S.

No Activity Name Works Included


Duration
(days)
Number of lamps connected
Wattage of lamps
Type of Lamps(MH/HPSV)
Load Cpacity & Phase(1-Ph,3-Ph)
To Fix Junction Box
To give Incoming and Outgoing cable
connections
To Set bulbs ON & OFF time
Observation To Monitor readings of available chokes 5
To Replace available choke with Ballast
To give cable connections
Observation To Monitor readings of ballasts 5
4
If any Technical problems
occure after installation
Like cable burn & any Leakages 3
5
To recollect chokes with
Department approval
To remove all the cable connections &
handovering chokes with approval
3
20 Total Days required to complete pilot project
1
2
3
Pilot Project Completion Schedule
Installation of Automation
System
1
2 Installation of Ballast
1 Site inspection