SL

NO
ACTIVITY REMARKS
1
Approved Drawing required for main girder
fabrication.
2 WPS & PQR Available
3 WELDER QUALIFICATION Available for 2 Welders
4 PL.40mm - MTC Verification TC Required
5 PL.40mm - Marking, Preheating & cutting Thermal chalk (100C) - required.
6 PL.40mm - Edge grinding & Bevelling (as per drg.) Template required.
7 Alignment & fitup
8
Electrode baking at 250C for 2Hrs & Portable oven
shall be kept ready for use.
E7018 - 2.5, 3.15 & 4.0mm
9
Preheating & interpass temp. maintainence(100C) &
root welding(E7018)
Thermal chalk (100C) & DP Test kit
required
10 Back grinding & DP Test
11 Sequential Welding completion on both sides
12 Cleaning, grinding & straightening
13 ULTROSONIC Test UT Equipment required
14 Holes marking & drilling for plug welding Drilling m/c required.
15 40mm Plate fitup with main girder flange
16 Preheating & plug welding
17 Fillet root welding & random LPI
18 Stiffener fitup & welding
19 Cleaning & grinding