No Pekerjaan Satuan Kuantitas Harga Satuan Jumlah Harga Umum

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

No

Pekerjaan

Umum
1 Mobilisasi dan Demobilisasi
2 Pekerjaan Sondir

Satuan

Kuantitas

Harga Satuan

Jumlah Harga

Ls
Titik

1.00
1.00

10,000,000.00
10,000,000.00

10,000,000.00
10,000,000.00

Pekerjaan Tanah
Galian Tanah
Urugan Kembali
Dewatering
Cerucuk Bambu

m3
m3
Ls
m

1.00
1.00
1.00
1.00

35,000.00
45,000.00
25,000,000.00
10,000.00

35,000.00
45,000.00
25,000,000.00
10,000.00

Pekerjaan Struktur
1 Beton K-350
2 Pasangan Batu Bata
3 Water Stop

m3
m3
m

1.00
1.00
1.00

2,500,000.00
700,000.00
200,000.00

2,500,000.00
700,000.00
200,000.00

Pekerjaan Lain-Lain
1 Pemindahan

Unit

1.00

50,000,000.00

50,000,000.00

1
2
3
4

TOTAL

98,490,000.00