ID Task

Mode
Task Name Duration Start Finish Total Slack Successors Resource
Names
1
GLOBAL VILLA 107 days Sun 6/1/14 Mon 10/6/14 0 days
2
PRE-CONSTRUCTION 37 days Sun 6/1/14 Sun 7/13/14 1.2 days
3
INITIATION 7 days Sun 6/1/14 Sun 6/8/14 0 days 4 MAN
4
PLANNING 30 days Tue 6/3/14 Sun 7/13/14 1.2 days 6 MAN[200%]
5
CONSTRUCTION 72 days Mon 6/30/14 Wed 9/24/14 0 days
6
EXECUTION 60 days Mon 6/30/14 Wed 9/24/14 0 days 7SS+5 days,9 MAN[400%],MACHINE[200%],MATERIAL[10]
7
CONTROLLING 60 days Sun 7/6/14 Tue 9/16/14 7 days 9 MAN
8
POST CONSTRUCTION 10 days Thu 9/25/14 Mon 10/6/14 0 days
9
CLOSING 10 days Thu 9/25/14 Mon 10/6/14 0 days MAN
19%
84%
100%
80%
1%
2%
0%
0%
0%
May Jun Jul Aug Sep Oct Nov
Project1
Page 1
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Project1
Page 2