Survey No 166/1,2,3, 171/1, 172,167,168, Village : Padana Gandhidham, Dist. Kutch
Hazard & Operability Study (FOR DESUR DEPOT EXISTING FACILITIES AND PROPOSED FACILITIES)
PREPARED BY
VAIBHU SAFETY CONSULTANTS FF-11, Akshat Complex, Nr. Reliance Petrol Pump, High Tension Road, Subhanpura, Vadodara-390 023 Phone: 9825756467/9427838021 (M) Ph : 0265-2395798
Prepared By M/s. Kutch Chemical Industries Limited Page : 2 HSE Department Rev. : 00
ACKNOWLEDGEMENT
We express our sincere thanks to management of Kutch Chemical Industries Ltd for providing unstinted support during the HAZOP Study without which the HAZOP study could not have been possible. The courtesy extended to our team is highly appreciated.
Prepared By M/s. Kutch Chemical Industries Limited Page : 3 HSE Department Rev. : 00
CERTIFICATE
We are pleased to certify that this HAZOP Study Report of Company has been conducted by us.
HAZOP STUDY is a legal requirement as per the rules 10 to 13 under Manufacture, storage and import of Hazardous chemicals rules, 2000 and environment (protection) Act, 1986.
It is obligatory of the occupier to carry out a "HAZOP Study", as required under item no. (II) (2) of the format for application of the Site Appraisal Committee and as per the Schedule 1 of the Factories Act under Section 2(CB) - Item No. 11 of the Schedule.
The Executive Summary is given in the beginning to highlight the important summary of our report and methodology of the HAZOP Study carried out.
FOR VAIBHU SAFETY CONSULTANT
Authorized Signatory
Prepared By M/s. Kutch Chemical Industries Limited Page : 4 HSE Department Rev. : 00
CONTENTS
SECTION NO.
CONTENTS
NO. OF PAGES 1 Objective and Methodology of HAZOP Study
8 1.1 Objectives 8 1.2 Scope of The Work 8 1.3 Methodology 8 2 Introduction to HAZOP
10 2.0 Hazard and Operability Study 10 3 Introduction Of the Unit
13 3.1 Introduction of the unit 13 3.2 Details of Unit 13 3.3 Google map 20 3.4 Site Plan 21 3.5 Organisation chart 22 3.6 Details of storage of Hazardous Materials in Bulk 22 3.7 Facilities / System 28 3.8 Process Flow chart 29 4 HAZOP Sheets 49
Prepared By M/s. Kutch Chemical Industries Limited Page : 5 HSE Department Rev. : 00
LIST OF TABLES
TABLE NO.
CONTENTS
Page No. Table- 4.1 Hazop Study Worksheet (Transferring of Chlorsulfonic Acid to service tank) 50 Table- 4.2 Hazop Study Worksheet (Charging of Acetanilide) 51 Table- 4.3 Hazop Study Worksheet (Reaction) 52 Table- 4.4 Hazop Study Worksheet (Dumping) 53 Table- 4.5 Hazop Study Worksheet (Reduction) 54 Table- 4.6 Hazop Study Worksheet (Condensation) 55 Table- 4.7 Hazop Study Worksheet (Esterification) 57 Table- 4.8 Hazop Study Worksheet (E. O. storage tank) 58 Table- 4.9 Hazop Study Worksheet (From outlet of storage tank to inlet of batch tank) 61 Table- 4.10 Hazop Study Worksheet (Raw material to the storage tank ( Day Tank )) 63 Table- 4.11 Hazop Study Worksheet (Reaction Process) 64 Table- 4.12 Hazop Study Worksheet (Chilling of the HCL) 65 Table- 4.13 Hazop Study Worksheet (Gas cleaning) 66 Table- 4.14 Hazop Study Worksheet (Reaction) 67 Table- 4.15 Hazop Study Worksheet (Melting of Sulfur) 68 Table- 4.16 Hazop Study Worksheet (Burning of sulfur with air) 69 Table- 4.17 Hazop Study Worksheet (Catalyst convertor) 70 Table- 4.18 Hazop Study Worksheet (Rector) 71 Table- 4.19 (Gas mixture) 72 Table- 4.20 Hazop Study Worksheet (High Boiler fractional Distillation Column) 74 Table- 4.21 Hazop Study Worksheet (Final Product Distillation Column) 75 Table- 4.22 Hazop Study Worksheet (Reaction of Chlorine) 76 Table- 4.23 Hazop Study Worksheet (Reaction) 78 Table- 4.24 Hazop Study Worksheet (Reaction) 80 Table- 4.25 Hazop Study Worksheet (Distillation) 81
Prepared By M/s. Kutch Chemical Industries Limited Page : 6 HSE Department Rev. : 00
HAZOP SUMMARY
HAZOP SUMMARY
SR. NO. OBSERVATION AREA SUMMARY 1 UTILITY SERVICES Utility is the heart of the chemical process industries. All the critical equipment shall be connected with the D. G. Set.
Company has their own captive power plant.
Overhead water tank for cooling operation shall be provided. Under worst case of GEB & DG failure cooling operation shall not be suffered. Stand by pump for cooling shall be provided . All the utilities line shall be provided with arrow indicators & content . this not only help of for better production but also help during the emergency it avoid the human error.
A system shall be devised to maintain the sufficient quantity of water in the seal pot & scrubber to prevent escape of EO gas in the atmosphere.
Common Dump tank shall be provided in the plant. The capacity of the same shall be the 1.10 times the biggest reactor in the plant.
Written check procedures are not available for the checking the leak point in Vessel & piping system. Human errors may occurs during the verbal check. Written procedures shall be developed. Periodic inspection of the Sulfur burner to be ensured.
To handle the chlorine emergency chorine kit to be ensured and maintained in tip top condition at all time.
Flange guards needs to be provided on Acid lines.
Non return Valve to be provided on pump discharge line.
Arrow indicator to be provided on pipeline.
Pump, storage tank & pipe line identification to be done.
Color code for pipelines to be provided as per IS 2379.
Periodic checking of the condenser to be followed
2 STORAGE OF CHEMICALS All the storage has been provided with the separate area. All statutory norms are followed. It should be made restricted entry. A register shall be maintained. Double Static earthing to be provided to flammable material storage tanks as well as pipelines and powder handling machines.
Electrical earthing to be checked and record to be maintained and resistance to be maintained below 1 OHMs .
Prepared By M/s. Kutch Chemical Industries Limited Page : 7 HSE Department Rev. : 00
Safety valve Pressure gauges and other safety devises to be maintained in working condition and testing and calibration to be done once in a year.
Thickness measurement to be done for all storage tanks and comparison records to be maintained.
Tank ID, content and capacity to be displayed on each tanks and reactors.
3 INSTRUMENTATION Instrumentation has to play key role in the maintenance of process parameters. All the interlocks shall be tested every month. And the records shall be maintained. All the instruments shall be calibrated before the date expires. Calibration date for safety valve, shall be displays at site only.
Functioning of Instrumentation depend on the well supply of air. Under no circumstances the air pressure shall be reduced. The DMS & H2SO4 plant are DCS operated.
E. O. flow cutoff to be provided in connection with the temperature rise in VS plant. 4 ENVIRONMENTAL The organization has taken care of environment by converting all the by product into useful product. The concept of reduce, recycle & reuse has been vigorously followed. The generation of effluents is also well controlled. 5 ADMINISTRTION Standard Operating procedures to be prepared.
Work permit procedures to be followed for the handling of hazardous chemicals. 6 GENERAL Use of Personal Protective Equipment (PPE ) are not found during the various plant operation. PPE matrix shall be defined for all the process activity.
Alarms for vacuum failure in the dehydration shall be considered.
Stand by pump for reflux system shall be provided in distillation section.
Hot oil circulation line shall be inspected at least once in a month.
Prepared By M/s. Kutch Chemical Industries Limited Page : 8 HSE Department Rev. : 00
CHAPTER I
OBJECTIVE AND METHODOLOGY OF HAZOP STUDY
1.1 Objective :
The specific objectives of the study are-
Identification and assessment of major hazards potential in the storage and handling of petroleum products inside the depot. Study of built- in- safety measures and operational safety precautions in practice. Identification and assessment of major hazards potential in the process equipment. Suggesting measures to reduce risk by reducing hazard and reducing probability.
1.2 SCOPE OF THE WORK
The principal objective of this study is to evaluate the potential hazards to the plant.
To evaluate the process safety system of plant from the safety point of view considering the structural / electrical / instrumentation aspects. To evaluate the system provided to protect fire & explosion in product pipe line and system full proof. Evaluate the maintenance & operation system of the Terminal. Evaluate provided control parameters and instrumentation. Suggest better system for safe operation & maintaining plant in a safe manner.
1.3 METHODOLOGY
Design data, built in safety systems are studied. Discussions are held with Officials. Safety related individual system is discussed with HAZOP team member.
HAZOP exercise is conducted taking into consideration of each and every equipments, storage tanks, Tank truck filling gantry, pump house, pipe lines, operating procedures,
Prepared By M/s. Kutch Chemical Industries Limited Page : 9 HSE Department Rev. : 00
built in safety system, operating parameters and existing safety measures. Thus, this study is mainly oriented towards actual risks rather than chromic risks.
Possible causes of the possible events will be derived and consequences effect of such events will be discussed and required recommendation and follow-up sheet will be generated for implementation purpose.
Prepared By M/s. Kutch Chemical Industries Limited Page : 10 HSE Department Rev. : 00
SECTION II
INTRODUCTION TO HAZOP
2.0 Hazard and Operability Studies(HAZOP)
2.1 The basic concept of HAZOP is to have an exhaustive review of the plant layout and P& ID of KCIL. HAZOP study highlights the hidden operability problems and identifies hazards, which are likely to result from the expected intention of seemingly safe components or methods of operation.
2.2 This work utilizes imagination of team members to visualize ways in which a terminal can malfunction or mal-operated. Each part of the plant is subjected to a number of questions formulated around a number of guide words which are derived from method of study technique. In effect, the guide words are used to ensure that the questions which are posed to test integrity of each part of the design to explore every conceivable way in which that design could deviate from the design intention. This usually produces a number of theoretical deviations and each deviation is then considered how it could be caused and what would be consequences.
2.3 HAZOP is a brainstorming approach, which stimulates creativity and procedure for generating ideas. Possible results of this study are :- (a) Identify and examining many types of risks. (b) Identifying non-optimum system reliability. (c) Suggestive qualitative recommendations regarding control, strategy, material properties, material releases alternative design option, operation and maintenance.
2.4 The important terms pertaining to HAZOP study are:- Intention : - The intention defines how the part is expected to operate. This can take a number of forms and can be either descriptive or diagrammatic. In many cases, it will be a flow sheet (P & ID)
Prepared By M/s. Kutch Chemical Industries Limited Page : 11 HSE Department Rev. : 00
Deviation : - These are departures from the intention which are discovered by systematically applying the guide words. Causes : - These are reasons why deviation might occur. Once a deviation has been shown to have a conceivable or realistic cause, it can be treated as meaningful. Hazards : - These are the results of the deviations Consequences : - These are the consequences, which can cause damage, injury or loss.
2.5 A list of guide words Table- 3.1 list of guide words
Guide Words Meanings Comments None Complete negation of the intention No part of the intention is achieved e.g. no flow or reverse flow. More of Quantitative increase More of any relevant physical properties than there should be e.g. higher flow (rate or total quantity) higher temperature, higher pressure higher viscosity, more heat, more reaction etc. Less of Quantitative decrease Less of any relevant physical property than there should be, e.g. Lower flow (rate or total quantity), lower temperature, lower pressure, less heat, less reaction etc. Part of Quantitative decrease Composition of system different from what it should be e.g. Change in ration of components, component missing etc. More than Qualitative increase More components present in the system that there should be e.g. extra phase present (Vapor, solid), impurities (air, water, acids, corrosion products etc.) Other than Substitution What else can happen apart from normal operation e.g. Start up, shutdown, high/low rate running, alternative operation mode, failure of plant services, maintenance, catalyst change etc.
2.6 Guidewords are applied to the design intention. The design intention informs us what the equipment is expected to do.
Prepared By M/s. Kutch Chemical Industries Limited Page : 12 HSE Department Rev. : 00
NO Yes NO 2.7 A flow chart giving HAZOP procedure is given below:-
NO
NO
Yes
Select Line Select deviation Eg. More flow Is more flow possible ? Is it hazardous or does it prevent efficient operation ? Will the operator know that there is more flow ? What change in plant or methods will prevent the deviation or make it less likely or protect against the consequences. Is the cost of change justified Agree changes. Agree who is responsible for action. Follow up to see that action has been taken. Move onto next deviation Consider other causes of more flow Consider other changes or agree to accept hazard. What change in the plant will tell him
Prepared By M/s. Kutch Chemical Industries Limited Page : 13 HSE Department Rev. : 00
SECTION III
INTRODUCTION OF THE UNIT
3.1. COMPANY INTRODUCTION
M/s. Kutch Chemical Industries Ltd., is operating a manufacturing unit of various chemicals and dye intermediates at Survey No 166/1,2,3, 171/1, 172,167,168, Village : Padana, Gandhidham, Dist. Kutch
Produce unit is classified as Major Accident Hazards unit ( MAH Installation ) based on the storage of the listed hazardous chemicals more than specified threshold quantities.(Schedule 3 under Rule 68-J of the Gujarat Factories Rules-1963 (2004).
Kutch Chemical Industries Ltd, with spot light on export market potential was founded in 2004 near the Global all weather ports of Kandla and Mundra. It consists of a well integrated chemical complex consisting of Chlorination, Nitration, Sulphonation and Dyes Intermediates products.
3.2. DETAILS OF UNITS
Sr. No. Particulars 1. Full Name & Address of Unit : Kutch chemical Industries limited Plot no- 165,166/1&3,168,171/1&172 Village:Padana, Nr.Aquagel Chemicals, Gandhidham, Dist Kutch Gujarat. 2. Telephone No. : 02836-28551-52, Fax-02836-285233 3. Month & Year of Establishment
: 10 th J une 2002 4. Full name & Address of the occupier : Sh. Shivlal Goyal ( Director) 2, Sri Ram Society, Gotri Road Baroda 5. Full name & Address of the Factory manager : Sh. D.S.Purohit Plot no 23, Ward -9B(D) New Bharat Nagar, Gandhidham Pin- 370201 6. Man Power
: 172 including all shift G Shift- 31 A Shift- 47 B Shift- 47 C Shift- 47 7. No. Of shift & Shift timing : Total no of shift :- 04 General shift :- 09AM To 06 PM First Shift A:- 07 AM To 03 PM
Prepared By M/s. Kutch Chemical Industries Limited Page : 14 HSE Department Rev. : 00
Second Shift B:- 03 PM To 11PM Night Shift C:- 11PM To 07AM 8. Environs (Nearest Facilities)
9. Meteorogical Data
Latitude 23 10N Longitude 70 13 E
Temperature
Maximum 48 C Minimum 7.2 C
Relative Humadity :
Maximum 100 % Minimum 1 %
Annual Rain Fall :
Minimum 73.6 mm Maximum 1393 mm (1979)
Seasonal wind directions :
Jan- Feb N / NNW / ENE March Sept SW / WSW Oct to Dec N / NNE
4. Hospitals : Anjar , Distance- 20KM 10. Total Land at Plant 50 ACRE
Prepared By M/s. Kutch Chemical Industries Limited Page : 15 HSE Department Rev. : 00
11. Total Built-up area at the Factory 30000 M2 12. Power connection Demand : 3000 KVA 13. DG Set KVA: 250 KVA 14. Power plant details : DG Set - 2.5 MW Turbine 4.2 MW 15. Water Storage and source
Capacity in m3:20000 M3, Source Gujarat water infrastructure limited (GWIL) 16. Boiler
DMS Plant VAM SD30BHX/1 200TR OLD VS VAM SD30BHX/1 200 TR MCB & PNCB Ammonia compr 2 nos KC6-3 150 TR MCB Ammonia compr 2 nos KC6-3 150 TR PNCB Ammonia compr 2 nos KC6-3 150 TR PDCB Ammonia compr 5 nos KC6 300 TR New VS Ammonia compr 3 nos KC6 180 TR OLD VS Total 1480 TR 18. Cooling Tower
Particulars
Flow rate
T R Plants
Process cooling water 4200M3/H 3260 Acid Division Process cooling water 1300M3/H 1000 DMS Plant Process cooling water 1200M3/H 1000 OLD VS
Prepared By M/s. Kutch Chemical Industries Limited Page : 16 HSE Department Rev. : 00
Process cooling water 1200M3/H 1000 MCB Plant Process cooling water 1200M3/H 1000 Acetanilid e plant Process cooling water
600m3/H 500 PNCB Plant Process cooling water 600M3/H 250 PDCB Plant Process cooling water 500M3/H 300 New VS plant Process cooling water 1350M3/H 1100 TC Plant Total 9410 19. Effluent treatment Plant Capacity: 50 M3 20. Fire water source Water reservoir (GWIL) 14 Fire Water Reservoir capacity : M3 200M3 21. Department wise List of fire extinguishers with mapping if available Departments Total nos of F/Extinguisher Benzene storage 04 nos Power plant 12 nos PNCB Plant 16 nos MCB Plant 07 nos PDCB Plant 02nos Ice plant 01 no New VS Plant 09 nos ETP 01 no Acetanilide plant 06 nos EO Storage 05 nos Capacity-25 kg FO Storage 02 nos VS OLD 06 Nos CSA Plant 02nos DMS Plant 18 nos Methanol storage 04 nos SAP Plant 15 nos Boiler house 09 nos ECC Room 10 nos as spare Total 129 nos 22. SCBA sets availability and location mapping Total Nos of SCBA Sets 08 Nos Acid division C/R- 01No Chlorine Shed- 02 Nos DMS Plant- 01 Nos TC Plant- 02 Nos
Prepared By M/s. Kutch Chemical Industries Limited Page : 17 HSE Department Rev. : 00
Emergency Control centre- 02 nos 23. OHC facilities Occupational Health Centre is declared near main gate and factory medical officer visit schedule is once in a week. Well equipment Ambulence VAN. Stretcher-01 Oxygen cylinder with mask-01 First aid box- 10 nos in all departments 24. EMP Prepared as Per ISO-14000 25. EMP plan ( Action Plan) one page Prepared and displayed in all department 26. List of emergency facilities A. Dry powder (50% of fire extinguishers ) 50 nos B. CO 2 Cartridges ( 50% of fire extinguishers ) 200 gms (10 kg DCP 50 nos C. As above 2 Kg ( 75 Kg DCP ) 06 nos D. Sand scoops 50 nos E. Safety helmets 500 nos F. Water curtain nozzles 20 nos G. Stretchers 01 nos H. First aid box with anti snake serum 10 nos I. Rubber hand gloves 200 nos J . Explosive meter 01 no K. Fire entry suit w/o breathing apparatus 01 no L. Resuscitator 05 no M. Electric siren with 3 km range 01 no N. Hand operated siren Nil O. Water gel blandest NA P. Red/green flags for fire drill Nil Q. Pressure type self contained breathing apparatus with spare cylinder (30 minutes) 08 nos. R. Safety Shower 14 nos. 27. Fire Water Reservoir :- 200 M3 28. Other Source of Water :
Gujarat water infrastructure limited , Anjar
Prepared By M/s. Kutch Chemical Industries Limited Page : 18 HSE Department Rev. : 00
29. Fire Pump Details Pump Detail Number of Pump Head Capacity (Flow) KW/HP J ockey Pump 01 70 mtr 10.8 m3/h 10 Electrical Pump 01 70 mtr 270m3/h 120 Diesel Pump Nil Nil Nil Nil Total 02 Nil Nil Nil 30. Hydrant System Details Area / Plant Nos. Of Hydrant with Hose Box Nos. Of Monitors PNCB Plant Hydrant 07 nos Hose box- 01 nos 01 no MCB Plant Hydrant 01 nos Hose box- 01 nos
Acid Division Hydrant 11 nos Hose box- 03 nos Nil Old VS plant Hydrant 06 nos Hose box- 05 nos 01 no New VS Plant Hydrant 011nos Hose box- 05 nos
Acetanilide Plant Hydrant 01no Hose box- 01 no
PDCB Plant Hydrant 02 nos Hose box- 01 nos
Power Plant Hydrant 05 nos Hose box- 02 nos
Canteen Hydrant 01 no Hose box- 01 no
DMS Plant Hydrant 02nos Hose box- 02 nos
Total Hydrant 47 nos Hose box- 30 nos
31. License & Approval: A. Factory Inspectorate
Licence No : 018712 Validity : 31/12/2010 B. GPCB Consent No: 5991/3/5/2005 Validity : 31/1/2010 Note Application inward ID- 12531/Dated- 18/12/2009 for renewal of consent C. Solid waste Disposal
Member ship : TSDF, Nandesari Baroda D. Explosive licence No : Particulars Licence no Validity Chlorine G/WC/GJ /06/109(G15607) 30/09/2011
Prepared By M/s. Kutch Chemical Industries Limited Page : 19 HSE Department Rev. : 00
Ethylene oxide old VS Plant S/HO/GJ /03/718(SS5280) 31/03/2013 Ethylene oxide New VS Plant S/HG/GJ /03/1066(S32386) 31/03/2011 Furnace oil P/WC/GJ /15/2380(PII9928) 31/12/2010 Methanol P/HQ/GJ /15/4682(P120542) 31/12/2010 Benzene& Toluene P/HQ/GJ /15/4568(P20641) 31/12.2012
Prepared By M/s. Kutch Chemical Industries Limited Page : 20 HSE Department Rev. : 00
3.3. Google Map:
Prepared By M/s. Kutch Chemical Industries Limited Page : 21 HSE Department Rev. : 00
3.4. Site Plan:
Prepared By M/s. Kutch Chemical Industries Limited Page : 22 HSE Department Rev. : 00
3.5. ORGANIZATIONAL SET UP
Safety setup organisation chart
3.6. DETAILS OF STORAGE OF HAZARDOUS MATERIALS IN BULK
NAME OF HAZARDOUS SUBSTANCE MAX. STORAGE CAP.[Qty.] PLACE OF ITS STORAGE OPERATING PRESSURE AND TEMP. TYPE OF HAZARD CONTROL MEASURE PROVIDED Vinyl Sulphone Plant Ethylene Oxide 25 KL X 1 bullet 15 KL X 1 bullet Licenced Premises A/G SS 10 Kg/ cm2 Ambient Fire /Explosion/ Toxic Double Safety Valve Nitrogen Blanketing Double Static earthing Dyke wall Scrubber provided J umper clips on flanges Hydrant system Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Shed provided on bullets. Sprinkler provided on bullets. SCBA sets available. Safety shower. Chloro Sulfonic Acid 45 KL X 6 Nos Tank
Tank farm area A/G MS ATP Ambient Corrosive Level gauge provided. Scrubber provided Required PPEs provided to Advise Company of safety legislation & updates, safety awareness, carry out safety audits, update safety policy, provide training when required, to provide investigations and reports for any accidents. Directors Unit Head VP Operation GM Operation Dy. Mgr ((Fire & Safety) (General Shift only) Fire & Safety Supervisor (One in every shift)
Fireman Two in each shift
Prepared By M/s. Kutch Chemical Industries Limited Page : 23 HSE Department Rev. : 00
Chloro Sulfonic Acid (Proposed) 200 MT X 3 Nos. Do ATP Ambient Corrosive all employees Double drain valve will be provided to sulfuric Acid storage tank Full body protection will be provided to operator. Caution note and emergency first aid will be displayed and train for the same to all employees. Safety shower and eye wash will be provided in storage tank area and plant area. Total close process will be adopted for Sulfuric acid handling. Dyke wall will be provided to storage tank Caustic Lye 25 KL X 2Nos Tank Tank farm area A/G MS ATP Ambient Corrosive Caustic Lye 40 KL X6 Nos Tank Do ATP Ambient Corrosive Sulfuric Acid 20 KL X 1Nos Tank Do ATP Ambient Corrosive Hydrochloric Acid 30 KL X 3Nos Tank Tank farm area A/G HDPE ATP Ambient Corrosive Acetanilide Plant Acetanilide 600 MT Godown ATP, Ambient Combustible Flame proof plant, pumping transfer, close process, etc. Double Static earthing Dyke wall Tanker unloading procedure. SCBA sets available . Flame proof plant, pumping transfer, close process, etc. J umper clips on flanges Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor provided on vent line of the tank Aniline 100 KL X 1 No Tank Tank farm area A/G MS ATP, Ambient Flammable Aniline 200 KL X 1 No Tank Do ATP, Ambient Flammable Acetic Acid 100 KL X 2 No Tank Do ATP, Ambient Corrosive/ Flammable Dil. Acetic Acid 25 KL X 2 No Tank Do ATP, Ambient Corrosive Ethyl Acetate 25 KL X 1 No Tank 15 KL X 1No Tank Do ATP, Ambient Flammable MCB, ODCB, PDCB, DCB Plant Chlorine 209 Tonners Storage Shed 10 Kg/cm2 Ambient Toxic Chlorine Kit, Caustic Pit, SBA sets, Cl2 Shed, Cl2 Hood, EOT, etc. Provided. Chlorine 200 Tonners Storage Shed 10 Kg/cm2 Ambient Toxic Benzene 40KLX4 Nos Tank Total : 160 KL U/G Tank MS
ATP Fire Flame proof plant, pumping transfer, close process, etc. Double Static earthing Dyke wall Tanker unloading procedure. SCBA sets available . Flame proof plant, pumping transfer, close process, etc. J umper clips on flanges Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor provided on vent line of the tank Hydrant system Monochloro Benzene (MCB) 200KLX2Nos Tank Tank farm area A/G MS ATP Fire PNCB 90KLX 2 Nos Tank DO ATP Fire ONCB 200KLX 1 No Tank DO ATP Fire Dichloro Benzene (DCB) 200KLX 1 No Tank Tank farm area A/G MS ATP Fire
Prepared By M/s. Kutch Chemical Industries Limited Page : 24 HSE Department Rev. : 00
NB, PNT, ONT, Plant Toluene 40KLX4 Nos Tank Total : 160 KL U/G Tank MS
ATP Fire Flame proof plant, pumping transfer, close process, etc. Double Static earthing Dyke wall Tanker unloading procedure. SCBA sets available . Flame proof plant, pumping transfer, close process, etc. J umper clips on flanges Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor provided on vent line of the tank Hydrant system Benzene 40KLX4 Nos Tank
Total : 160 KL U/G Tank
MS ATP Fire Nitric Acid 20KLX3 Nos Tank MS A/G Tank ATP Corrosive Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees Sulphuric Acid 20KLX 1 No Tank MS A/G Tank ATP Corrosive PNT (P- NitroToluene) 200KLX1No Tank MS A/G Tank ATP Fire Flame proof plant, pumping transfer, close process, etc. Double Static earthing Dyke wall J umper clips on flanges Hydrant system Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor Provided. ONT O- Nitro Toluene 200 KLX 1 No Tank MS A/G(V) Tank ATP Fire MNT (Meta Nitro Toluene) 90KL X1 No Tank
200KLX 1 No Tank Total : 290 KL MS A/G (H) Tank MS A/G(V) Tank ATP Fire NB (Nitro Benzene) 150KLX 1 No Tank ATP Fire Sulphuric Acid Plant Sulfur powder 5000 MT Storage yard ATP Fire Separate storage area. Monitors provided surrounding the storage area. Automatic conveyer system for charging in melter. Oleum 65 % 250 MT X2 Nos Tank MS A/G Tank
Atmospheric Ambient Corrosive Level gauge provided. Scrubber provided Required PPEs provided to all employees Double drain valve will be provided to sulfuric Acid storage tank Full body protection will be provided to operator. Oleum 23% 250 MT X 1No Tank MS A/G Tank
Atmospheric Ambient Corrosive Oleum 65 % 100 MT X 2 Nos. MS A/G Tank
Atmospheric Ambient Corrosive
Prepared By M/s. Kutch Chemical Industries Limited Page : 25 HSE Department Rev. : 00
Liq Sulphur Trioxide MS A/G Tank
Atmospheric Ambient Corrosive Caution note and emergency first aid will be displayed and train for the same to all employees. Safety shower and eye wash will be provided in storage tank area and plant area. Total close process will be adopted for Sulfuric acid handling. Dyke wall will be provided to storage tank Sulphuric Acid 98 % 1000 MT X 2 Nos. tank MS A/G Tank
Atmospheric Ambient Corrosive CSA Plant Chloro sulphonic Acid 50 KLX 3 Nos Tank 140 KL X 01 Tank MS A/G Tank
Atmospheric Ambient Corrosive Level gauge provided. Scrubber provided Required PPEs provided to all employees Double drain valve will be provided to sulfuric Acid storage tank Full body protection will be provided to operator. Caution note and emergency first aid will be displayed and train for the same to all employees. Safety shower and eye wash will be provided in storage tank area and plant area. Total close process will be adopted for Sulfuric acid handling. Dyke wall will be provided to storage tank Chloro sulphonic Acid 2000 MT X 2 Nos Tanks MS A/G Tank
Atmospheric Ambient Fire Benzene Sulphonyl Chloride 100 MTX 2 Nos.
MS A/G Tank
Atmospheric Ambient Fire DASDA
100 MTX 2 Nos. MS A/G Tank
Atmospheric Ambient Fire Methanol 60KLX 4 Nos Tank MS A/G Tank
Atmospheric Ambient Fire Flame proof plant, pumping transfer, close process, etc. Double Static earthing J umper clips on flanges Hydrant system Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor Provided. Ethanol 200 KL X 1 No. tank MS A/G Tank
Atmospheric Ambient Fire
Prepared By M/s. Kutch Chemical Industries Limited Page : 26 HSE Department Rev. : 00
Ammonia Anhydrous ( Liquefied ) 50 MT X 1 No. Bullet MS bullet 35 0 C 4 to 10 kg/cm 2
Toxic Flame proof equipment, pumping transfer, close process, etc. Double Static earthing Dyke wall Scrubber provided J umper clips on flanges Hydrant system Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. SCBA sets available . Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees Hydrochloric Acid 25 KL X 03 Nos A/G HDPE Tank Atmospheric Ambient Corrosive Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees TC plant (PROPOSED) Thyonile chloride 150KL X 03 Tank SS A/G Bullet Atmospheric Ambient Corrosive Level gauge provided. Scrubber provided Required PPEs provided to all employees Double drain valve will be provided to sulfuric Acid storage tank Full body protection will be provided to operator. Caution note and emergency first aid will be displayed and train for the same to all employees. Safety shower and eye wash will be provided in storage tank area and plant area. Total close process will be adopted for Sulfuric acid handling. Dyke wall will be provided to storage tank Chlorine 140 Toner Storage Shed 10 Kg/cm2 Ambient Toxic Chlorine Kit, Caustic Pit, SBA sets, Cl2 Shed, Cl2 Hood, EOT, etc. Provided. Scrubber provided .
Prepared By M/s. Kutch Chemical Industries Limited Page : 27 HSE Department Rev. : 00
Sulpher trioxide 100 MT X 02 Tank MS Tank Atmospheric Ambient Corrosive Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees Chlorinated Paraffin Wax CPW (PROPOSED) HNP 65KLX 04 TANK MS Tank Atmospheric Ambient Flammable Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees HCL 75KLX 6 TANK HDPE TANK Atmospheric Ambient Corrosive Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees Chlorinated Paraffin oil 20 KLX 03 FRP Atmospheric Ambient Corrosive Safety Showers provided Caution note provided Dyke wall provided Level gauge provided. Double drain valve provided Scrubber provided Required PPEs provided to all employees
Furnace Oil/ LDO 27 KLX 2 Nos U/G tanks MS Tank Atmospheric Ambient Fire Flame proof plant, pumping transfer, close process, etc. Double Static earthing J umper clips on flanges Hydrant system Fire extinguishers Fencing and No Smoking and prohibited area. Tanker unloading procedure. Flame arrestor Provided. HSD 21 KL Tank MS Tank Atmospheric Ambient Fire
3.7. Facilities / System for process safety, transportation, fire fighting system and emergency capabilities to be adopted
Following facilities and system will be installed / implemented.
1. Total enclosed process system. 2. DCS operati on plant. 3. I nstrument & Plant Ai r System for control al l parameters.
Prepared By M/s. Kutch Chemical Industries Limited Page : 28 HSE Department Rev. : 00
4. Hi gh level , l ow level, High pressure, l ow pressure, hi gh temp, hi gh fl ow, low fl ow i ndicati on and cut off i nterl ocki ng provi ded on storage as wel l as process reactors. 5. Safety valve, rupture di sk provided on reactor and pressure storage tanks. 6. Static earthi ng and el ectric earthi ng (Double) wil l be provi ded. 7. J umpers for stati c earthing on pipeli ne fl anges of fl ammabl e chemi cal provi ded. 8. Fl ame proof li ght fitti ng install ed where ever it is required. 9. Emergency handli ng equi pments li ke SCBA sets, Fire exti nguishers, Gas mask, PPEs, Chl ori ne emergency Kit, chl ori ne hood, caustic pit, Ai r l ine respi rator, provi ded. 10. Full fl edge ETP plant made and it will take care of li qui d effl uent of the plant and fi nal discharge parameter will be mai ntained as per GPCB norms. 11. Scrubbers provided on al l process vent and air monitori ng carried out and parameters will be maintained as per GPCB norms. Fire Water reservoi r for fire hydrant and sprinkl er system. 12. Storage tank area are away from the process plant and Separation Di stance has been maintai ned. 13. Dyke wal l provi ded to all above ground storage tanks, coll ection pi t wi th val ve provi ded. 14. Fl ame arrestor with breather val ve is install ed on fl ammable material storage tank vent. 15. Li ghteni ng arrestor on all chimneys and buil di ng provi ded. 16. Fencing and cauti on notes and hazard i denti ficati on boards di splayed. 17. Onl y authori zed person are permi tted i n storage tank farm area. 18. Safety permi t for hazardous material l oadi ng unl oadi ng is prepared and i mplemented. 19. Static earthi ng provision i s made at all l oadi ng unloading poi nts of fl ammabl e chemi cal storage tank farm area. 20. TREM CARD provided to all transporters and trained for transportati on Emergency of Hazardous chemi cals. 21. Fire hydrant system and water spri nkler system i nstal led at tank farm area. 22. Caution note, safety posters, sti ckers and emergency preparedness plan will be displayed. 23. Emergency faciliti es and medi cal emergency facilities are avai lable at site. Occupational Health centre facility generated at factory premi ses and paramedi cal staff i s avail able round the clock. 24. Wi nd directi on i ndicators are provi ded. 25. Safety Shower and eye wash are i nstalled at aci d/ al kali handli ng area. 26. Tel e Communi cati on system and mobile phone wil l be used i n case of emergency situations for communi cati on. 27. Emergency siren i nstall ed at mai n gate as wel l as i n all plant. 28. Training programme are being conducted regul arl y and induction trai ni ng are bei ng provi ded to al l empl oyees on chemical safety and process safety.
Prepared By M/s. Kutch Chemical Industries Limited Page : 29 HSE Department Rev. : 00
NHCOCH 3 + 2Cl.SO 3 H ACETANILIDE NHCOCH 3 + SO 2 Cl HCl + H 2 SO 4 CHLORO SULPHONIC ACID
3.1 BRIEF DESCRIPTION OF PROCESS AND FLOW CHART
3.1.1 Vinyl Sulphone & Vinyl Sulphone Condense:
Chloro Sulphonation:
Chloro Sulphonic Acid is charged into the sulphonation reactor. Acetanilide is then slowly added to maintain the temperature below 80 C. The temperature is then maintained between 50-60 C. The batch thus prepared is transferred to the storage tank.
Dumping:
Sulphonated mass is charged into the Reactor cooled with brine. Ice water is then added slowly to remove all the HCl formed due to decomposition of excess Chloro Sulphonic Acid. The HCl is scrubbed and absorbed in water to make HCl. Further Ice water is added to dilute the concentrated Sulfuric Acid formed due to the decomposition of Chloro Sulphonic Acid. Here we get of Sulfuric Acid of strength 30-40%. The mass is then filtered out (ASC Cake).
Reduction:
Sodium Bi Sulphite slurry is added to the reactor. The pH is maintained neutral by adding Caustic Lye. The ASC wet cake is then charged under controlled temperature and pH. After addition is over the temperature is raised up to 50 C. The mass is then filtered and transferred to condensation vessel.
Condensation:
The reduction mass in condensation vessel is maintained at 50C. Ethylene Oxide is slowly added. The pH is maintained to 5-7 by adding dilute sulphuric acid. The material after condensation is transferred to the Nutsch Filter. The Mother liquor is stored in storage tank. The condensed product is then washed and dried.
Esterification:
The condensed product is charged in esterification reactor. Concentrated Sulphuric Acid is added. The temperature is then raised and maintained at 160C for 4 hours. Vacumm is applied to take out acetic acid vapors and being condensed. The product is then collected a tank. The dried Vinyl Sulphone is pulverized and packed in PVC bags.
Chlorosulphonation:
Prepared By M/s. Kutch Chemical Industries Limited Page : 30 HSE Department Rev. : 00
NHCOCH 3 + SO 2 Cl NaOH + NaHSO 3 NHCOCH 3 + SO 2 Na Na 2 SO 4 + NaCl NHCOCH 3 + SO 2 Na H 2 SO 4 + H 2 O O H2C CH2 + NHCOCH 3 SO 2 CH 2 CH 2 OH + Na 2 SO 4 ETHYLENE OXIDE NHCOCH 3 SO 2 CH 2 CH 2 OH + H 2 SO 4 NH 2 SO 2 CH 2 CH 2 OSO 3 H + CH 3 COOH VINYL SULPHONE Reduction:
Ethoxylation:
Esterification:
Prepared By M/s. Kutch Chemical Industries Limited Page : 31 HSE Department Rev. : 00
Process Flow Chart: Acetanilide 2182 CHLOROSULPHONIC ACID 10182 12364 Ice 14545 DUMPING(ICE) 26909 FILTERATION(Nutch) H2SO4 (35-40%) 12364 14545 SOD. BISULPHITE SLURRY(30%) 6545 CAUSTIC LYE 2182 21091 PRODUCT FROM FILT ETHYLENE OXIDE 1018 H2SO4 2269.00 24378.00 Salt FILTER 17753 SODIUM SULPHITE SALT (BYPRODUCT) 8299 6625.00 ETP CONDENSED PRODUCT 9454 6625.00 2262 MOISTURE LOSS DRYER 4363.00 PRODUCT FROM Dryer H2SO4 1455 ESTERIFICATION 5818.00 ACETIC ACID 1818 VINYL SULPHONE 4000.0 CHLOROSULPHONATION REDUCTION ETHOXYLATION MASS BALANCE/FLOW CHART OF THE VINYL SULPHONE
Prepared By M/s. Kutch Chemical Industries Limited Page : 32 HSE Department Rev. : 00
3.1.2 Sulphuric Acid
The process for the manufacture of sulphuric acid comprise the following steps:
1. Solid Sulphur after weighment is fed to sulphur melter which is provided with steam coils. The ash content of the molten sulphur settles in the melter cum settler and molten sulphur free of impurities is pumped to the sulphur burner where it is burnt with air. Sulphur is converted in to SO2 in the sulphur burner as per the following reaction
S + O2 SO2
2. SO2 is further converted to SO3 in presence of Vanadium Pentoxide catalyst in the converter as per the following reaction: 3. SO2 + O2 SO3
The conversion of SO2 to SO3 is carried out in stages in all the five pass of the convertor. The conversion is optimized by intermediate cooling of gases between the different stages and also by interpass absorption of SO3 after 3 rd pass of the convertor.
4. The gas from the 3 rd & 5 th pass of the convertor containing SO3 is cooled & then fed to the interpass & final absorption tower where SO3 is removed by circulating Sulphuric Acid in the absorption towers. The concentration of sulphuric acid is controlled by addition of water in the pump tank.
5. Air for sulphur burner is routed through Air Filter to drying tower and further to suction side of Centrifugal Air Blower. 98.5% acid is circulated through drying tower at 70C, thus heating to 125C before entering sulfur burner. This system helps to increase generation of steam and hence power generation.
6. SO2 emission during start up of the plant is controlled by a Venturi Scrubber using alkali as scrubbing medium. The plant therefore does not cause any pollution either during start up or during normal operation.
The process as described above has been divided into five main sections described as follows:
Sulphur Circuit
The weighed quantity of sulphur of about 99.5% purity is fed to the first compartment of sulphur melter. The heat for melting sulphur is provided through steam coils. The optimum pressure to be maintained for melting sulphur in the first compartment is upto 7 kg/cm2 G.
The molten sulphur flows from compartment no. 1 to pumping compartment through underflows/overflows. The sulphur pumps for feeding sulphur are fitted in pumping compartment. The total time of retention in the compartments corresponds to more than 72 hrs at normal rated production capacity of the plant. In order to achieve
Prepared By M/s. Kutch Chemical Industries Limited Page : 33 HSE Department Rev. : 00
optimum results, it is necessary that the feeding of sulphur to the melter should be maintained at specified temperature of 135 C. All compartments are fitted with steam coil to provide the necessary heat for maintaining the temperature of molten sulphur at the desired level. Molten sulphur from the pumping compartment is pumped to the sulphur burner through one of the submersible type sulphur pumps through specially designed sulphur feeding gun. The rate of feed of sulphur to the sulphur burner is controlled by operation of sulphur feed control valve. Drain lines have been provided in the molten sulphur discharge line at two different points. The optimum steam pressure for coils located in 2 nd , 3 rd , 4 th through pumping compartments of the sulphur melter is around 4 kg/cm2 G. This regulated steam pressure is achieved through pressure reducing valve. Molten sulphur line starting from the discharge flange of the sulphur pump to the inlet of the sulphur burner is suitably steam jacketed to maintain correct temperature of molten sulphur fed to the sulphur burner.
SO2 Scrubber It is very important that SO2 emission during plant startup is controlled within persmissible limits. This is achieved by use of a alkali scrubber located after the final absorption tower where gas is scrubbed with circulating alkali solution.
DM and Water Softening Plants For generation of steam of high quality DM water is required for this purpose RO plant and DM plant will be installed.
The plant is provided with data logging system through DCS control circuits for control of parameters like Acid concentration control, pump tank level control, Boiler feed water level control, boiler feed water from deaerator temperature control. All the output signals are fed to a computer and output data is collected based on reports to be prepared including log sheets.
Prepared By M/s. Kutch Chemical Industries Limited Page : 34 HSE Department Rev. : 00
3.1.3 Oleum & SO3
Oleum (23%)
Oleum 23% is manufactured by absorbing SO3 gas with Sulphuric Acid.
H2SO4 + SO3 H2S2O7
Oleum 23% means free SO3 in the product is 23%, which is equivivalent to 105.17% Sulphuric Acid. This way 23% Oleum is equivalent to 1.07 of 98% Sulphuric Acid.
The sulphur required for 1 ton of 23% oleum is 0.326 x 1.07 =0.349 ton.
Oleum (65%)
Oleum 65% means, the free SO3 in this product is 65% which is equivalent to 114.626% sulphuric acid. This way the oleum 65% is equivalent to 1.17 times of 98% sulphuric acid.
The sulphur required for 1 ton of 65% Oleum 0.326 x 1.17 =0.381 ton
Liquid SO3
Liquid SO3 is =1.25 times of 98% Sulphuric Acid. The Sulfur required for 1 ton of liquid
SO3 =0.326 x 1.25 =0.41 ton.
Prepared By M/s. Kutch Chemical Industries Limited Page : 35 HSE Department Rev. : 00
Sulphur Metler (135C) 163.25 MT 904341 M 3 Air Drying Tower Furnace (1100) (Oxygen: 245 MT) Water WHB Steam Steam Turbine to Generate 4 MW Power Convertor (upto 3rd pass) 100 MT DM Water H2SO4 (98.5%) Acid Pump Tank P IPAB(Inter Pass Absorption Tower 99% H2SO4 Convertor (4th pass) Oleum Storage (23% or 65%) 99% H2SO4 H2SO4 (98.5%) Storage Final Absorption Tower Alkali Scrubbe r Vent to Atmosphere Wastewater 500 MT/Day 0.8 KLD Oleum Tower Oleum Pump Tank (Oleum 23% or 65%) PROCESS FLOW CHART OF H2SO4(98.7%), Oleum (23% & 65%)
Prepared By Kutch Chemical Industries Ltd. Page : 36 HSE Department Rev. : 00
SO3 + HCl ClSO3H (l) (g) (l) 80 36.5 116.5 1567 HCl Chilling 1567 Chilled HCl H2SO4 Gas Cleaning Bleed 1567 Dry HCl 99.90% 3433 Liq SO3 Reactor 100.00% Gas to Stack Caustic Scrubber 0.8 Castic Solution Wastewate To ETP 10% 0.8 KL/Month 5000 Chlorosulphonic Acid MASS BALANCE OF CHLOROSULPHONIC ACID Condenser SO3 Liquid 7500 Oluem Pump Tank (23%) 8070 Oleum Tower (23%) SO3 Convertor (132 C) PROCESS FLOW CHART OF SO3 LIQUID
3.1.4 Chloro Sulphonic Acid
The HCl gas is refrigerated and cleaned in gas cleaning tower. The dry HCl is reacted with liq SO3 to get Chloro Sulphonic Acid. The unconverted gas is scrubbed in caustic scrubber.
Chemical Reaction:
Mass Balance:
Prepared By Kutch Chemical Industries Ltd. Page : 37 HSE Department Rev. : 00
3.1.5 Sulfonation (of ONT/PNT, Tobias, VS)
Take ONT/PNT in as sulfonator and charge 98% Sulphuric Acid and 65% Oluem in it slowly. After completion of reaction blow sulfomass in another vessel containing water, charge common salt, mix it, cool it and filter in neutsch. Material is then centrifuge. Collect filterate as Spent Sulphuric Acid for sale. Sulphonated ONT/PNT from centrifuge is then packed in HDPE bags and sent for sale. For Tobias, Take Oleum (65%) in sulfonator, charge Tobias Acid slowly and after completion of charging raise temperature and maintain it. Now cool the sulphonated mass and blow it in Brine water. Allow for mixing, filter and give wash of brine water. Centrifuge the mass and collect the wet cake as product and packed in HDPE bags.
ONT 137 H2SO4 98 H2S2O7 178 413 Water 18 Common Salt 117 (NaCl) 548 Spent Acid (25%) Filteration (Water+Salt+Sulfuric Acid) 217 331 Centrifuge 2 (Recycle to Drawning Vessel) Wet Cake 215 Sulfonator Drawning Vessel MASS BALANCE OF SULPHONATION ONT/PNT
Prepared By Kutch Chemical Industries Ltd. Page : 38 HSE Department Rev. : 00
3.1.6 BENZENE SULPHONYL CHLORIDE
Benzene is reacted with Chloro Sulphonic Acid in a agitated vessel at low temperature at about 20 -25 C. Chloro Sulphonic Acid is used in excess for the reaction. The reacted mass is then kept under agitation for some time. It is then transferred to another vessel containing chilled water. During the addition, the vessel is cooled up to desire temperature till the addition complete. The contents are kept under agitation for some time. The mass is then separated. The acid layer is transferred to the storage tank for sale. The organic layer is washed, dried & distilled under vacuum to get the product. The HCl gas evolved during the reaction & isolation is send to CAS plant for making Chloro Sulphonic Acid.
663 Benzene HCl gas 1980 CSA 310 2333 Isolation Dilute H2SO4 1500 833 Distillation Crude Dimethyl Sulphone 1485 15 Benzyl Sulphonyl Chloride MASS BALANCE OF BENZYL SULPHONYL CHLORIDE Reactor
3.1.7 Thionyl Chloride
Sulphur is charged in sulfur monochloride reactor along with chlorine in measured quantity and reacted over a period of 12 hours to Sulphur Monochloride (SMC), which is stored for further reaction. Thionyl Chloride reacted is fed with SMC, SO3 and Chlorine. Reactor is fitted with fractionating column. TC gas thus produced is passed through 3 condenser, out of which first condenser used cooling water and other two condenser use chilled water. Crude TC is then sent to Distillation column as reflux. A part of crude TC is reacted with sulfur to get pure Thionyl Chloride.
Prepared By Kutch Chemical Industries Ltd. Page : 39 HSE Department Rev. : 00
818 Sulphur 890 Chlorine 1708 2044 SO3 To Sulfuric Acid & SBS plant (Recycle) 890 Chlorine 1627 3015 2400 Product 600 Product 15 Total Product 3000 MASS BALANCE OF THIONYL CHLORIDE SMC Reactor TC Reactor Condenser Distillation Column Alkali Scrubber is provided to absorb SO2 when required; similarly chlorine scrubber removes traces of chlorine. Byproduct is recycled back to sulfuric acid plant, where it is converted to Sulphur Trioxide for reuse in TC Plant.
Sulfuric Acid & Oluem (65%) are taken in Sulfonator, Para Nitro Toluene (PNT) is then charged. The mass in then dumped in to the water, cooled and filtered in Neutsch filter. The acid is then separated, The mass (PNTOSA) is then oxidized with sodium hypochloride. After completion of the reaction common salt is charged at the room temperature the mass is then filtered in Neutsch Filter . Then reduction of PNTOSA is carried out with Fe, HCl and NH4Cl. Filter the reduction mass & isolate the filterate using dilute H2SO4 & filter it in Neutsch filter. Material thus prepared is DASDA. Which is then centrifuged and packed in the HDPE bags.
Prepared By Kutch Chemical Industries Ltd. Page : 40 HSE Department Rev. : 00
PNT 63 H2SO4 45 Oleum 82 190 Water 20 Salt 15 225 Neutsch Filter 58 To ETP 167 Centrifuge 30 ML(Recycle) 137 Drawning Common Salt 15 Soda Ash 18 NaOCl 69 Water 25 264 Neutsch Filter 58 To ETP 206 Centrifuge 5 ML(Recycle) 201 Drawning Fe 5 HCl 8 NH4Cl 15 229 Filter Press 27 To ETP 202 Isolation Vessel 202 Neutsch Filter 26 To ETP 176 Centrifuge 6 ML(Recycle) 170 Isolation Vessel Product DASDA MASS BALANCE OF DASDA Sulfonator Drawning Vessel Oxidation Reduction Vessel PNT(137) 98 178 PNTSA (217) + 2HCl + 3H2O 2NaOCl +H2O 217 149 18 474 73 54 Fe/HCl NH4Cl (DNSDA) Di-Sodium Salt (Nitro form) Di-Sodium Salt (Amino form) 414 + H2SO4 414 370 DASDA CH3 + NO 2 H 2 SO 4 + H2S2O7 2H2SO4 CH3 NO 2 + SO3H O2N SO3Na - C = C H H S O 3 N NO2 H2N SO3Na - C = C H H S O 3 N NH2 H2N SO3Na - C = C H H S O 3 N NH2 H2N SO3H - C = C H H S O 3 H NH CH3 NO 2 + SO3H 2 O2N SO3Na - C = C H H S O 3 N NO2 Chemical Reaction:
Mass Balance:
Prepared By Kutch Chemical Industries Ltd. Page : 41 HSE Department Rev. : 00
3.1.9 Power Generation of 10 MW (Coal)
For power generation steam will be generated from the boiler, which is then sent to steam turbine to generated the power. At the outlet of the turbine steam goes to condenser to recover the water utilized and further sent back to the boiler. The fuel utilized for the boiler will be Coal. To generated 10 MW, a steam of 40 MTD required, which is generated from the coal based boiler. The coal consumption for the required steam would be approximately 10 MTD. For Power plant, separate coal yard will be made in which coal will be stored, from coal yard the coal will be sent to crusher. The crushed coal is then sent to silo for ultimate feed in to the combustion chamber.
Process Flow Chart: High Pressure Steam 45 kg/cm 2 410C Exhaust 0.1 kg/cm 2 100 C Condenser Condensate back to Boiler feed water Turbine Generator Set
3.1.10 Sodium Bi Sulphite
Sodium Carbonate and Water is charged in the reactor. Sulphur Dioxide is then passed slowly to the reactor. The mass is then allowed for continuous mixing. The material thus prepared is Sodium Bi Sulphite.
Na2CO3 + 2SO2 + H2O 2NaHCO3 + CO2 106 64 18 208 28 Sodium SBS Carbonate Chemical Reaction:
CO2 Sodium Carbonate 106 28 SO2 64 Water 18 160 Reactor MASS BALANCE OF SODIUM BI SULPHITE Mass Balance:
Prepared By Kutch Chemical Industries Ltd. Page : 42 HSE Department Rev. : 00
1979 Liq SO3 DME Gas 1138 1524 Methanol Day Tank Heat Exchanger Reactor Containing Al2O3 Catalyst(260C) Reactor 386 Water To ETP Condensation Tank Pure Dimethyl Sulphate 3000 Distillation 117 98% Spent Sulfuric Acid MASS BALANCE OF DIMETHYL SULPHATE 3.1.11 Dimethyl Sulphate
Methanol from day tank in the plant is taken through metering pump passed through heat exchanger and condenser in gas cycle. The methanol gas is passed through the aluminum catalyst, further it is reacted with liquid SO3. The ration of consumption of methanol + SO3 for DMS produced is as follows:
SO3 =0.70 MT Methanol =0.55 MT.
The moisture shall be collected out of Methanol and sent to ETP. After reaction of SO3 + Methanol gas in a closed reaction , Which will have chilled water circulation in jacket. The crude DMS formed is having a high acidity. The distilled and acid thus produced is 98% Sulphuric Acid. This is a by product and will be sold.
Prepared By Kutch Chemical Industries Ltd. Page : 43 HSE Department Rev. : 00
260C 2 CH3OH CH3-O-CH3 + H2O Catalyst(Al2O3) Methanol Dimethyl Ether 2 x 32 46 18 CH3-O-CH3 + C6H5NH2 (CH3)2C6H5NH2 Dimethly Aniline 46 93 123 DME Gas Aniline 1134 560 780 Methanol Day Tank Heat Exchanger Reactor Containing Aluminium Catalyst Reactor 220 Water To ETP Condensation Tank 1694 1500 Pure Dimethyl Aniline Distillation 194 Wastewate to ETP MASS BALANCE OF DIMETHYL ANILINE 3.1.12 Dimethyl Aniline
Methanol from day tank in the plant is taken through metering pump passed through heat exchanger and condenser in gas cycle. The methanol gas is passed through the aluminum catalyst, further it is reacted with Aniline. The product is then distilled to get Dimethyl Aniline The moisture shall be collected out of Methanol and sent to ETP.
Chemical Reaction:
Mass Balance:
3.1.13 Diethyl Sulfate
Ethyl Alcohol and SO3 reacts in presence of catalyst Sodium Sulphate and Urea and formed Ethyl Hydrogen Sulfate (EHS). This EHS mass is ammoniated by ammonia and EHS gets converted into Diethyl Sulfate. Ammonia is passed in Ethyl Hydrogen Sulfate mass. The product thus formed is crude Diethyl Sulphate. Moisture content present in the Ethyl Alcohol reacts with SO3 and forms Sulphuric Acid. Distillation of crude EHS takes place under vacuum. The pure DES is produced and transported to the storage tanks.
Prepared By Kutch Chemical Industries Ltd. Page : 44 HSE Department Rev. : 00
Calcium Carbonate is reacted with Hydrochloric Acid to get Calcium Chloride.
2CaCO3 +4 HCl 2CaCl2 + 2 HCO3
Chemical Reaction:
Prepared By Kutch Chemical Industries Ltd. Page : 45 HSE Department Rev. : 00
0.2 Water 5 Lime Stone Ventury Scrubber (Alkali) ETP 4 HCl 0.2 9 Sludge to ETP 1 8 CaCl2 Clear Liquid Mosture Loss 5 Dry CaCl2 Product Reactor Filter Press MASS BALANCE OF CALCIUM CHLROIDE Evaporator Mass Balance:
3.1.15 Di Calcium Phosphate
Rock Phosphate is reacted with Hydrochloric Acid to generated Phosphoric Acid, which is further reacted with Lime stone to get DCP which separated and crystallized.
Prepared By Kutch Chemical Industries Ltd. Page : 47 HSE Department Rev. : 00
Water 860 Alumina Hydrate/Bauxite 456 Sulphuric Acid 1316 1316 456 Sulphuric Acid Moulding in to Slab Reactor Settling Tank Reactor MASS BALANCE OF ALUM 3.1.18 Aluminium Sulphate (Alum)
Aluminium Sulphate is manufactured by the reaction of Aluminia Hydrate and Bauxite with Sulphuric Acid.
Bauxite is ground in the pulveriser to 90% passing through 200 mesh and elevated to batch hopper through bucket elevator. Measure quantity of water is added in the lead bonded reactor and slowly sulphuric acid is to be added in the reactor.. After getting the required temperature in the reactor, slowly ground bauxite i.e added. After the addition of measure quantity of bauxite/alumina hydrate, the agitator is kept on for about 45 minutes, solution is then dumped in to the settling tank.
The decanted solution of Aluminium Sulphate is then taken to the reactor and the required quantity of sulphuric acid is added after getting the required temperature Hydrated Alumina is added slowly. After addition, Aluminum Sulphate is moulded in the trays with the help of tray filling arrangements. The slabs after cooling are to be taken out from the trays and stacked in the store.
Prepared By Kutch Chemical Industries Ltd. Page : 48 HSE Department Rev. : 00
350 Urea Reactor 3300 SO3/Oleum (23-25%) 3650 R/C Mother Liquor Mixing 5150 Separation Spent Acid 2400 2750 100 Water Make -Up 2500 Cyrstallisation 1500 1000 Packing/Bagging Figure are in Ton/Month MASS BALANCE OF SULFAMIC ACID 3.1.19 Sulfamic Acid
Urea & 23-25% Oleum are fed at controlled rates to reactor, which is cooled by chilled water/brine and cooling water. The reaction products are diluted by mixing with recycled mother liquor (available after separation of crystals of sulfamic acid). Temperature is controlled during mixing by chilled water/brine. Dilute acid streams (70% sulfuric acid) is separated after the mixing operation and is sold to SSP/Alum manufacturer.
NH2CONH2 + SO3 NH2CONHSO3H + CO2 Chemical Reaction: NH2CONHSO3H + H2SO4 2NH2SO3H + CO2 Overall Reaction NH2CONH2 + SO3 + H2SO4 2NH2SO3H + CO2 60 80 98 2 x 97 44
Mass Balance:
Prepared By Kutch Chemical Industries Ltd. Page : 49 HSE Department Rev. : 00
SECTION IV
HAZOP SHEET
HAZOP SHEET
Prepared By Kutch Chemical Industries Ltd. Page : 50 HSE Department Rev. : 00
VS PLANT Table: 4.1 HAZOP STUDY WORKSHEET
Study Title Transferring of Chlorsulfonic Acid to service tank. Drawing No. Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Storage tank, Pump Activity Transferring of Chloro Sulfonic Acid to Service Tank. Design intent PRES. TEMP FLOW VACU. Material : Chloro Sulfonic Acid Amb Amb ---- Source : Formthe storage Tank
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Flow No 1. No material in the storage tank. 2. Pump tripped. 3. Pump valve closed.
No material to service tank. Pressure gauge provided on the pump discharge valve. 1. Level indicator to be provided on service tank. 2. Arrow indicators to be provided on pipeline
Less 1. Valve partially closed. 2. Leakage in the pipe line. 3. Less material in the storage tank.
More time taken to fill the service tank.
More 1. Pump Ampere more. 2. Discharge valve fully open than required set value.
Early filling of Service tank 1. Level indicator provided. 2. Vents are connected to scrubber.
Prepared By Kutch Chemical Industries Ltd. Page : 51 HSE Department Rev. : 00
Table: 4.2 HAZOP STUDY WORKSHEET
Study Title Charging of Acetanilide Drawing No. Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered -- Activity Charging of acetanilide Design intent PRES. TEMP FLOW VACU. Material : Acetanilide Nil Amb NA -- Source : Bag packing
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Charging No No material No process will take place. Material is charge under the supervision. Separate storage to be identified with the marking
Less 1. Human error. 2. Material weight is less than what is mentioned on the bag.
1. Disturbance in the process. 2. More
More 1. Human Error 2. Material packing weight is more than what is printed on it. 1. Disturbance in the process. 2. Product quality may detoriate. 1. Charge batch to be earmarked. 2. Identification of bag to be done in local language.
Wrong 1. Human error. 2. Wrong labeling. 3. Wrong supply of material from supplier.
Disturbance in the process.
Prepared By Kutch Chemical Industries Ltd. Page : 52 HSE Department Rev. : 00
Table: 4.3 HAZOP STUDY WORKSHEET
Study Title Reaction Drawing No. Revision No. NIL Date 08.07.2010 Hazop Team Part Considered Rector Activity Reaction Design intent PRES. TEMP FLOW VACU. Material : Acetanilide +Chlorosulfonic. ----- 80 ---- ----- Source : Fromthe storage tank & Manual charging of bag.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Pressure More 1. Chilled water supply low. 2. More quantity of CSA. 3. No stirrer operation. 4. Entry of water in the reactor 5. No scrubbing of HCL water, Accumulation of vapor in the reactor. 6. Choking in the scrubber. Pressure & temperature will go on increasing. Exothermic Reaction will take place. 1. Vent provided to scrubber. 2. Pressure gage provided on Reactor. 3. Temperature gauge provided on reactor. 4. Safety valve & pressure gauge are provided on reactor cooling jacket. 5. Sight glass provided. 1. Standard operating procedure to be prepared. 2. Arrow indicators to be provided on pipe line. Less 1. Good cooling 2. Control Rate of Raw material addition. No process hazards Temperature More As per pressure Less Good cooling water flow No process hazards. It is process requirement.
Water Entry in the reactor Leakage Temperature & Pressure will go on increasing. 1. Thickness monitoring of the reactor is carried out. 2. Hydro testing of the jacket at periodic interval.
Prepared By Kutch Chemical Industries Ltd. Page : 53 HSE Department Rev. : 00
Table: 4.4 HAZOP STUDY WORKSHEET
Study Title Dumping Drawing No. Revision No. Nil Date 08.07.2010 Hazop Team Part Considered Dumping vessel Activity Dumping of sulphonated mass. Design intent PRES. TEMP FLOW VACU. Material : Sulphonated mass. Gravity 5 ---- ---- Source : Fromsulfonator
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More
1. No addition of ICE water. 2. Poor cooling of the reactor. 3. Choking in the HCL scrubber line. 1. Maximum temperature will be the ambient. 1. Temperature Gauge 2. Pressure gauge provided. 3. Total closed process 4. Safety valve provided on Chilled water cooling line. 1. Only administrative checks to be ensured. 2. SOP to be prepared. Less Good cooling 1. It is good for the process 2. No safety & health hazards.
Pressure More Increase in temperature due to above hazards. No process & safety hazards
Less Flow More Not Applicable There is no flow measurement as sulphonated reaction mass is directly dumped in the dumping vessel.
Less Not applicable Other than Part of No full charging Process delayed Physical inspection
Prepared By Kutch Chemical Industries Ltd. Page : 54 HSE Department Rev. : 00
Table: 4.5 HAZOP STUDY WORKSHEET
Study Title Reduction Drawing No. Revision No. Nil Date 08.07.2010 Hazop Team Part Considered Reduction Activity Reduction Design intent PRES. TEMP FLOW VACU. Material SBS +Caustic Lye 50 Source From
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Poor/No cooling. 2. Damaged insulation 3. Stirrer not moving/stopped 4. More addition of caustic. 5. Charging of normal water. 1. Desired process will not achieved. 2. Temperature will rise. 1. Temperature Gauge 2. Pressure gauge provided. 3. Total closed process 4. Safety valve provided on Chilled water cooling line. Visual check by the operator
Less 1. Good cooling. 2. Controlled addition of material in controlled way. No process & safety hazards as it is requirement of the process.
Pressure More No effect on pressure rise as it is only neutralization & reduction by adding caustic lye. No process & safety hazards Less Not possible.
Prepared By Kutch Chemical Industries Ltd. Page : 55 HSE Department Rev. : 00
Table: 4.6 HAZOP STUDY WORKSHEET
Study Title Condensation Drawing No. Revision No. Nil Date 08.07.2010 Hazop Team Part Considered Condensation Rector Activity Design intent PRES. TEMP FLOW VACU. Material : Reduction Mass +Ethylene Oxide 50 --- ---- ---- Source : Reduction & EO formstorage tank
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Hot oil circulation is more. 2. More hot material from the reduction it self. 3. Flow of EO in case above desired level. Increase in temperature & pressure. 1. Safety valve provided on reactor & day tank 2. Rupture disc provided on reactor & day tank. 3. Temperature & Pressure gauge provided. 4. Stand by pump for the cooling have been provided. 5. Safety valve provided on Chilled water cooling line. 6. Temperature control at50 C by providing chilling cooling & hot oil circulation in reactor jacket. 7. Dump vessel provided to transfer reaction mass in case pressurize & increase in temperature. 8. Load shell tank provided 9. Nitrogen PRV skid provided for the Nitrogen blanketing. 1. Visual check by the operator 2. E. O. flow cutoff to be provided in connection with the temperature rise. 3. Arrow indicators to be provided on pipeline. 4. Nitrogen blanketing to during reaction to be provided.
Prepared By Kutch Chemical Industries Ltd. Page : 56 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature Less Human error- Chilled water circulation valve is open.
Desired process will not achieve. BMR is prepared & followed. Physical checks are required. Pressure More Increase in temperature due to above mentioned causes Temperature Increase. Pressure Gauge provided on reactor & operator will take action accordingly.
Less Not possible
Flow ( EO ) More 1. Human Error 2. Valve passed.
Increase in temperature & pressure.
1. Sight glass 2. Line Sight Glass Provided. 3. Flow meter provided on Inlet of reactor. 4. Double mechanical seal in stirrer 5. Total closed process 6. Flameproof fitting provision. 7. Double static earthing provided. 8. J umpers provided on flange joint. 9.
No/Less 1. No material 2. Valve jammed 3. Wrong setting of the valve
Delayed in the process.
Prepared By Kutch Chemical Industries Ltd. Page : 57 HSE Department Rev. : 00
Table: 4.7 HAZOP STUDY WORKSHEET
Study Title Esterification Drawing No. Revision No. Date 08.07.2010 Hazop Team Part Considered Esterification Reactor Activity Esterification Design intent PRES. TEMP FLOW VACU. Material : Sulfuric Acid +Condensed product. ---- 160 Yes Source : FromCondensation
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Increase in flow of Sulfuric acid. 2. J acket temperature is more. 3. Less quantity of condensed material.
1. Pressure will increase. 2. PH may affected.
1. Temperature & pressure gauge provided. 2. Safety valve & Pressure gauge provided on Reactor jacket. 3. Sight glass provided. 4. Vent are connected to scrubber. Physical & administrative checks to be ensured. Less 1. No heating in the jacket. 2. No flow of sulfuric acid.
1. No safety & health hazards. 2. Desired process temperature will not achieved. 3. Delayed in the batch cycle.
Pressure More As per the temperature
Less As per the temperature
Prepared By Kutch Chemical Industries Ltd. Page : 58 HSE Department Rev. : 00
Table: 4.8 HAZOP STUDY WORKSHEET
Study Title E. O. storage tank Drawing No. NIL Revision No. NIL Date 28-06-2008 Hazop Team Deepak Chanchad Part Considered Storage Tank Activity Storing of E. O. Design intent PRES. TEMP FLOW VACU. Material : E. O. N. A. N.A. Source : E. O. Storage tank
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature
More
1. No chilled water supply. 2. Ambient temp high. 3. Poor insulation (water entry inside insulation). 4. E. O. not consumed for some days.
1. Development of pressure in Ethylene Oxide tank. 2. Blow off from Safety Valve. 3. Toxic & Fire Hazards. Explosion Hazards. Air pollution. Leakage from flange may occur. 4. Metallic impurities. 5. In case temperature is more than 20 C then polymerization may occur. 1. PSV provided. 2. Chilled water cooling provided. Safety Valve provided. 3. Rupture disc provided. 4. Insulation to tank provided. 5. Magnetic level type flow indicator provided. 6. Ethylene Oxide gas sensor monitoring systemprovided. 7. Pressure Gauge provided. 8. Fix Fire water monitor system provided. 9. Sprinkle on Systemon EO tank provided. 10. Hi temperature alarms provided. 11. Chilling coil provided. To storage tank covers 90 % in the bottom2-3 tons E. O. left without chilling. 1. To dilute the 1 liter of EON, 18 liters water is required. Considering this sufficient quantity of water shall be ensured. 2. All flange joints shall be checked regularly.
Prepared By Kutch Chemical Industries Ltd. Page : 59 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature Less 1. Good Chilling. 2. Too cold atmosphere during the winter.
1. Decrease in E. O. Pressure.
1. Temperature Gauge provided. 2. Insulation provided.
Pressure More 1. N2 valve passing. 2. More temperature in the storage tank.
1. Leakage from flange may occur 2. Blow off from Safety Valve. 3. Toxic & Fire Hazards. Explosion Hazards. Air pollution.
1. Pressure switch provided on E. O. tank. 2. Inbuilt N2 pressure is 5.8 kg/cm2 so by human error N2 valve remains open than also it will not rise up to 5.8 kg/came. Safety valve of Storage tank set at 6.5 Kg/cm2
1. During the pop of Safety valve it shall be ensured the sufficient quantity of water for dilution. 2. In case Safety valve do not set to its back position after venting the extra pressure (this scenarios shall be considered.) 3. Foamtype monitor shall be considered. 4. Calibration for all instruments shall be done vigorously.
Less 1. Leakage from flange joints, 2. Pump discharges less. 3. Mal functioning FCV 4. Valve partially closed. In case activation of any interlock than also the flow will be low.
Prepared By Kutch Chemical Industries Ltd. Page : 60 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Flow More Covered under pressure 1. During the pop of Safety valve it shall be ensured the sufficient quantity of water for dilution. 2. In case Safety valve do not set to its back position after venting the extra pressure (this scenarios shall be considered.) 3. Foamtype monitor shall be considered. Calibration for all instruments shall be done vigorously. Less
Covered under pressure Process disturbance. Spillage hazards
Reverse
Not Possible
No Safety hazards
Auto shut off valve provided. Leakage of water in storage tank.
Other than Leakage from cooling coil
Moisture in E.O. quality problemin EO. Wastage of material Pressure gauge on the outer side of the cooling coil shall be provided.
Prepared By Kutch Chemical Industries Ltd. Page : 61 HSE Department Rev. : 00
Table: 4.9 HAZOP STUDY WORKSHEET
Study Title Fromoutlet of storage tank to inlet of batch tank. Drawing No. 0 Revision No. NIL Date 28-06-2008 Hazop Team Mr Deepak Chanchad Part Considered Storage tank & pump Activity Transferring of Raw material Design intent PRES. TEMP FLOW VACU. Material : E. O. Amb Source : Fromstorage tank
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More
1. Seasonal effect 2. Poor insulation of pipeline. 3. Falling of hot water on uninsulated line. 4. Incoming E. O. from storage tank itself has high temperature. 1. More pressure in the pipeline may give rise to leakage. 2. Frompoor flange joints, valve. Fire & health hazards. Insulation on pipeline & batch tank provided. 1. To dilute the 1 liter of EON, 18 liters water is required. Considering this sufficient quantity of water shall be ensured. 2. All flange joints shall be checked regularly.
Less
1. Seasonal effect 2. lekage of chilled water in E.O. from tank. No workplace Hazards. It the basic requirement but High moisture in E.O. Wastage of E. O.
Safety valve provided on batch tank.
Pressure More Covered under flow
Less Covered under flow
Prepared By Kutch Chemical Industries Ltd. Page : 62 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Flow More
1. N2 pressures more. 2. Valve failure 3. FIC mal function. 4. Human error.
1. Pressure rise in batch tank. 2. Leakage in flange joint. 3. Safety valve of batch tank may popup. 4. Tank filling operation completed in less time. Pressure gauge shall be provided on batch tank. Less
1. Choking in the excess flow valve. (Holes are choked.) 2. Low pressure of N2 itself. 3. Valve choked.
No safety hazards but it will take more time for filling operation.
Reverse No chances 1. NRV provided. 2. Auto shut off valve provided.
Prepared By Kutch Chemical Industries Ltd. Page : 63 HSE Department Rev. : 00
ACETALININDE PLANT Table 4.10 HAZOP STUDY WORKSHEET Study Title Raw material to the storage tank ( Day Tank ) Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Storage tank & pump Activity Transfer Design intent PRES. TEMP FLOW VACU. Material : Acetic Acid Am Am Source : Fromstorage tank.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Flow Pressure No
1. No material in the storage tank. 2. Pump tripped. 3. Pump discharge valve closed. 4. Heavy leakage in pipe line. No material to service tank. Pressure gauge provided on the pump discharge valve.
1. Non-returnable Valve to be provided. 2. Arrow indicator to be provided on pipeline. 3. Stand by pump to be provided. 4. Pump, storage tank & pipe line identification to be done. 5. Color code to be provided. 6. Work permit procedure to be followed for handling of hazardous chemicals. 7. PPE compliance to be followed during handling of acid. More 1. Valve opened more than set value 2. Human Error. More material to the service tank.
Reverse Not possible Less SOP to be prepared.
Prepared By Kutch Chemical Industries Ltd. Page : 64 HSE Department Rev. : 00
Table 4.11 HAZOP STUDY WORKSHEET
Study Title Reaction Process Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Storage tank & pump Activity Reaction Design intent PRES. TEMP FLOW VACU. Material : Acetic Acid & Aniline +Acetic anhydride. Am 130 Source : Fromthe storage tank.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Hot oil circulation temperature is more. 2. Choking of pipeline of inlet & out let of condenser. 3. Poor cooling in condenser. 1. Process Disturbance. 2. (Reaction time will be more.) 3. Product will char.
1. Pressure gauge & temperature gauge to be provided. 2. Safety valve provided on reactors jacket.
1. Arrow indicator to be provided. 2. Sand tray to be provided for the collection of storage. 3. SOP to be prepared.
Less 1. Ambient temperature is low. 2. Good cooling. 3. Hot oil circulation temperature is low. Efficient process will not take place.
Pressure More Atmospheric pressure reaction SOP to be prepared.
Less
Not possible Power failure No process will take place. DG set provided.
Prepared By Kutch Chemical Industries Ltd. Page : 65 HSE Department Rev. : 00
CHLORO SULPHONIC ACID PLANT
Table 4.12 HAZOP STUDY WORKSHEET
Study Title Chilling of the HCL Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Storage tank & pump Activity Chilling Design intent PRES. TEMP FLOW VACU. Material : HCL ---- ---- ---- Source : FormMCB plant
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Chilling No
1. No supply of chilling media. 2. Power failure 3. Insulation damaged. 4. Seasonal effect 5. HCL flow is low. 6. More impurities of organics from the other plant.
1. Poor chilling of the HCL. 2. Process delayed. 1. Temperature controller is provided. 2. Insulation provided on the chiller.
More Not possible.
Reverse Not possible.
Prepared By Kutch Chemical Industries Ltd. Page : 66 HSE Department Rev. : 00
Table 4.13 HAZOP STUDY WORKSHEET
Study Title Gas cleaning Drawing No. Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Activity Cleaning of HCL Design intent PRES. TEMP FLOW VACU. Material : HCL Source : Fromchilling section
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Cleaning No
1. No supply of HCL. 2. Cleaning media circulation stopped. 3. Poor circulation. 4. H2SO4 exhausted. 1. No Health & Safety hazards. 2. Quality of cleaning of the HCL will be affected. (Moister will not removed and due to moisture wet gas will carry over in the reaction.
1. Physical check for the cleaning media which is to be changed after certain cycle. 2. Pump stop alarmto be provided. More Good quality of cleaning media. No process & safety hazards.
Temperature More Choking in scrubber & vapor. Accumulation in gas phase.
Prepared By Kutch Chemical Industries Ltd. Page : 67 HSE Department Rev. : 00
Table 4.14 HAZOP STUDY WORKSHEET
Study Title Reaction Drawing No. Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Activity Reaction Design intent PRES. TEMP FLOW VACU. Material : Dry HCL & SO# 3-5 kg /cm2 Am As per blower --- Source : Fromthe storage tank.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Flow More 1. HCL flow as per blower. 2. SO3 flow more than set value. 3. Human error. 1. No process disturbance. 2. Un reacted sulfur trioxide generation will be more. 1. Temperature indicator provided. 2. Pressure gauge provided.
Arrow indicators & pipeline color code to be provided. Less/ No 1. Blower amp low. 2. Blower stopped Process Delayed. Temperature More Flow of HCL & SO3 are more. Increase in temperature & pressure.
Less Flow of HCL & SO3 are less. Decrease in pressure & temperature
Power failure --- 1. Un-reacted gas will come out fromthe scrubber. 2. Circulation will be stopped & reaction will take place. Captive Power plant.
Prepared By Kutch Chemical Industries Ltd. Page : 68 HSE Department Rev. : 00
SULFURIC ACID PLANT Table 4.15 HAZOP STUDY WORKSHEET
Study Title Melting of Sulfur Drawing No. 0 Revision No. NIL Date 07.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Storage tank & pump Activity Melting Design intent PRES. TEMP FLOW VACU. Material : Sulfur 135 Source : Fromthe Sulfur storage tank.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Low quantity of sulfur (Sulfur fed poorly. 2. Steamtemperature high. 3. Ambient temperature high. Good for the process.
1. DSC operated plant. 2. Pressure indicator provided. 3. Temperature gauge provided. 4. Level indicator provided. 5. Closed process 6. Controls on flow. Temperature & pressure are provided. Interlocks between the Burner temperature & steamflow is suggested. Less 1. Incoming steam temperature low. 2. Ambient temperature low. 3. More quantity of sulfur fed in the burner.
Pressure More
1. Temperature is very high. 2. Choking in the upward stream.
Over pressurization may affect on there factory wall over a long run.
Pressure indicator provided. Temperature gauge provided. 1. Physical checks to be ensured. 2. Periodic inspection of the Sulfur burner to be ensured. Less As per low temperature. Sulfur & Steam Mixing Leakage in the steamcoil. Material will spoil. Temperature gauge & pressure gauge provided.
Power failure ---- Sulfur May jammed Captive Power Plant. Critical equipment should be connected with the DG supply.
Prepared By Kutch Chemical Industries Ltd. Page : 69 HSE Department Rev. : 00
Table 4.16 HAZOP STUDY WORKSHEET
Study Title Burning of sulfur with air. Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Sulfur Burner Activity Pumping Design intent PRES. TEMP Sulfur VACU. Material : Sulfur 1100 - ---- Source : Fromthe Sulfur storage tank.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Incoming air temperature is high. 2. Efficient operation of furnace. No process hazards as it is the process requirement. 1. Temperature controller provided. 2. Glass window provided. Arrow indicators to be provided on fuel line. Less 1. Poor incoming air temperature 2. Poor flow of fuel. Conversion process of the SO2 will not take place.
Pressure More 1. Incoming air flow is more than set value. 2. Discharge of SO2 gas restricted due to choking. 3. Rupture of partition wall. 4. More incoming pressure fromthe sulfur melter. Heavy leakage may started formthe panel door & also some time rupture of furnace.
Less 1. No flow of air. 2. No sulfur fromthe melter. No Health & safety hazards.
Flow More As per more pressure. Low As low pressure. Power failure. J amming of sulfur In burner. DG set provided.
Prepared By Kutch Chemical Industries Ltd. Page : 70 HSE Department Rev. : 00
Table 4.17 HAZOP STUDY WORKSHEET
Study Title Catalyst convertor Drawing No. 0 Revision No. Nil Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Sulfur Burner Activity Design intent PRES. TEMP FLOW VACU. Material : SO3, Vanadiumpentoxide. Source :
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. Incoming air temperature is high. 2. Efficient operation of furnace. No process hazards as it is the process requirement. 1. Temperature controller provided. 2. Glass window provided.
Less 1. Poor incoming air temperature 2. Poor flow of fuel.
Conversion process of the SO2 will not take place.
Pressure More 1. Incoming air flow is more than set value. 2. Discharge of SO2 gas restricted due to choking. 3. Rupture of partition wall. 4. More incoming pressure fromthe sulfur smelter. 5. Heavy leakage may started formthe panel door & also some time rupture of furnace.
Less 1. No flow of air. 2. No sulfur fromthe melter. No Health & safety hazards.
Flow More As per more pressure. Low As low pressure. Power failure. J amming of sulfur In burner. DG set provided.
Prepared By Kutch Chemical Industries Ltd. Page : 71 HSE Department Rev. : 00
THYONYL CHLORIDE PLANT Table 4.18 HAZOP STUDY WORKSHEET
Study Title Rector Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Activity Reaction process Design intent PRES. TEMP FLOW VACU. Material : Chlorine & Sulfur 105 Source : FromStorage
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. More quantity of Catalyst, 2. More Charge quantity of either Chlorine & Sulfur 3. Hot oil temperature is more. Pressure & temperature will go on increasing. 1. Temperature gauge & pressure gauge provided. 2. Rotometer provided for the chlorine control. 3. Sight glass provided. 4. Safety valve provided. 5. Cooling & chilling arrangement with alternative provided. 6. Chlorine PRV station provided. 7. In case of increase of temperature chlorine charging supply will closed. 8. In case of increase of pressure raw material charging supply will closed. 1. Arrow indicator to be provided on pipeline. 2. Stand by pump to be provided. 3. Pump, storage tank & pipe line identification to be done. 4. Color code to be provided. 5. Work permit procedure to be followed for handling of hazardous chemicals. 6. PPE compliance to be followed during handling of acid. Less 1. Less quantity of catalyst. 2. Hot oil temperature is less or less quantity of HO is fed due to leakage valve partially closed. Reaction time will increase.
Prepared By Kutch Chemical Industries Ltd. Page : 72 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Pressure More
As per temperature Less
Flow More Human error. More charging of material.
Pressure & temperature will go on increasing.
Power failure No GEB supply. Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 73 HSE Department Rev. : 00
Table 4.19 HAZOP STUDY WORKSHEET
Study Title Gas mixture Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Activity Gas Mixing Design intent PRES. TEMP FLOW VACU. Material : Chlorine, SO2 & SDC Source : FromStorage
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More 1. More quantity of Catalyst, 2. More Charge quantity of eithe Chlorine & Sulfur 3. Hot oil temperature is more. 4. More SO2 fromthe holder tank. Pressure & temperature will go on increasing. 1. Temperature gauge & pressure gauge provided. 2. Rotometer provided for the chlorine control. 3. Sight glass provided. 4. Safety valve provided . 5. Cooling & chilling arrangement with alternative provided. 6. Chlorine PRV station provided.
1. Non returnable Valve to be provided. 2. Arrow indicator to be provided on pipeline. 3. Stand by pump to be provided. 4. Pump, storage tank & pipe line identification to be done. 5. Color code to be provided. 6. Work permit procedure to be followed for handling of hazardous chemicals. 7. PPE compliance to be followed during handling of acid. 8. Periodic checking of the condenser to be followed. Less 1. Less quantity of catalyst. 2. Hot oil temperature is less or less quantity of HO is fed due to leakage, valve partially closed. Reaction time will increase. Pressure More As per temperature Less 1. Human error. 2. More charging of material. Pressure & temperature will go on increasing.
Flow More No GEB supply. Pump circulation will stop.
Power failure Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 74 HSE Department Rev. : 00
Table 4.20 HAZOP STUDY WORKSHEET
Study Title High Boiler fractional Distillation Column Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered HBFC, Condenser, Heat Exchanger & Carbon bed. Activity Distillation Design intent PRES. TEMP FLOW VACU. Material : Crude TC Source : Fromthe Crude TC Reciever.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More Good Heating
1. No process hazards. It is part of the requirement. 2. It will accelerate the distillation process
1. Temperature gauge & pressure gauge provided. 2. Sight glass provided. 3. Safety valve provided . 4. Cooling & chilling arrangement with alternative provided. 5. Chlorine PRV station provided.
1. Non return Valve to be provided. 2. Arrow indicator to be provided on pipeline. 3. Stand by pump to be provided. 4. Pump, storage tank & pipe line identification to be done. 5. Color code to be provided. 6. Periodic checking of the condenser to be followed. Less Poor Heating No distillation will take place. Process delayed.
Pressure More Not possible ----- Less Not Possible ----- Flow More Not possible ----- Power failure No GEB supply. Distillation will not achieve. Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 75 HSE Department Rev. : 00
Table 4.21 HAZOP STUDY WORKSHEET
Study Title Final Product Distillation Column Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered HBFC, Condenser, Heat Exchanger & Carbon bed. Activity TC Distillation Design intent PRES. TEMP FLOW VACU. Material : Crude TC Yes Yes Source : From HBFC.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required Temperature More Good Heating
1. No process hazards. It is part of the requirement. 2. It will accelerate the distillation process
1. Temperature gauge & pressure gauge provided. 2. Sight glass provided. 3. Safety valve provided . 4. Cooling & chilling arrangement with alternative provided.
1. Non returnable Valve to be provided. 2. Arrow indicator to be provided on pipeline. 3. Stand by pump to be provided. 4. Pump, storage tank & pipe line identification to be done. 5. Periodic checking of the condenser to be followed. Less Poor Heating No distillation will take place. Process delayed.
Pressure More Not possible ----- Less Not Possible ----- Flow More Not possible ----- Power failure No GEB supply. Distillation will not achieved. Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 76 HSE Department Rev. : 00
MONOCHLORO BENEZEN PLANT
Table 4.22 HAZOP STUDY WORKSHEET
Study Title Reaction of Chlorine Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Activity Reaction Design intent PRES. TEMP FLOW VACU. Material : Chlorine & Benzene Source : Fromthe storage tank
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Temperature More 1. More quantity of chlorine due to wrong setting of Rotometer. 2. Rotometer malfunction 3. Poor cooling of reactor. 4. Ambient temperature is high. 5. More flow of benzene due to human error.
1. Flame Proof fitting are provided. 2. Rota Meter is provided. 3. Double static earthing provided to all equipment. 4. J umpers are provided on all the pipe line joint. 5. Benzene flow cut off at high temperature in reactor have been provided. 6. Temperature controllers are provided in front of Operators cabin.
1. To handle the chlorine emergency chorine kit to be ensured. 2. Chlorine detectors to be provided. Less 1. Flow of chlorine is less. 2. Rotometer malfunctions. 3. No benzene flow or choking in spray nozzles. 4. Chlorine sprayer got choked.
Prepared By Kutch Chemical Industries Ltd. Page : 77 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Pressure More As per flow
Less As per flow
Flow More 1. Rotometer failure 2. More flow fromthe chlorine header itself. Temperature will go on increasing
Less 1. Rotometer malfunction. 2. Less flow fromthe chlorine itself. 3. Valve closed. Process delayed. Power failure 1. No supply due to electrical fault 2. & also the captive power plant not running. Captive power plant provided. 1. Chlorine supply to be closed immediately as it leads to environmental hazards. Un reacted chlorine will go to the atmosphere. 2. DG set to be provided & all critical equipment shall be connected with the DG supply.
Prepared By Kutch Chemical Industries Ltd. Page : 78 HSE Department Rev. : 00
DMS PLANT
Table 4.23 HAZOP STUDY WORKSHEET
Study Title Reaction Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr Deepak Chanchad Part Considered Activity Reaction Design intent PRES. TEMP FLOW VACU. Material : Methanol Yes 260 No Source : Fromthe Heat exchanger & condenser
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Temperature More 1. Hot oil circulation is more. 2. More temperature of the methanol gas. 3. More charging of the catalyst. 4. Ambient temperature is more.
1. Pressure will go on increasing. 2. No process hazards. 3. It is the part of requirement.
1. DSC Plant operation 2. Flow control valve provided on the methanol. 3. Flame Proof fitting are provided. 4. Double static earthing provided to all equipment. 5. J umpers are provided on all the pipe line joint. 6. Safety Valve & Pressure gauge are provided on Hot oil circulation circuit. 1. Calibration of all instruments to be carried out. 2. SOP to be prepared. 3. Annual shut down to be carried out and corroded plant to be replaced. 4. Thickness monitoring of the vessels to be carried out. Less Low catalyst quantity of catalyst due to human error. 1. Process delayed. 2. DMS gas will not produced.
Pressure More As per flow
Less As per flow
Prepared By Kutch Chemical Industries Ltd. Page : 79 HSE Department Rev. : 00
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Flow More 1. Pump Ampere more. 2. Valve fully open 3. In the system. 4. Human error.
Less 1. Pump amp low 2. Leakage in the pipe line. 3. Valve partially closed in the HE & condenser system. 4. No material in the storage tank.
Power failure 1. No GEB supply. 2. Sudden failure in the electrical system. Process disturbance. Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 80 HSE Department Rev. : 00
Table 4.24 HAZOP STUDY WORKSHEET
Study Title Reaction Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Activity Chilling Reaction Design intent PRES. TEMP FLOW VACU. Material : SO3 & Methanol Yes No Source : Fromthe reactor.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Temperature More 1. Not Possible. 2. Chilling process 1. DCS operated plant. 2. Closed process 3. Pressure gauge provided on the chilled water jacket. 4.
Less 1. Good chilling effect. 2. Winter days. 3. Good insulation 1. Good for the process. 2. No safety hazards
Pressure More Not possible
Less Not possible
Flow More Not possible
Less Not possible.
Power failure 1. No GEB supply. 2. Sudden failure in the electrical system. Process Disturbance Captive power plant provided.
Prepared By Kutch Chemical Industries Ltd. Page : 81 HSE Department Rev. : 00
Table 4.25 HAZOP STUDY WORKSHEET
Study Title Distillation Drawing No. 0 Revision No. NIL Date 08.07.2010 Hazop Team Mr. Deepak Chanchad Part Considered Activity Distillation Design intent PRES. TEMP FLOW VACU. Material : DMS vapour. Yes No Source : Fromthe reactor.
Parameter Guide Words Possible causes Possible consequences Measures/Existing facilities safeguard Action Required
Temperature More Good Heating
1. No process hazards. It is part of the requirement. 2. It will accelerate the distillation process 1. Temperature gauge & pressure gauge provided. 2. Sight glass provided. 3. Safety valve provided . 4. Cooling & chilling arrangement with alternative provided. 5. Chlorine PRV station provided.
1. Non returnable Valve to be provided. 2. Arrow indicator to be provided on pipeline. 3. Stand by pump to be provided. 4. Pump, storage tank & pipe line identification to be done. 5. Color code to be provided. 6. Periodic checking of the condenser to be followed. Less Poor Heating No distillation will take place. Process delayed. Pressure More Not Possible Less Not Possible Flow More Not Possible Less Not Possible. Captive power plant provided. Power failure 1. No GEB supply. 2. Sudden failure in the electrical system. Process Disturbance
Prepared By Kutch Chemical Industries Ltd. Page : 82 HSE Department Rev. : 00