ESL G3 Post Installation Check List

Physical Set Up
Has the library been leveled to 0.00 +/-0.30 using the digital level?
Has the x-axis rail been leveled to 0.00+/-0.05 in reference to the floor of the library using the
digital level?
Has the accessor assembly (y-axis rail) been aligned to within 1mm of the scribe marks?
Have the x and y-axis belt tensioners been set to within 5 mm?
Are all magazines seated correctly?

Drives
Are all drives installed in the correct drive sled positions?
Are all thumb screws that retain the drive sled tightened?
Do all the drives have a blinking green status LED?
Are all the green tape drive LEDs synchronized?

Boards
Are all blades inserted in the correct bays and locked into place?
Is the LBX terminator installed on the last frame?

Configuration
Has a Teach > Configure (Tools>Library Diagnostics>Teach>Configure) and a Teach > Calibrate
(Tools>Library Diagnostics>Teach>Calibrate) been preformed?
Has a full inventory from the physical view been preformed (Operations > Inventory)?
Has an Installation Verification Test been run (Tools>Library Diagnostics>Verification Test)?