ID Task

Mode
Task Name Duration Start
1 PHASE I -Project Proposal 16 days Aug 18 '14
2 Brainstorming 1 day? Aug 19 '14
3 Data Collection 3 days Aug 20 '14
4 Codes, laws and legislation3 days Aug 20 '14
5 Features in the building 3 days Aug 20 '14
6 Justification 3 days Aug 20 '14
7 Data compilation 3 days Aug 20 '14
8 Data Analysis 6 days Aug 25 '14
9 Master Map Preparation 5 days Aug 25 '14
10 Boundaries 1 day? Aug 25 '14
11 Position of structure 4 days Aug 25 '14
12 Vehicular Network 4 days Aug 25 '14
13 M&E Scheduling 1 day Aug 29 '14
14 Cost Estimation 4 days? Aug 25 '14
15 Discussion 1 day? Sep 1 '14
16 Report Writing 11 days Aug 22 '14
17 Cover 1 day? Sep 1 '14
18 Table of Content 1 day? Sep 5 '14
19 Introduction 3 days Aug 25 '14
20 Literature Review 10 days Aug 22 '14
21 Limitation 3 days Aug 25 '14
100%
60%
75%
15%
10%
100%
0%
0%
0%
0%
10%
0%
0%
0%
0%
0%
S M T W T F S S M T W T F S S M T W T F S S M T W T
Aug 17, '14 Aug 24, '14 Aug 31, '14 Sep 7, '14
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Critical
Critical Split
Late
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Final Proposed Workplan
Page 1
ID Task
Mode
Task Name Duration Start
22 Methodology 2 days Aug 28 '14
23 Results 3 days Aug 28 '14
24 Conclusion 1 day Sep 2 '14
25 Recommendation 1 day Sep 4 '14
26 Appendices 1 day Sep 4 '14
27 References 10 days Aug 22 '14
28 Submission 3 days Sep 4 '14
29 Proof Read 2 days Sep 4 '14
30 Compilation 2 days Sep 4 '14
31 Print and Sign 2 days Sep 4 '14
32 Handing over 1 day Sep 8 '14
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S M T W T F S S M T W T F S S M T W T F S S M T W T
Aug 17, '14 Aug 24, '14 Aug 31, '14 Sep 7, '14
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Critical
Critical Split
Late
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
Final Proposed Workplan
Page 2

You might also like