UPDATE

Connecticut Department of
Energy and Environmental Protection

Bashan Lake Dam Improvements


Update
Date November 08, 2014

Connecticut Department of Energy and Environmental Protection

Drawdown
09/22/2014 Gate Opening

11/07/2014 12.5 feet down

Connecticut Department of Energy and Environmental Protection

09/11/2014 - Bids open, apparent low bidder


09/22/2014 - Bashan Lake Dam gate opened
10/23/2014 - Contract signed with DAmato
Construction Company, Inc.
11/05/2014 Contract approved and
Awarded. Notice To Proceed (NTP) issued.
Contractor mobilization
Connecticut Department of Energy and Environmental Protection

Boat Launch
09/29/2014 - 2 feet down

11/03/2014 11.2 feet down

Connecticut Department of Energy and Environmental Protection

Look Ahead
Weir boards to be installed in historic
cofferdam upstream of dam structure week of
11/17/2014.
Work will commence on the dam and gate
structure. New gate closure in March 2015
Work till completion of gate structure then
continue onto buttress wall downstream.
Boat launch work to commence in Spring 2015
Connecticut Department of Energy and Environmental Protection

Questions and Comments


Please contact Dan Biron at (860) 424-3892 or
dan.biron@ct.gov with any concerns.