Professional Documents
Culture Documents
HPQC Q&a - Tarakesh
HPQC Q&a - Tarakesh
HPQC Q&a - Tarakesh
tarakeshsaptesting@gmail.com
Page 1
TARAKESH
Test Resources: Enables us to manage test resources in a hierarchical tree structure. Tests resources can
be associated with tests.
Test lab: Enables us to run tests and analyze the results.
Defect Module: Helps us to report defects, determine, repair priorities and reopen defects.
Dashboard: Helps to create graphs, reports and excel reports.
Test Table
Test Step Table
Test Set Table
Run Table
Defect Table
Requirement Table
Convert Requirement to test: convert requirement to test in a specified subject in the test plan tree. We can
convert selected requirement or all requirements in the requirements tree.
Generate a test from requirements: convert requirement to a test in a specified subject in the test plan tree
and a specified test set in the Test Lab modules. This method enables us to quickly run a test when
analyzing our requirements.
tarakeshsaptesting@gmail.com
Page 2
TARAKESH
Delete only Test Runs: In this we can select a period of time before which we want to delete test run result
Delete only Run Steps: In this we can select a period of time before which we want to delete run steps.
tarakeshsaptesting@gmail.com
Page 3
TARAKESH
create a list of available host for test execution and also organize hosts into groups to be used for a specific project.
Following condition must be kept in mind before executing test on remote host:
1. QTP must be installed on each machine where you wish to execute the tests.
2. QTP must be configured to allow other HP products to run
3. QTP Connectivity add-in installed on both the Host (QTP) machines as well as the QC machine.
4. Define your host machines in the Host Manager of QC.
5. Ensure that Object Repositories and/or Function Libraries which are used by all scripts are 'shared' and accessible
from all machines.
Finding similar Defects: compare a selected defect with all other existing defects in project.
Finding similar Text: compare a specific test string against all other existing defects in project.
Adding Defects: After finding new defect we submit to QC project. The project stores defect information
that can be accessed by authorized users.
Reviewing New Defects: Reviewing all new defects and decide which one to fix.
Repairing Open Defects: Fix the Open defects.
Testing a New Application Build: Run test on the new build of the application.
Analyzing Defect Data: View Defect Report to see how many defects were resolved, and how many still
remain open.
tarakeshsaptesting@gmail.com
Page 4
TARAKESH
setting. We can apply filters and sort conditions, and display information according to our specification. Following
types are reports are available to us in QC:
Requirement Module Reports: Standard Requirements, Tabular, Requirement with coverage test,
requirement with Coverage test and Steps, requirement with linked Defects, requirements with Traceability,
report selected.
Test Plan Module Reports: standard test planning, subject tree, tests with design steps, tests with covered
Requirements, tests with linked Defect, report Selected,
Test Lab Module Reports: current test set, cross test set, test set Hierarchy with tests, cross test set with
tests, execution notification.
Defects Module Reports: standard Defects, Tabular defects, fixed or rejected Defects, report selected.
Requirement Module Graphs: requirements summary graph, requirements progress graph, requirements
coverage graph, requirements- trend graph, graph wizard.
Test Plan Module Graphs: test planning summary graph, test planning progress graph, test plan trend
graph, graph wizard,
Test Lab Module Graph: test execution summary graph( current test set), test execution progress
graph(current test set), test execution summary graph(cross test set), test execution progress graph(cross
test set) , graph wizard.
Defect Module Graph: defect summary graph, defect progress graph, defect age graph, defect trend graph,
graph wizard.
QC helps to maintain project database of test that covers all functionality of application.
QC offers integration with HP testing tools (WinRunner, QTP and Load Runner) as well as third party tools.
QC provides an intuitive and efficient method for scheduling and executing test sets, collecting test results,
and analyzing the data.
Qc helps in defect tracking, enabling to monitor defects closely from initial detection to resolution.
By linking QC to email system, defect tracking information can be shared by all application development,
quality assurance and customer support.
tarakeshsaptesting@gmail.com
Page 5
TARAKESH
Q18. How to map the requirements with test cases in Quality Centre?
For mapping the requirement with test cases we do:
1. In requirements tab select coverage view
2. Select requirement by clicking on parent/child or grandchild
3. On right hand side (In coverage view window) another window will appear. It has two tabs:
-Tests coverage
-Details
Test coverage tab will be selected by default or you click on it.
4. Click on select tests button a new window will appear on right hand side and you will see a list of all tests. You
cans elect any test case you want to map with your requirements.
Q21. What is difference between Generate Test from the requirements and Convert
requirements to test?
When we convert the requirements to test in a specified subject in the test plan tree where as in generating test case,
the test case generates from requirements are stored in a specified subject in a test plan tree and a specific test set
in Test Lab module. And by default we cannot generate a test for the following, which do not enable to coverage:
Business
Folder
Groups
tarakeshsaptesting@gmail.com
Page 6
TARAKESH
tarakeshsaptesting@gmail.com
Page 7