Power Plants in Tamil Nadu

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

No.

Developer Area
1 TNEB (Tamil Nadu Electricity Board) Athipattu
2 TNEB (Tamil Nadu Electricity Board) Ennore
3 TNEB (Tamil Nadu Electricity Board) Mettur
4 TNEB (Tamil Nadu Electricity Board) Tuticorin
6 NLC (Neyvelli Lignite Corporation) Neyvelli
7 TNEB (Tamil Nadu Electricity Board) Mettur
8 NCTPS (North Chennai Thermal Power Station) Mettur/Salem
9 UDI Infrastructure Nagapattinam
10 Coastal Energen Pvt Ltd Tuticorin
11 PEL Power Pvt Ltd Nagapattinam
12 NSL Power Pvt Ltd Nagapattinam
13 SRM Energy Ltd Cuddalore
14 Cuddalore Powergen Corporation Ltd Cuddalore
15 Ind-Barat Power Pvt Ltd Tuticorin
16 Sri City Infrastructure Dev Ltd Tuticorin
17 Apollo Infrastructure Project Finance Pvt Ltd Marakkanam
18 Kuruvimedu Thermal Power Kuruvimedu
19 Ramanathapuram Power Ramanthapuram
20 McNamara International Pvt Ltd Nagapattinam
21 ETA Star Energy Pvt Ltd
22 GEMAC Energy Ltd (GEL)
23 NTPC/TNEB Joint Venture Vallur
24 Kattupalli Thermal Power Kattupalli
25 NTPL Tuticorin
26 Udangudi Power Trichendur
27 Cheyyur Ultra Mega Power Cheyyur
28 Ultra Mega Power Nagapattinam
29 Jayamkondam Power
30 Neyveli TPS III Power
31 Ennore Power
32 Manali Power
33 Chengalpet Power
34 NTPC Thermal Power Marakkanam
Capacity COD
630MW
Phase 1 (1 x 210MW) - Oct 1994
Phase 2 (1 x 210MW) - Mac 1995
Phase 3 (1 x 210MW) - Feb 1996
450MW
Phase 1 (1 x 60MW) - Mac 1970
Phase 2 (1 x 60MW) - Feb 1971
Phase 3 (1 x 110MW) - May 1972
Phase 4 (1 x 110MW) - May 1973
Phase 5 (1 x 110MW) - Dec 1975
840MW
Phase 1 (1 x 110MW) - Jan 1987
Phase 2 (1 x 110MW) - Dec 1987
Phase 3 (1 x 110MW) - Mac 1989
Phase 4 (1 x 110MW) - Mac 1990
1050MW
Phase 1 (1 x 210MW) - Jul 1979
Phase 2 (1 x 210MW) - Dec 1980
Phase 3 (1 x 210MW) - Apr 1982
Phase 4 (1 x 210MW) - Mac 1991
Phase 5 (1 x 210MW) - Feb 1992
2490MW
Phase 1 (6 x 50MW) & (3 x 100MW) - Jul 1962
Phase 2 (7 x 210MW) - Sep 1970
600MW Phase 1 (1 x 600MW) - Oct 2013
1200MW
Phase 1 (1 x 600MW) - Mac 2014
Phase 2 (1 x 600MW) - May 2014
1980MW Phase 1 (3 x 660MW)
1200MW Phase 1 (2 x 600MW)
1050MW Phase 1 (3 x 350MW)
1500MW Phase 1 (2 x 600MW)
2000MW
1320MW Phase 1 (2 x 600MW)
1320MW
1000MW
2000MW
1000MW
1000MW
2000MW
1200MW
600MW
1500MW Phase 1 (3 x 500MW)
1600MW
1000MW Phase 1 (2 x 500MW)
1600MW Phase 1 (2 x 800MW)
4000MW
4000MW
1600MW
1000MW
1885MW
842MW
630MW
2000MW
Remarks
Initial COD for all units was to be achieved by August 2011
Plant was to be set up by 2012. Includes a 1000 m3 per day
desalination plant and a 2500 acre of land consisting of
township, schools, collegs and hospitals
Phase 1 to be commissioined by the end of 2015
PPA signed with Tata Power Company for entire power offtake
PPA has been signed with TNEB (Tamil Nadu Electricity Board)
in September 2006
COD targetted for September 2012
Feasibility study completed. EIA in progress
COD targetted for August 2012
COD to be achieved by September 2013