Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

1.

The factors that will be used for pre-qualification of bidders for construction project are:
a. experience,
b. financial stability,
c. quality performance,
d. manpower resources,
e. equipment resources,
f. Current workload.




2. This table contains the performance criteria and scores for four potential suppliers to Kramerica
Industries. Evaluate the data and identify the best source for Kramerica.
Performance
Dimension
Company
A
Company
B
Company
C
Company
D
Quality (W=0.4) 3 4 2 5
Cost (W=0.3) 4 3 5 3
Flexibility (W=0.2) 5 3 4 2
Speed (W=0.1) 2 5 5 4
3. This table contains a list of three companies that have been rated on four weighted performance
dimensions. Which of the following statements regarding this information is best?
Performance Strickland Thatherton Mega-Low Amerigas
Dimension
Quality (W=0.5) 4 4 2 4
Cost (W=0.4) 4 3 5 3
Speed (W=0.1) 2 2 4 5