Resistance Measurement
This measurement must be carried out by a qualified electrician.
If the atomizer been disassembled, it must be measured at the back
mounted atomizer of the electrical resistance between chuck and
paint pipe and between chuck and turbine. The bell cup must not be
mounted.
The electrically conductive parts in the atomizer are electrically
interconnected to one another. During operation of the atomizer at
high voltage, as a result of the connection of the electrodes the supply

are under high voltage supply


DANGER
Risk of Property damage and Production disruption
Malfunction of the high voltage due to high resistance.
After working on the inside of the atomizer check the resistance.
A resistance measurement shows whether the electrical connection of
the parts with one another is OK:
The resistance between chuck and color tube must be 10 . Test
voltage 4-24 V.
The resistance between chuck and shaft / turbine must be 0.1 milli
ohms. Test voltage 50 V.
If resistance is larger, the atomizer must be disassembled again.
Check all contact surfaces. Then assemble the atomizer again.

27.12.2014 03:24 KRAUSS, RALF