Professional Documents
Culture Documents
PMP Cheat Sheet
PMP Cheat Sheet
PMP Cheat Sheet
Based on PMBOK V4
The reader is responsible to verify and confirm all information presented herein.
Human Resource Management
Organizational Structures: Functional, Matrix (weak, balanced,
Initiation
strong) , Projectized, Composite
Planning
Maslows Hierarchy of Needs: Physiological, Safety, Social, Self
Execution
-esteem, Self-actualization.
Monitor and Control
McGregor: Theory X, Theory Y.
Closing
Ouchi: Theory Z. Motivated by commitment, opportunity advancement.
Herzbergs Theory of Motivation: Hygiene factors, Motivating Agents.
Knowledge Areas
Leadership Styles: Directing, Facilitating, Coaching, Supporting,
Integration
Autocratic, Consultative, Consensus.
Scope Management
Project Manager Powers: Formal (legitimate,) Reward, Penalty
Time Management
(coercive), Expert, Referent.
Cost Management
Conflict Management: Withdraw (avoid), Smooth (accommodate),
Quality Management
Compromise, Force, Collaborate, Confront (problem solving.)
Quality Management
HR Management
Communications Management Ishikawa = Fishbone Diagram: cause and effect.
Pareto Diagram: Identify problems and frequency. 80/20 Rule.
Procurement Management
Flow
Charts; Control Charts.
Risk Management
Just in Time: Reduces inventory; requires additional quality control.
Professional Responsibility
Quality Theories: Kaizen (continuous improvement,) Six Sigma, TQM
(total quality management.)
Earned Value Management
Kaizen: Small improvements to reduce costs and improve consistency.
BAC = Budget At Completion
Deming Cycle: Plan, Do Check, Act.
EV = Actual % * BAC
Cost Management
PV = Planned % * BAC
Cost Estimating - Accuracy
AC = Sum of all incurred costs Rough Order of Magnitude (ROM): -50% to +100%
Budgetary: -10% to +25%
CV = EV - AC
Definitive: -5% to + 10%
SV = EV - PV
Risk Management
CPI = EV / AC
Risk Strategies (threats): Avoid, Transfer, Mitigate, Accept.
< 1 = Over Budget
Risk Strategies (opportunities): Exploit, Share, Enhance, Accept.
> 1 = Under Budget
Qualitative Risk Analysis: Chance and impact of risk occurrence
SPI = EV / PV
Results in prioritized list of risks; risk ranking.
< 1 = Behind Schedule
Quantitative Risk Analysis: Numerical analysis of probability
> 1 = Ahead of Schedule and impact.
Tools: Interviews, Sensitivity Analysis, Decision Tree Analysis,
EAC = BAC / CPI
Simulation, Monte Carlo Analysis.
EAC = AC + ETC
Closing
EAC = AC + (BAC + EV) / CPI
Contract Close: Before project close
ETC = EAC - AC
Project or Phase Close: Lessons Learned
VAC = BAC - EAC
PMI Code of Ethics: Respect, Fair, Honest.
BCWS = PV
Processes
BCWP = EV
Key Formulas
ACWP = AC
Standard Deviation = (P - O) / 6
Tips:
PERT = (O + 4M + P) / 6
Negative is bad
Positive is good
If Variance: EV - Something
If Index: EV / Something
If Cost related use AC
If Time related use PV
Most formulas start with EV
Time Management