DAKSHIN HARYANA BIJLI VITRAN NIGAM

Instruction No. 32 /2007/P&D



From
The Chief Engineer/P&D,
DHBVN, Hisar.

To

All C.E.s(OP) in DHBVNL,
All S.E.s(OP) in DHBVNL.

Memo No.Ch. 112/ DD-169
Dated: 11.01.2007

Subject: Norms for erection charges and various over-head
charges for preparing cost estimates for turnkey works and departmental
works.
Produced below are the norms for erection charges and various over-head
charges for preparing cost estimates for turnkey works and departmental works
for information and further necessary action at your end:-
1 Cost of material As per the rates circulated by CE(P&D).
Such rates are to be revised on quarterly
basis by the office of CE(P&D).
2 Erection charges 10% on the cost of material
3 Overhead charges
i) Transportation charges 2.5% on the cost of material
ii) Service Tax 1.83% on the cost of material
iii) Contingency charges 3% on the cost of material
iv) T& P charges 1% on the cost of material
v) Insurance & handling
charges
0.67% on the cost of material
vi) Contractor profit &
Supervision etc.
6%
Total overhead charges 15% on the cost of material

All the previous instructions/ Orders stand superseded by this above
instruction.
The above instruction be considered with immediate effect.
Superintending Engineer/P&D,
For Chief Engineer/ P&D,
DHBVN, Hisar.

Copy to the:

1. Sr. P.S. to M.D., DHBVNL, Hisar for kind information of the M.D.
2. Sr. P.S. to Director, (OP)/Projects, DHBVNL, Hisar for kind information of
the Directors.
3. Chief Engineer / MM, DHBVNL, Hisar..
4. G.M./Commercial, DHBVNL, Hisar.
5. CE/PD&C, UHBVN Panchkula.
6. FA&CAO/MM, DHBVN, Hisar.
7. FA(HQ), DHBVN, Hisar.

You might also like