Sr # Activity

1 Architecture Re-vamp
2 Hardware Procurement
3 Web Server Replication
4 DB Rationalization
Current Status
Current Status
> T0-BE Architecture has been finalized , development will start from 14th April
> Hardware has been finalized, actual cost (quotation from sourcing) awaited
> Implementation has been completed (handed over to Ops)
> Deployment will be carried out in the next possible outage window
> Working has been completed (hander over Ops)
> Activity will be carried out by 17th April
Status
Delay of 2 Weeks
Delay of 2 Weeks
In-progress
In-progress
Med
After doing re-analysis on this activity it was agreed among the stakeholders to cancel this activity.
Target after this patch was to achieve expiry job execution to 45 min from 4 hours.