DSOA VILLA COMPLEX - PHASE III (P-048/B)

CONSTRUCTION OF 160 VILLAS COMPLEX


WEEKLY PROGRESSSUMMARY
28 J uly 2014
CONTRACT DATA
PARTY NAME REPRESENTATIVE
Client : DUBAI SI LI CON OASI S Mr.ALI AL BEDAI WEI
Consultant : ARCHGROUP Mr. MANOJ G.
Contractor : ARABTEC CONSTRUCTI ON L.L.C. Mr. BASSAM AL SAHO
CONTRACT PERIOD
(DAYS)
COMPLETION DATE TIME ELAPSED
ORIGINAL REVISED ORIGINAL REVISED PLANNED ACTUAL DAYS PERCENTAGE
CLUSTER 'P'
(14)
8.75% 1-J ul-13 244 - 1-Mar-14 - 100.00% 100.00% 0.00% 393 161.07%
CLUSTER 'Q' & 'M'
(78)
48.75% 1-J ul-13 366 1-J ul-14 100.00% 99.84% -0.16% 393 107.38%
CLUSTER 'N' & 'O'
(68)
42.50% 1-J ul-13 428 - 1-Sep-14 - 97.75% 74.27% -23.48% 393 91.82%
GRAND TOTAL 100.00% 1-J ul-13 428 1-Sep-14 99.04% 88.99% -10.06% 393 91.82%
POINTSTOBE MENTIONED:
1). Theprogress Updateis Based on BaselineProgrammeRev. 01, dated 29.08.13
POTENTIAL RISK
Sr. No. Action by Duedate
CONFLICTSWITH OTHER SUBCONTRACTORS
Description
AHEAD /
DELAY
SECTION
PERCENT
CONTRIBUTION
START
DATE
WORK PROGRESS
Page 1 of 1 SUMMARY