Schedule Steel Structure
Schedule Steel Structure
Schedule Steel Structure
Task Name
Duration
Start
Finish
9/30
184 days
Wed 10/9/13
Sun 4/13/14
184 days
Wed 10/9/13
Sun 4/13/14
Shop Drawing
14 days
Wed 10/9/13
Wed 10/23/13
Material Supply
30 days
Thu 10/24/13
Fri 11/22/13
Steel Fabrication
60 days
Sat 11/23/13
Thu 1/23/14
Delivery
60 days
Fri 1/24/14
Mon 3/24/14
Preparation
7 days
Thu 2/6/14
Wed 2/12/14
Steel Erection
60 days
Thu 2/13/14
Sun 4/13/14
Task
Progress
October
November
10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2
10/9
December
12/9 12/16 12/23 12/30
1/6
January
1/13 1/20
1/27
2/3
February
2/10 2/17
2/24
3/3
March
3/10 3/17
3/24
3/31
4/7
April
4/14
10/23
10/24
11/22
11/23
1/23
1/24
3/24
2/6
2/12
2/13
Summary
Page 1
4/13