Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

__________________________________________________________________________________________________________________________

Bill de Blasio Dr. Feniosky Pea-Mora


Mayor Commissioner



Weekly Construction Bulletin
Broad Channel Reconstruction Project- Queens, NY
Project # HWQ1182A
Monday, 9/29/2014
Office of Community Outreach and Notification
The following is the anticipated construction work schedule, field conditions permitting for next week. Please
note that parking may be restricted in work area. Advance notification will be given.


Date Location Operation Work Hours
9-29-14 to
10-3-14
End of West 11
th
and West 13
th
Road
at Jamaica
Review of cofferdam plan to assess
impact on private property
7 AM to 6 PM

NOTES:
WATER SHUT-OFF NOTIFICATIONS: In addition to a 72- hour Advisory, a prior 24-hour notification will be distributed/posted to any/all affected
location(s).
NO PARKING SIGNS: will be distributed/posted 72-hours prior to the temporary elimination of street parking. Please observe posted parking regulations
in construction areas.

FOR FURTHER INFORMATION: Contact Fern Weinreich, the Community Construction Liaison at 516-361-8822 or email:
broadchannelccl@gmail.com. Website: www.nyc.gov/DDC Video: http://www.nyc.gov/webuild


We thank you in advance for your cooperation during this construction project.

You might also like