Note for approval
Sub: Extension of service validity of M/s Jai Amarnath Construction.
Ref: WO no. 3200002153, dated 13.07.12
Validity and nature of work: 31.12.2013, laying of MS pipe at new ash dyke.
With respect to above subject regarding extension of validity of M/s Jai Amarnath construction, we wish
to bring your notice that M/s Jai Amarnath construction have already started the laying of MS pipe since
Jul13, due to delay in opening of fronts clearance in new ash dyke, ash slurry pipe line work has been
extended from time to time.
Therefore it is proposed to extend the completion period as mentioned below.
M/s Jai Amarnath construction, shall laying complete slurry piping with processing of bill within 31
st
July, 14
Hence it is requested to extend the validity of Work Order.

Put up your approval please.



Govind Chaurasia Gyanendra Kumar
Sr. Engineer (AHP) AGM (AHP)


Ashok Singh Yadav
(GM BTG & BOP)


Naresh Goyal
(President Power)