Materials On board
Scaffold Erected
Permit No
Start Date
WON
COMMENTS
ICC
Electrical Shutdown Activities
Electrical
820959 Instrument J/B JBD-402 Re-Placement 121578 21057 N/A Yes Shutdown Cupboard/Shelf 2
871913 Detailed Inspection DB-LPL 121524 21045 N/A N/A
696673 Replace Earth Fault Relays & CTs 121687 21086 N/A Yes Shutdown Cupboard/Shelf 2
871899 SD100 Protection Testing 121868 Per N/A N/A Switching Plans to complete
945596 Welding Ring Main Protection Testing 122376 21202 N/A N/A Switching Plans to complete
945611 3410 Auto Tx Protection Testing 122406 21203 N/A N/A Switching Plans to complete
945617 3420 Auto Tx Protection Testing 122408 21204 N/A N/A Switching Plans to complete
890130 3130 48" Caisson Pump Cable Conn/Re-Conn 122569 21255 N/A Yes Shutdown Cupboard/Shelf 1
890121 3140 48" Caisson Pump Cable Conn/Re-Conn 122570 21256 N/A Yes Shutdown Cupboard/Shelf 1
945681 48" Caisson Pump Protection Relay to Install Test 122458 21224 N/A Yes Shutdown Cupboard/Shelf 1
MCC9 Starter Handle Replacements Yes
Chloropack Fuse switch replacement Yes Shutdown Cupboard/Shelf 1
Page 1
PRIORITY SHUTDOWN LIST
Additions to Plan
898699 Teg Heater Control Pnl Pm 121828 21114 N/A N/A
TEG Heater Panel L6610 Electrical Components
945547 122339 21195 N/A Yes Parts in Gas Comp Sw/Room
Upgrade
773614 Gas Lft Control Pnl J6260 Inspection 121829 21115 N/A N/A
933180 Replace Distribution Cir Breakers 110V Ups Suite 122098 N/A Yes
Various TeroTech Workscopes Various N/A N/A See Workscope Folder
Dehydrator Transformers Removals Mod 2 See workscope/check ICC/Method statements
820969 Stream A Inst Workscope (Heat Trace) Remove/Replace permit
Vendor Required
ABB Protection Testing
Terotech Battery tests
Tyco Fire & Gas Pnl Self Test
Page 2