1. The float switch at mixing tank will detect low level. The solenoid valve (SV) will open
and the milk will feed into mixing tank from milk tank.
2. The milk will feed into mixing tank until float switch detect high level. The solenoid
valve (SV) will close when reaches high level and heater will on. It will heat up and
maintain the temperature at 80C.
3. The temperature transmitter (TT) will send the signal to the temperature indicator
(TIC).
4. After temperature reaches 80C, Dosing Pump 1 (DP 1) on and inject 123ml of citric
acid into mixing tank. After injecting, Dosing Pump 1 (DP 1) will off and Dosing Pump
2 (DP 2) on.
5. Dosing Pump 2 (DP 2) will inject 223ml into tank. After injecting, Dosing Pump 2 (DP
2) will off and the agitator will on for mixing.
6. After 30 minutes, the agitator will stop mixing and heater will off. The ball valve will
open.
7. The mixture will go to through filtering process. This is where the curd and whey will
be separated in filter tank.
8. After 2 minute, the Ball Valve (BV) will close and pneumatic arm and screw conveyor.
9. After curd flow through the screw conveyor, it will go to the product tank.
10. After 5 minute, the pneumatic arm and extruder will off.