Tg-374 18.625in Cement Rev No. 1
Tg-374 18.625in Cement Rev No. 1
Tg-374
9. November 2011
18-5/8in Casing Inner String Cement Job
Operational Objectives:
o
Operational Hazards:
o
o
Pumping cement stinger out of shoe (i.e. use HWDP to mitigate risk)
Cement stinger seals leaking
Well Status:
o
o
o
o
o
o
o
o
o
o
Operations
1. Weld 20-3/4in wellhead assembly to landing ring with 4 x 6inch
strips.
o
o
o
o
o
o
Cement stinger assembly: Stab-in sub, 3x stands 5in HWDP, 1 x stand 5 dp, 1
single 5in DP + 1 x 1.67m pup joint, Side Entry Sub, TIW Valve, handling pump
joint.
Make up Side entry sub assembly connections before stabbing into shoe with
stinger.
Orientate side entry sub to face cement manifold
8. RIH and land stinger into stab-in shoe (at top of shoe) at 123.7 m
with 3 tons
o
o
o
Do not allow the cement string to turn once stabbed into shoe. This will damage
the seals.
Do not pick up out of the shoe, this can damage or roll the seals.
Install Lo torque valve on the cementing side entry sub.
11.
Circulate 2 x OH Annulus volumes (190 bbls) with rig pumps
at 250gpm.
o
12.
Close TIW valve and apply 200psi behind with the rig
pumps.
13.
Put VARISCO Pump discharge hose directly to waste pit (bypassing shakers).
14.
15.
Dowell flush through line with water and pressure test line against lo torque
valve 300/2000psi 5/5mins.
16.
Dowell pump according to the following schedule at
5bbls/min:
50bbls Water ahead
137 bbls 1.50sg Lead Slurry
66 bbls 1.90sg Tail Slurry
2
Observe at wellhead for returns at all times. Notify company man if returns are
lost.
Have CemNet ready for addition in case of lost returns while pumping cement.
Notify company man if returns come up through 18-5/8in x 5in annulus.
Keep samples of cement pumped, 2 at start of cement job and 2 at end of
cement job and 2 from the returns at the cellar at the end of the job.
17.
Bleed off pressure and check for backflow. If no backflow,
proceed with the following:
18.
Close Lo-Torque Valve and break off cement line. Open Top
Drive IBOP.
19.
20.
21.
22.
Line up rig pump and flush cmt stinger with 50 bbls mud at
700gpm through Top Drive.
23.
24.
25.
26.
Pick up Side Entry Sub assembly, break out and lay down
SES and pup joints.
Next Operation: Install side outlet valves - Nipple up 21-1/4in
Diverter system. Drillers instruction will follow.
Thanks,
JV Gas Team
09.11.2011