tests are unplanned
work and an extension of time would be unavoidable if this work is on the critical path.
Further, such cost could not have been included in the Contract Price. It is necessary to
avoid any such text change that imputes such risk that cannot be managed.
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to extension of time and additional cost,
the Engineers fair decision may be affected greatly by the Employer's views. Any such
text changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
21
38.2
<Interpretation>
Any text change to FIDIC Red Book Clause 38.2 which deletes the Contractors right to
an additional cost for making openings of any part of the Works covered up in proper
manner would impose an unmanageable risk to the Contractor.
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to additional cost, the Engineers fair
decision may be affected greatly by the Employer's views.
Both such text changes should be avoided as being against FIDIC Red Book principles
and unfair.
Check Point
FIDIC Clause
22
40.2
<Interpretation>
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to extension of time and additional cost,
the Engineers fair decision may be affected greatly by the Employer's intention. Any
such text changes should be avoided as being against FIDIC Red Book principles and
unfair.
Check Point
FIDIC Clause
23
41.1
<Interpretation>
The issuance date of the Notice to Proceed marks the commencement of the contractual
construction period. The FIDIC Red Book requires the Contractor to submit a
programme under Clause 14.1, and Cash Flow forecast under Clause 14.3 within the
number of days stipulated in Part II such period counting from the date of the Letter of
Acceptance. The Contractor is also required to submit the Performance Security under
Clause 10.1, and a breakdown of the Lump Sum prices under Clause 57.2.
A time limit for the issuance of the Notice to Proceed is usually stipulated in the
21
Appendix to Tender in relation to the date of issuance of the Letter of Acceptance by the
Employer. The Contractor is not able to schedule the Works when the Notice to Proceed
and Letter of Acceptance are delayed. Therefore if there is a text change which deletes
the time limit for issue of the Notice to Proceed from the date of the Letter of
Acceptance the Contractor may be forced to stand in readiness for a long time. The
Contractor would also be forced to start contractual activities, such as the preparation of
the Performance security under Clause 10.1, and preparation of the Lump Sum prices
breakdown of under Clause 57.2 in order to submit these within 28 days from the date of
the Letter of Acceptance. This would be so even if the Notice to Proceed had not been
issued by the Engineer after 28 days from the Letter of Acceptance. Such a text change
creates a risk that cannot be managed by the Contractor and should not be incorporated.
An Employer may have many internal problems to overcome to commence the project
such as land compensation, arrangement of budget and staff arrangement. It may be
difficult to predict how long these tasks will take to solve and that may be the reason to
make a text change so as not to stipulate a time limit in the Appendix. However,
managing these various procedures is not the Contractors problem but is the Employer's
responsibility. Managing these procedures is a prerequisite for the smooth execution of
construction works.
Check Point
FIDIC Clause
24
42.2
<Interpretation>
Any delay in giving possession of, and access to, the site is necessarily the responsibility
of the Employer. Such matters cannot be managed by any Contractor. If a delay to either
of these activities actually affects the critical path of the Works, an extension of time is
unavoidable. Text changes to impose responsibility for these activities on the Contractor
therefore should be avoided.
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion in relation to extension of time and additional cost, the
Engineers fair decision may be affected greatly by the Employer's views. Any such text
22
changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
25
44.1
<Interpretation>
Any amendment which changes the conditions for, or deletes entirely, any of the five
reasons for extensions of time and of the Contractors right to claim for extension of
time should be avoided. Such an amendment attempts to impose on the Contractor risks
that he cannot manage. Any such text changes should be avoided as being against FIDIC
Red Book principles and unfair.
Check Point
FIDIC Clause
26
47.1
<Interpretation>
The Guidelines for Procurement under JBIC ODA Loans published January 2005
recommend liquidated damage at a rate of 0.1% per day of the Contract price or 0.5 %
per week of the Contract Price. It also recommends an upper limit in the range of
between 5% and 10% of the Contract Price.
Any text change which deletes the upper limit of liquidated damages and has the
possibility of deducting extremely large amounts of money may be judged as a penalty
if a dispute proceeds to arbitration. Any decision that liquidated damages are a penalty
causes there to be a doubt on the effectiveness of the whole liquidated damages
provision.
Contractors may include a contingency in their bid price to cover the risk of extremely
large amounts of liquidated damages set out in the bid documents. If the Works are not
delayed then the contingency is an unnecessary expense for the Employer. There is also
the possibility that capable contractors will be deterred from bidding as described in
Checkpoint 12. Such text changes have no advantage for the Employer or the
Contractor.
23
Check Point
FIDIC Clause
27
48.1
<Interpretation>
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to issue of a Taking-Over Certificate, the
Engineers fair decision may be affected greatly by the Employer's intention. Any such
text changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
28
49.1
<Interpretation>
The Defects Liability Period set out in the FIDIC Red Book Appendix to Tender is
usually one year for civil works. There is also an implication that the Engineer's
monitoring of the Works as a third party during the construction process functions to
ensure that the economic life of the civil works and structure will generally be durable in
the range of between 30 and 50 years.
Any text change which imposes an excessive risk on the Contractor by unreasonably
extending the defects liability period may increase the bid price and make the project
more expensive for the Employer. There is also the possibility that capable contractors
would be deterred from bidding as described in Checkpoint 12. Such text changes have
no advantage for the Employer or the Contractor.
Check Point
FIDIC Clause
29
49.2
<Interpretation>
The Contractor cannot control natural wear and tear caused by operation of facilities
during the Defects Liability Period, even if such a text change is made to impose such a
responsibility on the Contractor. Wear and tear of facilities and structures is natural
when they are put into use under normal operating conditions.
To impose such responsibility on the Contractor is an unfair expansion of the
Contractors obligations and may increase the bid price and expense to the Employer.
24
There is also the possibility that capable contractors will be deterred from bidding as
described in Checkpoint 12. Such text changes have no advantage for the Employer or
the Contractor.
Check Point
FIDIC Clause
30
50.1
<Interpretation>
If there is a text change which requires the Engineer to get the Employer's prior
permission to exercise his discretion in relation to additional cost, the Engineers fair
decision may be affected greatly by the Employer's view. Any such text changes should
be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
31
51.1
<Interpretation>
FIDIC Red Book Clause 51.1(b) provides that "to omit any such work" is a part of a
variation. However, the right of the Employer is conditional on the fact that such
omission shall not be for the purpose of having that work carried out by the Employer or
by another contractor. It is necessary to avoid any text change which deletes such
provision because this is a violation of the right of the Contractor to carry out the
contractual work.
Check Point
FIDIC Clause
32
52.3
<Interpretation>
25
The basis of this clause is to balance the Employer's and the Contractor's risk for
increases or decreases of the Effective Contract Price. To accomplish this balance of risk
it is necessary to allow for the adjustment of the Effective Contract Price if such
increase or decrease of variations adversely the affects the proportion and therefore
recovery of indirect construction costs.
The Effective Contract Price shall be adjusted in relation to the amount of contract
variations. Any text change which specifies an unreasonably high percentage for
variations before adjustment is made should be avoided.
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion in relation to increase or decrease amount of the Effective
Contract Price, the Engineers fair decision may be affected greatly by the Employer's
intention. Any such text changes should be avoided as being against FIDIC Red Book
principles and unfair.
Check Point
FIDIC Clause
33
53.1
<Interpretation>
The basic philosophy behind a claim notice period being set as 28 days is that the
Employer and the Contractor are able, in good time, to identify which contemporary
records will be required to substantiate the claim and to take any action that may be
appropriate. Clearly memory alone is not a good basis as it becomes fainter as time goes
by. There is also a common sense view that a 28 days period is appropriate for the
Contractor to recognize that an event may developed into a claim. A text change to
shorten this 28 days period should be avoided because of possible unfair restriction of
the Contractors rights.
The FIDIC Red Book Clause 53.3 requires the Contractor to send to the Engineer, with
an explanation of the grounds upon which the claim is based, with an account giving
detailed particulars of the amount claimed. According to the Contract, the assessed value
of the claim will be paid to the Contractor when the Engineer has determined that the
amount claimed was reasonable in the light of the facts and rights under the Contract.
26
Check Point
FIDIC Clause
34
54.3
<Interpretation>
FIDIC Red Book Clause 54.3 sets out the range of support to be offered by the
Employer to the Contractor regarding customs clearance. The clause does not clearly
specify the details of such support. The Employer must therefore describe in Part II of
the Conditions of Contract, the details of the Employer's support. What support the
Employer provides actually varies in different countries and projects.
Any text change which deletes such support from the Employer may not only expand
the Contractors obligation but also obstruct execution of the Project.
Customs departments usually require endorsement by the Employer for re-export of the
Contractors construction equipment after the construction in accordance with FIDIC
Red Book Clauses 33.1 and 54.1.
Check Point
FIDIC Clause
35
59.2
<Interpretation>
Under FIDIC Red Book Clause 59.2(a) all nominated subcontractors should undertake
towards the Contractor such obligations and liability that will enable the Contractor to
discharge his own obligations and liabilities towards the Employer.
Any text change which prevents the Contractor from rejecting any subcontractor
selected by the Employer who will not undertake such responsibility shall be avoided
because it prejudices the Contractor's chance of keeping the quality of work and time
period stipulated in the Contract.
Check Point
FIDIC Clause
36
59.4
Does the Contractor have the right to set out in the Contract
his attendances and profit on Nominated Subcontractors?
Payments to Nominated Subcontractors
<Interpretation>
The Contractor shall submit his method statement, applications for approval of
construction materials, and selection of subcontractors. It is a right of the Contractor to
27
receive profit and payment for services which he provides to the subcontractors. The
rate of profit and payment for charges must be at the Contractors discretion.
The Tender document must include a format sheet to include the appropriate rate of
profit and payment for charges in the build up of the Contract Price. This format sheet
shall provide separate columns for the rates for his own work and subcontracted work as
the Contractors management input is different in each case.
Therefore FIDIC Red Book Clause 59.4(c) should have no text change to fix the rates to
a single rate to avoid violation of the Contractors right.
Check Point
FIDIC Clause
37
60.1
Is the party to pay for the bank commissions and fees etc.
clearly defined in the contract?
Monthly Statements
<Interpretation>
The JBIC Sample Bidding Document recommends a clause for Certificates and
Payment. The numbering system of this recommended clause is different from FIDIC
Red Book but the effect of the clause is the same.
If the Employer intends to pay the bank for opening letters of credit, making remittance
and other bank charges including those incurred by the Contractor then it is necessary to
clearly specify this in the Contract.
The Contractor can request payment for these bank fees under Clause 60.1(e) and
include them as any other sum to which the Contractor may be entitled under the
Contract in both the FIDIC Red Book and the JBIC Sample Bidding Documents.
Check Point
FIDIC Clause
38
60.2
<Interpretation>
Both the FIDIC Red Book and the JBIC Sample Bidding Documents specify the time
limit for the Employer to honour an Engineers certificate for payment as 28 days.
Any text change to extend the 28 day honouring period will extend the time limit for
payment by the Employer and will probably increase the Contract Price. There is also
the possibility of deterring capable contractors from bidding as stipulated in Checkpoint
28
12. Therefore such text changes should be avoided from the perspective of economic
rationality.
Check Point
FIDIC Clause
39
-
<Interpretation>
The provision of an advance payment allows the Contractor to pay for preparation of the
site and temporary works until receipt of the first interim payment.
The advance is amortised by the Employer deducting a defined amount from an
otherwise due interim payment. The JBIC Sample Bidding Document recommends that
repayment should be calculated so as to obtain full recovery of the advance payment by
the time 80% of the Contract Price has been certified for payment.
Any text change to make the Contractor repay the advance payment much before
interim payments have reached 80% of the Contract Price should be avoided as they
may undermine the original purpose of the advance payment.
Check Point
FIDIC Clause
40
60.3
<Interpretation>
FIDIC Red Book Clause 60.3 provides that the first half of the retention money shall be
returned to the Contractor upon the issue of the Taking-Over Certificate with respect to
the whole of the Works. This recognises the fact that the Employers risk from the
default by the Contractor is reduced at this time. The second half of the retention money
is still held by the Employer to cope with the risk of the Contractor not remedying
defects in workmanship. For this reason the second half of the retention money is
released only at the end of the defects liability period at the same time as the
performance security is also returned to the Contractor.
Any text change to request the Contractor to submit a bank bond in exchange for the
return of the first half of the retention money may impose on the Contractor an
excessive obligation beyond the FIDIC Red Book model. Any such text changes should
be avoided as being against FIDIC Red Book principles and unfair.
29
Check Point
FIDIC Clause
41
60.10
<Interpretation>
The JBIC Sample Bidding Documents recommend 56 days as the time for payment in
FIDIC Red Book Clause 60.8..
Any text change which allows the Employer to delay payment beyond the standard time
limit of 56 days and / or deletes the obligation to pay interest for delayed payment may
push up the Contract Price. Such a text change could deter capable contractors from
submitting a bid as stipulated in Checkpoint 12 and should be avoided from the point of
view of economic rationale.
It is important that the payment obligation of the Employer should be clearly specified
in FIDIC Red Book Clause 60.10. The actual time of payment by the Employer could
vary according to the particular contract definition. Payment could be the time of
delivery by the Employer of necessary documents to the Contractor, or delivery to JBIC,
or at the time of actual payment into the Contractors bank account. The FIDIC Red
Book Clause 60.10 should clearly specify the time of payment to define the starting date
for calculation of interest.
Check Point
FIDIC Clause
42
65.3
<Interpretation>
If there is a text change that the Engineer requires the Employer's prior permission to
exercise his discretion on cost related to damage caused by Special Risks, the Engineers
fair decision may be affected greatly by the Employer's intention. Any such text changes
should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
43
FIDIC Clause
65.5
<Interpretation>
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion on the amount of increased cost arising from Special Risks, the
Engineers fair decision may be affected greatly by the Employer's view. Any such text
changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FI DIC Clause
44
65.8
<Interpretation>
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion in relation to additional cost, the Engineers fair decision may
be affected greatly by the Employer's view. Any such text changes should be avoided as
being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
45
67.1
<Interpretation>
Chapter 11 of the JBIC Sample Bidding Documents provides for the use of a Dispute
Adjudication Board (DAB). The DAB comprises three (3) members in the case of a
project in which the contract price exceeds 42 million US$ (equivalent to 5.0 billion
Japanese Yen) as the optional method for the settlement of disputes. Under the FIDIC
Red Book Clause 67.1 this option is included at the discretion of the Employer as a
method of resolving differences over any Engineers decision.
There have been projects where the establishment of a DAB was suspended because of
the large sums of money to be paid for the DAB by both the Employer and the
Contractor. Even if the sharing of such cost was stipulated in the FIDIC Red Book the
cost of a DAB can be exceptionally high especially if the adjudicators come from third
countries. The Employer should have understood that such expenses are inevitable when
the DAB procedure was selected.
31
Check Point
FIDIC Clause
46
67.3
<Interpretation>
There should be proper consideration given to the selection of the dispute settlement
procedure incorporated in an international contract especially in the case of the
nomination of an arbitration rules / organization which is based in the country of the
Employer and (usually) the country where the Works are to be carried out. The general
rule should be to appoint a truly international and neutral rules / organization such as
International Chamber of Commerce (ICC).
Check Point
FIDIC Clause
47
69.1
<Interpretation>
The FIDIC Red Book Clause 60.10 (a) provides a period of 28 days within which
payment should be made by the Employer for interim certificates and 56 days for the
Final Certificate. The FIDIC Red Book Clause 69.1 also provides a period of 14 days
for the effectiveness of a notice of termination for Employer's failure to pay as required.
Proper consideration should be give to these periods taking into account the
implementation method and the context of the country where the Works are to be carried
out. The specification of these time limits shall be subject to sufficient investigation
especially when the executing agency has no authority to make a decision on the issue
related to this clause and is required to consult with other government authorities.
It is necessary to investigate all the circumstances surrounding the executing agency at
the same time as considering the rights of Contractor stated and implied in the Contract.
Check Point
48
FIDIC Clause
69.4
<Interpretation>
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion in relation to extension of time and additional cost, the
Engineers fair decision may be affected greatly by the Employer's intention. Any such
text changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
49
70.1
<Interpretation>
The JBIC Sample Bidding Documents recommend alternative provisions to FIDIC Red
Book Clauses 70.1 to 70.7 in Part II of the Conditions of the Contract.
It is necessary to avoid any text change to restrict the Contractors right which deletes
this clause, or specifies unreasonable formula, or automatically cuts a certain percentage
of price escalation, or limits adjustment to the cases of drastic movement in price.
Check Point
FIDIC Clause
50
70.2
<Interpretation>
The FIDIC Red Book Contract stipulates that the Contractor is entitled to additional
costs incurred due to changes in legislation and any text changes that limits the
Contractor's right to price adjustment only in circumstance when the additional amount
would exceed a certain limit are unfair.
The limits of price adjustment under Clause 70.1 can be ambiguous as described in the
Commentary on Clause 70.1 above. A description which clarifies adjustment to be made
under Clause 70.1 is required in a particular project.
If there is a text change that requires the Engineer to get the Employer's prior permission
to exercise his discretion on increase or decrease cost caused by changes in legislation,
33
the Engineers fair decision may be affected greatly by the Employer's view. Any such
text changes should be avoided as being against FIDIC Red Book principles and unfair.
Check Point
FIDIC Clause
51
72.2
<Interpretation>
When the Employer specifies his obligation to pay, in more than one currency, an
unbridgeable gap in the Contractor's actual cash flow may be caused if the text changes
fix that ratio. There is also the possibility that the bid price will be increased by the
contractor making provisions for this exchange risk and the restriction on the recovery
for Clause 70.1 price adjustment. Any such text changes should be avoided as being
against FIDIC Red Book principles and unfair.
34
Appendices
Appendix -1
67.1
67.2
67.1
67.2
53.1 Cost
Within 28 days
Reference of
dispute to
DAB*1
Reference of
dispute to
Engineer
44.2 Time
67.1
Within 84
days
53.3 Cost
Within 28 days
DABs
Decision*1
Within 84
days
Notice of ground and details of Claim
Engineers
Decision
44.2 Time
Yes
Agreement to Engineers
or DABs Decision
Settlement
of Dispute
No
67.1
Notice to commence
Arbitration
Agreement to
the Determination
Yes
Settlement
Within 70 days
of Claim
67.2
Attempt at Amicable
No
Settlement
Within 56 days
Occurrence of Dispute
Yes
Amicable Settlement
of Dispute
No
Arbitration
67.3
AP-1
Settlement
J BI C
JAPAN
BANK FOR
INTERN ATIONAL
COOPERATION
JapanBankforInternationalCooperation
Head Office
4-1 Ohtemachi 1-chome, Chiyoda-ku,
Tokyo 100-8144, Japan
Telephone : Tokyo 81- 3 - 5 2 1 8 - 9 6 1 1
Facsimile: Tokyo 81 - 3 - 5 2 1 8 - 9 6 4 0
URL: http://www.jbic.go.jp
E-mail: pdds@jbic.go.jp