Professional Documents
Culture Documents
Test CERC
Test CERC
Test CERC
960 mw Sasan project in Madhya Pradesh could not achieve its "full load" in Marc
h 2013 and rejected its plea to appoint an independent technical panel to look i
nto the readiness of that unit.
"We do not find any requirement to constitute a committee as suggested by the pe
titioner in view of our finding that the unit-3 (first unit of the Sasan project
) of the generating station was unable to achieve its full load on March 31, 201
3," the Central Electricity Regulatory Commission said in an order.