Professional Documents
Culture Documents
Project Cost Managment PDF
Project Cost Managment PDF
Company
LOGO
Agenda
1. Definitions
2. Payback / Time Value of Money
3. Estimate Cost
4. Determine Budget
5. Control Cost
6. Earned Value Management
5/16/2009
Definitions (1)
Profit = Revenue Costs
Definitions (2)
Indirect costs are costs that are not directly
5/16/2009
Definitions (3)
Sunk cost is money that has been spent in the
5/16/2009
Definitions (4)
Variable Costs: change with the amount of
5/16/2009
Definitions (5)
Internal Rate of Return: interest rate received for
5/16/2009
Payback Period
Year
0
1
2
3
4
5/16/2009
Project A Project B
-1,000
-1,000
500
100
400
300
300
400
100
600
Project A
5/16/2009
10
Project B
5/16/2009
11
12
Example of PV Calculation
100
300
300
-50
10%
90.91
247.93
225.39
-34.15
530.08 = PV
5/16/2009
13
5/16/2009
14
Scope Statement
WBS
WBS Dictionary
2. Project Schedule
3. Human Resource Plan
5/16/2009
15
5/16/2009
16
5/16/2009
17
5/16/2009
18
2. Basis of Estimates
Estimation Assumptions
Constraints
19
Quiz
Analogous estimating:
20
Quiz
The cost of choosing one project and giving up
another is called:
A. fixed cost.
B. sunk cost.
C. net present value (NPV).
D. opportunity cost.
The answer is: D
5/16/2009
21
22
3. Scope Baseline
4. Project Schedule
5. Resource Calendars
6. Contracts
7. Organizational Process Assets
5/16/2009
23
5/16/2009
24
25
26
5/16/2009
27
5. Variance Analysis
6. Project Management Software
5/16/2009
28
5/16/2009
29
5/16/2009
30
EVM Terms
Planned Value (PV), formerly called the budgeted cost of
work scheduled (BCWS), also called the budget, is that
portion of the approved total cost estimate planned to be
spent on an activity during a given period
Actual Cost (AC), formerly called actual cost of work
performed (ACWP), is the total of direct & indirect costs
incurred in accomplishing work on an activity during a
given period
31
EVM Formulas
5/16/2009
32
EVM Example
PV = $42,000
EV = $38,000
AC = $48,000
CV = EV AC
= $38,000 - $48,000 = -$10,000
CV% = CV / EV
= -$10,000 / $38,000 = -26%
5/16/2009
33
34
35
SPI= EV / PV
= $38,000 / $42,000 = 0.90
$0.90 worth of work was performed for each
$1.00 worth of work that planned to be done..
5/16/2009
36
Estimate at Completion
The managements assessment of the cost of
the project at completion
After variance analysis, the estimated cost at
completion is determined
Can use calculated indices or use management
judgment.
37
Variance at Completion
VAC = BAC - EAC
(BAC=$80,000)
= $80,000 - $101,265 = -$21,265
Based on past performance, project will
exceed planned budget by $21,265
ETC= EAC - AC
(BAC=$80,000)
= $101,265 $48,000 = $53,265
5/16/2009
38
5/16/2009
39
Case 1
PV = $ 1,860
EV = $ 1,860
AC = $ 1,860
5/16/2009
40
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
Spending Variance = EV AC
= - $ 200
5/16/2009
41
Case 2
But with EV measurements,
we see...$400 worth of work
is behind schedule in being
completed; i.e., we are 21
percent behind where we
planned to be.
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
SV
= EV PV = - $ 400
SV % = SV / PV x 100 = - 21 %
5/16/2009
42
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
CV
= EV AC = - $ 200
CV % = CV / EV x 100 = -13 %
5/16/2009
43
Case 2
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
SPI = EV / PV = $ 0.79
CPI = EV / AC = $ 0.88
5/16/2009
44
Case 2
This is the worst kind of
scenario, where all
performance indicators
are negative.
PV = $ 1,900
EV = $ 1,500
AC = $ 1,700
45
Case 3
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
5/16/2009
46
Case 3
The bad news is that our
work efficiency is a bit
low; were getting only 92
cents of work done on
the dollar. As a result,
we are behind schedule.
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
SPI = 0.92
SV = - $ 200; SV % = - 8 %
5/16/2009
47
Case 3
PV = $ 2,600
EV = $ 2,400
AC = $ 2,200
CV = $ 200; CV % = 8 %
CPI = 1.09
5/16/2009
48
Case 4
PV = $ 1,700
EV = $ 1,500
AC = $ 1,500
SV = - $ 200; SV % = - 12 %
SPI = 0.88
5/16/2009
49
Case 4
PV = $ 1,700
EV = $ 1,500
AC = $ 1,500
CV = $ 0.00
CPI = 1.00
5/16/2009
50
Case 5
A positive scenario;
right? But is it because
we are out-performing
our learning-curve
standards or because
we planned too
pessimistically?
5/16/2009
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
51
Case 5
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
SPI = 1.14
CPI = 1.14
5/16/2009
52
Case 5
...work is ahead of
schedule by 14
percent and
under-running cost
by 12.5%.
PV = $ 1,400
EV = $ 1,600
AC = $ 1,400
SV = $ 200; SV % = 14 %
CV = $ 200; CV % = 12.5 %
5/16/2009
53
Text
Thank You
Text
waleed_k@aucegypt.edu
Text
Text
5/16/2009
54