OPTION WORKSHEET: LONG TERM OPTIONS

VALUING AN OPTION TO ABANDON A PROJECT


This program calculates the value of an abandonment option.
Inputs relating the underlying asset
Enter the present value of cash flows from continuing project = $254.00 (in currency)
Entet the annualized standard deviation in ln(present value of CF) 30.00% (in %)
Enter the remaining life of the project = 25 (in years)
Enter the value received on abandonment = $150.00 (in currency) (Net out any abandonment costs)
Enter the number of years that you have rights to abandon project 10 (in years) (< or = project life)

General Inputs
Enter the riskless rate that corresponds to the option lifetime = 7.00% (in %)

VALUING A LONG TERM OPTION/WARRANT


Stock Price= $254.00 T.Bond rate= 7.00%
Strike Price= $150.00 Variance= 0.09
Expiration (in years) = 10 Annualized dividend yield= 4.00%
OPTION WORKSHEET: LONG TERM OPTIONS

d1 = 1.35
N(d1) = 0.91

d2 = 0.4
N(d2) = 0.65

Value of Option to Abandon = $10.56