Mid Tem Exam CIVIL4810-2013-2014 PDF
Mid Tem Exam CIVIL4810-2013-2014 PDF
Faculty of Engineering
COURSE CODE
CIVIL4810
LEVEL / SEMESTER
4/1
COURSE TITLE
PROJECT MANAGEMENT
ACADEMIC YEAR
2013-2014
DATE
TIME
10:00 am
DURATION
MAXIMUM MARK
100
COURSE COORDINATOR :
STUDENT NAME
STUDENT ID
GROUP NO
INSTRUCTIONS TO CANDIDATES
This question paper consists of 3 pages.
Answer ALL questions as required.
Write your ID, NAME and GROUP NUMBER clearly on all
of your answer books.
Follow all examination rules.
Do not bring books or other related materials into the
examination room.
Page |2
Question 1:
[20 marks]
[20 marks]
On the construction of a small dams project, allowable man hours for earthwork are
5000hr, for lying roller compacted concrete (RCC) are 8000hr and for spillway works
are 6000hr. Assume the shift time to be 8 hours per calendar day.
How many workers will be required in total if the earthwork to be finished in two
month, lying of RCC in three months and spillway works in one month?
Question 3:
[35marks]
Dependence
A
A
B
B
C
C
D
D,E
E,F
F,G
K
J,K
H,I,J,K
H
M,L
Duration
2
5
3
5
3
2
4
6
12
18
3
7
3
1
1
9
[16marks]
[16marks]
[3marks]
Page |3
Question 4:
[25 marks]
Consider the Figure Q4, which location you will select to buy the cement (100T) and
steel (1000T) for your project based in Sohar?
DUBAI
175km
SOHAR
300km
NIZWA
200km
MUSCAT
Figure Q4
Hauling Charges:
Dubai-Sohar: 2.0OMR/T/100km
Nizwa-Sohar: 1.5OMR/T/100km
Muscat-Sohar:1.2OMR/T/100km
Approximate Price of Cement:
Dubai: 20OMR/T
Nizwa: 14OMR/T
Muscat: 21OMR/T
Approximate Price of Steel:
Dubai: 200OMR/T
Nizwa: 190OMR/T
Muscat: 210OMR/T