STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500-
NTPC REF NO: SIM/1/TS/ /
SHEET 1 OF 3 PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE : 500 MW STEAM TURBINE GENERATOR 1. PLANT DETAILS GENERATOR SYSTEM CONSISTS OF TURBOGENERTOR, EXCITER, GENERATOR PROTECTION, EXCITATION CONTROL SYSTEM. NAME PLATE DETAILS RATED DATA & O/P TURBO GEN. MAIN EXCITER PILOT EXCITER APPARENT POWER 588 MVA ------ 65 VA ACTIVE POWER 5!! MW "#8! W ------ CURRENT 16166 A 6"!! A 1$5 A VOLTAGE %1 & 1.!5 V 6!! V %%! & %% V FRE'UENCY 5! () ------ *!! () PF !.85+LAG, ------ ------ STATOR WDG CONN YY ------ ---- (YDROGEN PRESS ".5 BAR ----- ----- CONT PERM UNBAL LOAD 8 - ------ ------ RATED FIELD VOLTAGE CURRENT "*! V *!*! A ------ ------- %. TESTING OB.ECTIVE TO TEST T(E C(ARACTERISTICS OF GENERATOR AND REACTIVE CAPABILITY RESPONSES OF GENERATOR. /, MEASUREMENT OF WINDING , INSULATION RESISTANCE //, OPEN & S(ORT CIRCUIT C(ARACTERISTICS ///, REACTIVE CAPABILITY CURVE RESPONSE C(ECING ".PROPOSAL I S(ORT CIRCUIT C(ARACTERISTIC GENERATOR P(ASE TERMINALS ARE S(ORTED TOGET(ER. MAC(INE IS EXCITED AT T(E FULL SPEED OF PRIME MOVER+STEAM TURBINE,. A C(ARACTERISTIC CURVE IS PLOTTED BETWEEN EXCITATION CURRENT AND GENERATOR CURRENT II OPEN CIRCUIT C(ARACTERISTIC GENERATOR P(ASE TERMINALS ARE OPENED AS USUAL. MAC(INE IS EXCITED AT T(E FULL SPEED OF PRIME MOVER+STEAM TURBINE,. A C(ARACTERISTIC CURVE IS PLOTTED BETWEEN EXCITATION CURRENT AND GENERATOR TERMINAL VOLTAGE. GENERATOR PROTECTIONS ARE ONE-BY-ONE T(ROUG(LY C(ECED. GENERATOR PT0 ARE P(ASE IN-P(ASE OUT WIT( GRID /v!/"""/##$/%&'v(!$)&'/*+#/$%!*%,-1/./.5//03012&% STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500- NTPC REF NO: SIM/1/TS/ / SHEET . OF 3 PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE : 500 MW STEAM TURBINE GENERATOR PT0. WIT(IN PERMISSIBLE LIMITS OF VOLTAGE DIFFERENCE +*-, & FRE'UENCY +!.1 (1, ,GENERATOR IS SYNC(RONISED WIT( GRID. *.SERVICES RE'UIRED GENERATOR CIRCUIT BREAER,EXCITATION SYSTEM,FIRE PROTECTION SYSTEM,%%! V DC SUPPLY,DM CW SYSTEM, LUBE OIL SYSTEM,AUX COOLING WATER SYSTEM,(YDROGEN COOLING SYSTEM, GENERATOR PROTECTION SYSTEM 5.! SAFETY PRECAUTIONS I, FIRE EXTINGUIS(ER SYSTEM2S READINESS II, GENERATOR CABIN IS TO BE LOCED AND INSPECTION WINDOW MUST BE GLASS COVERED. III, 3GENERATOR ONLINE/DANGER %1 V2 CAUTION BOARD TO BE FIT IV, MEN & MATERIALS TO BE EPT AWAY FROM GENRATOR 6. EMERGENCY PROCEDURE GENERATOR TO BE TRIPPED. EXCITATION & GENERATOR TRANSFORMER BACC(ARGING TO BE PUT OFF. CO % WILL BE RELEASED ON FIRE DETECTION. #. STATE OF T(E PLANT AFTER T(E ERECTION OF GENERATOR,(% GAS TO BE FILLED IN T(E ROTOR AFTER PASSING T(E (YDROGEN LEAAGE SYSTEM.COOLING SYSTEM TO BE IN CIRCULATWED MODE. BEARING COOLINGS TO BE ENSURED.POWER & CONTROL CIRCUIT OF GENERATOR & EXCITATION SYSTEM TO BE VERIFIED. FIRE PROTECTION SYSTEM EPT READY. 8. COMMISSIONING PROCEDURE C(EC T(E POLARISATION INDEX & WINDING RESISTANCE VALUES OF GENERATOR ARE WIT(IN T(E PERMISSIBLE LIMITS AS PER STANDARD. NO PROTECTION OPERATED .EXCITATION SYSTEM IS READY FOR GIVING FULL EXCITATION. T(EN DO T(E PROCEDURES AS IN SEC ".! $. COMPLETION CRETERIA GENERATOR IS WIT(STANDING FULL LOAD WIT( PERMISSIBLE VARIATION OF ITS PARAMETERS LIE WINDING TEMP,FRAME TEMP ETC. TRIAL RUN OF GENERATOR IS SUCESSFULLY COMPLETED /v!/"""/##$/%&'v(!$)&'/*+#/$%!*%,-1/./.5//03012&% STATION: NTPC SIMHADRI BHEL REF NO : PS-DC-186-500- NTPC REF NO: SIM/1/TS/ / SHEET 3 OF 3 PLANT AREA : ELECTRICAL SYSTEM TESTING SCHEDULE : 500 MW STEAM TURBINE GENERATOR 1!. APPENDICES DRAWINGS4 O & M MANUAL OF GENERATOR,EXCITATION SYSTEM SC(EMATIC DRAWINGS OF STATOR COOLING,(% FILLING SYSTEM LOG S(EETS 4 I, IR VALUES,WR VALUES OF GENERATOR II, OCC,SCC TEST REPORTS III, LIST OF PROTECTIONS INCLUED IV, READINESS OF AUX SYSTEMS ---------------------------- 5 --------------------5 ----------------- /v!/"""/##$/%&'v(!$)&'/*+#/$%!*%,-1/./.5//03012&%