Professional Documents
Culture Documents
Task Pricing
Task Pricing
Time (hrs)
Phase I Research
Task 1 Identify Property 3
Task 2 Visit Site 14
Task 3 Obtain Relevant Documents 15
Task 4 Research Relevant Codes and Requirements 32
Task 5 Research Environmental Impact 4
Total 68
Phase II Develop Alternatives for Site Use
Task 1 Identify and Analyze Land Use Options 10
Task 2 Develop Preliminary Alternatives 78
Task 3 Establish Criteria and Evaluate Alternatives 12
Task 4 Formulate Recommendation 8
Task 5 Present Preliminary Alternatives to Client for Selection 8
Total 116
Phase III Finalize Design
Task 1 Design Water and Fire Protection Delivery 21
Task 2 Design Wastewater Retention Removal 21
Task 3 Design Energy Delivery 21
Task 4 Develop Road Specifications 21
Total 84
Phase IV Project Presentation
Task 1 Present Design at Engineering Days 48
Task 2 Give Final Presentation 16
Task 3 Present Final Report 16
Task 4 Delivery of Final Design to Client 8
Total 88
Total Project 356
75/hr
100/hr
100/hr
75/hr