1. The resource requirement of the activities of a project is given below.

.
Activities
Days
Workers
Predecessor(s)
A
1
5
--B
2
5
--C
2
4
--D
3
4
A
E
1
4
B
F
4
4
B
G
2
6
C,F
H
6
4
D,E
A total of 12 workers are available. Can we manage the job with these workers?
2. A job requires the following resources.
Activities
Days
T
U
V
W
X
Y
Z

2
14
9
3
2
8
3

Crane
Operators
5
2
3
1
3
4
6

Predecessor(s)
-T
T
T
W
V& X
U&Y

Six crane operators have been recruited for the job but one would join on the 5 th day. How would
you manage the job so as to complete it at the earliest?