P&T Co. Distribution Problem
Unit Cost Destination (Warehouse) Range Name Cells
Joka Behala Tollygunge Jadavpur Demand D18:G18
Source Park Street 464 513 654 867 ShipmentQuantity D12:G15
(Cannery) Howrah 352 416 690 791 Supply J12:J15
Rajarhat 995 682 388 685 TotalCost J18
Dummy 0 0 0 0 TotalReceived D15:G15
TotalShipped H12:H15
Shipment Quantity Destination (Warehouse) UnitCost D5:G8
(Truckloads) Joka Behala Tollygunge Jadavpur Total Shipped Supply
Source Park Street 0 20 0 50 70 = 70
(Cannery) Howrah 80 45 0 0 125 = 125
Rajarhat 0 0 70 30 100 = 100
Dummy 0 0 0 5 5 5
Total Received 80 65 70 85
= = = = Total Cost
Demand 80 65 70 85 148,200
P&T Co. Distribution Problem
Unit Cost Destination (Warehouse)
Joka Behala Tollygunge Jadavpur
Source Park Street 464 513 654 867
(Cannery) Howrah 352 416 690 791
Rajarhat 995 682 388 685
Dummy 0 0 0 0
Shipment Quantity Destination (Warehouse)
(Truckloads) Joka Behala Tollygunge Jadavpur Total Shipped
Source Park Street 0 20 0 50 70 =
(Cannery) Howrah 80 45 0 0 125 =
Rajarhat 0 0 70 30 100 =
Dummy 0 0 0 5 5 =
Total Received 80 65 70 85
= = = =
Demand 80 65 70 85
Range Name Cells
Demand D18:G18
ShipmentQuantity D12:G15
Supply J12:J15
TotalCost J18
TotalReceived D15:G15
TotalShipped H12:H15
UnitCost D5:G8
Supply
70
125
100
5
Total Cost
148,200