This document contains questions for a class test on project management. It asks the student to define key terms like dummy activity and different types of float. It also asks the student to list important parameters for project monitoring and control and the responsibilities of a project auditor. Additionally, it provides a sample project and asks the student to calculate the expected project duration and probability of completing the project within a certain time frame. Finally, it asks the student to discuss the importance of project audits and describe the project audit lifecycle as well as explain what a project management information system is and its functionality.
Term End Examination - May 2013 Course: MEE239 - Project Management Slot: B1+TB1 Class NBR: 1081 Time: Three Hours Max - Marks:100 PART - A (10 X 4 40 Marks) Answer ALL Questions
This document contains questions for a class test on project management. It asks the student to define key terms like dummy activity and different types of float. It also asks the student to list important parameters for project monitoring and control and the responsibilities of a project auditor. Additionally, it provides a sample project and asks the student to calculate the expected project duration and probability of completing the project within a certain time frame. Finally, it asks the student to discuss the importance of project audits and describe the project audit lifecycle as well as explain what a project management information system is and its functionality.
This document contains questions for a class test on project management. It asks the student to define key terms like dummy activity and different types of float. It also asks the student to list important parameters for project monitoring and control and the responsibilities of a project auditor. Additionally, it provides a sample project and asks the student to calculate the expected project duration and probability of completing the project within a certain time frame. Finally, it asks the student to discuss the importance of project audits and describe the project audit lifecycle as well as explain what a project management information system is and its functionality.
This document contains questions for a class test on project management. It asks the student to define key terms like dummy activity and different types of float. It also asks the student to list important parameters for project monitoring and control and the responsibilities of a project auditor. Additionally, it provides a sample project and asks the student to calculate the expected project duration and probability of completing the project within a certain time frame. Finally, it asks the student to discuss the importance of project audits and describe the project audit lifecycle as well as explain what a project management information system is and its functionality.
Answer all the question. Write the significance of Dummy activity. Distinguish between total float, free float and independent float. List important parameters for project monitoring and control. Find the responsibilities of project auditor. Define Capacity Planning.
[2 x5]
2. a) Find the responsibilities of Project Manager.
[4] b) A project has 8 activities and the time estimates corresponding to each activity is given below: Activity Immediate Activity Time (in weeks) Preceding Optimistic Most likely Pessimistic activity Time Time Time A 4 7 13 B A 6 9 11 C 5 7 9 D B,C 3 5 7 E B,C 7 8 10 F C 2 3 5 G D,F 6 7 8 H E,G 2 3 4 i. Find the expected duration of the project. ii. Compute the probability of completing the project in 35 weeks or less. [6] 3. a) Discuss the importance of Project Audit. Briefly explain the Project Audit Life-Cycle. [5] b) What is a Project Management Information System? Explain its functionality and utility. [5]
Term End Examination - May 2013 Course: MEE239 - Project Management Slot: B1+TB1 Class NBR: 1081 Time: Three Hours Max - Marks:100 PART - A (10 X 4 40 Marks) Answer ALL Questions