Roosevelt Island Cornell Tech Demo Site Utility Presentation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

CORNELL TECH SITE PLAN

08.12.14

RENDERING

08.12.14

DEMOLITION UPDATE

Aric Domozick
PAL Environmental Services

08.12.14

DEMOLITION UPDATE

Bldg
J

Bldg Bldg Bldg


A
B
G

Presentation name DD.MM.YY

Bldg
E

Bldg
C

Bldg Bldg
D
H

Bldg
F

PROGRESS UPDATE
PHASE 1
Faade demolition is complete.
Structural demolition is complete.
Foundation removal is ongoing.
Crushing operation has begun, as well as grading and
backfilling.
Operations will be
complete by
December 31, 2014.
08.12.14

BUILDING D NOV. 3, 2014

Presentation name DD.MM.YY

BUILDING D NOV. 4, 2014

Presentation name DD.MM.YY

BUILDING D NOV. 5, 2014

Presentation name DD.MM.YY

10

BUILDING D NOV. 6, 2014

Presentation name DD.MM.YY

11

BUILDING D NOV. 7, 2014

Presentation name DD.MM.YY

12

BUILDING D NOV. 10, 2014

Presentation name DD.MM.YY

13

BUILDING D NOV. 14, 2014

Presentation name DD.MM.YY

14

PROGRESS UPDATE
PHASE II
Interior abatement and demolition work complete in all buildings.
Current Work

Building E: work to begin this week

Building G: work complete

Building J: work is underway and approximately 30% complete

Future Work

Building A: anticipated start date of January 2015

Building B: anticipated start date of March 2015

Operations complete by June 2015.

08.12.14

PHASE II BUILDING G

08.12.14

PHASE II BUILDING J

08.12.14

SITE UTILITY WORK

John DiCapua
Tishman Construction

08.12.14

SITE UTILITY WORK

19

SITE UTILITY WORK

Presentation name DD.MM.YY

21

SITE UTILITY WORK

Presentation name DD.MM.YY

20

SITE UTILITY WORK


CURRENT FENCE LOCATION

22

SITE UTILITY WORK


TEMPORARY FENCE LOCATION

23

SITE UTILITY WORK


CENTRAL UTILITY PLANT (CUP)

Presentation name DD.MM.YY

24