Aftermath

Section number to go here


Date 00.00.00 Presentation title to go here 2
Aftermath
7 people dead in total
71 injured
Aftermath
Investigations by the British transport police and HSE
Victims of the incident called for a public inquiry but were never
given one
20% of points in the area found to have loose bolts
HSE told railtrack to review the design of them
Jarvis and railtrack found to be at blame
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 3
Aftermath
Jarvis fined 12 million, plus the loss of contracts
Network rail fined 3 million in 2011
Physical costs not stated
Date 00.00.00 Create your footer by changing copy in the Header and Footer section 4
Aftermath
Railtrack took most of the maintenance in house
A review of the design of the points was carried out
Standard of the points improved

Date 00.00.00 Create your footer by changing copy in the Header and Footer section 5
Date 00.00.00 Presentation title to go here 6 6
Aftermath
Bolts in adjustment bars not
being fitted found to be the
cause
This was because Jarvis had
a poor maintenance routine
Also partly railtracks fault for
giving wrong instruction
Could have been avoided by
regular visual inspection by
Jarvis and correct information
given by railtrack