SAP LTP Business Process - Cycle
SAP LTP Business Process - Cycle
SAP LTP Business Process - Cycle
A plannig scenario has to be created for a plant in T code MS31 & for the same
Planning scenario
configuration settings has to be made in OPU5 for the planned orders for LTP.
2.Requirements has to be given in MD61 in an inactive version and also after giv
ing the requirements
kindly remove the tick mark against version- active check box.
3.Assign this plan to the planning scenario in MS32,release it and ensure the pl
anning file entries are
entered or created,the same can be checked using MS21.
4.After taking LTP simulation run in MS02(individual material) or MS01 you can s
ee the simulated
planned orders obtained in MS04 T code.
5.These Simulated planned orders can't be converted into production orders or it
cant be used for any
business confirmation purpose.
6. For capacity planning analysis,use T Code CM38,
Before that Ensure for all the work centers in CR03 which are used for operation
under capacity header
you have included the check box for Long term planning,otherwise in CM38 you can
't see any capacity
requirements data.
7.Before executing CM38,ensure under settings---> general you are giving the per
iod settings properly.
********************************************************************************
***************************************************************
Production Types:-
Discrete Manufacturing
EE Repetitive manufacturing
EE Process Manufacturing
EE Kanban
EE Engineer-to-Order Production
********************************************************************************
****************************************************************