Professional Documents
Culture Documents
EV Case
EV Case
No. of experiment
EV in forecast
info window
1
2
3
1%
0%
1%
0%
1%
1%
12000
12000
24000
EV in data tab of
periodical cost
graph
12000
12000
24000
Images supporting the above mentioned results can be seen in the following
pages:
At this point I will register progress for each cost element to see and to
compare the results in forecast window and data tab of periodical cost
graph. I designed three experiments just like the previous scenario: the
results can be seen in the following table:
No. of experiment
EV in forecast
info window
1
2
3
1%
0%
1%
0%
1%
1%
12000
12000
24000
EV in data tab of
periodical cost
graph
17191.49
6808.51
24000
There is no registered time for the second activity thus theres no actual, commited or actual cost
registered for the cost element related to the second activity. This can be seen in the following image:
entered a 1% progress for each. we obtained the incurred cost which can be seen in the above image.
After this I created a REV forecast, then connected i t to the mentioned budget, after that created an
snapshot for the current financial period and then entered progress for the single cost element manually
in forecast window. The Earned value calculated in the forecast window after entering the progress was:
progress * budgeted cost (BAC). In this case I entered 1 % progress which will make an amount of 12000
due to the estimated cost of 1200000. And the EV in data tab of periodical cost graph was exactly
the same.
2: second scenario:
In this case
But the EV in data tab of periodical cost graph was inconsistent with the calculated EV in forecast
window .
However when I defined another activity with the same cost element, things changed completely. To
simplify the issue, I entered the same estimation for both cost elements in activities and when I entered
the same progress in forecast window the EV for both cost elements were exactly the same : 12000. But
entering 1% progress for the first activity and 0% progress for the second one, caused an EV amount of ---- in data tab of periodical cost graph but reversing the registered progresses ended with an EV
amount of ----- in graph. Results are summarized in the following table:
1st cost element progress
1%
0%
0%
1%
EV in forecast
window
12000
12000
In case that activity details may help, I took a print screen from each:
1st activity:
EV in graph
2nd activity:
The question is in the logic behind the calculated EV in graph. And why the