CALCULATION QUANTITIES OF (CEMENT+SAND+C.

AGG+WATER) OF RCC
TYPE OF WORK

Quantity

mixture

RCC

M3

FOOTING
NICKS
GROUND BEAM
COLUMN
LINTELS
FLOOR BEAM

91.06
5.65
21.76
12.52
2.32
21.3
31.8
4.77

RATIO
1.2.4
1.2.4
1.2.4
1.2.4
1.2.4
1.2.4
1.2.4
1.2.4

FLOOR SLAB
STAIR SLAB

cement
KG
317
317
317
317
317
317
317
317

/M3
0.2
0.2
0.2
0.2
0.2
0.2
0.2
0.2

sand
NO. BAG
606.2
37.6
144.9
83.3
15.4
141.8
211.7
31.8

TOTAL QAUNTITY

/M3
0.43
0.43
0.43
0.43
0.43
0.43
0.43
0.43

caorse agg
TOTAL
47.0
2.9
11.2
6.5
1.2
11.0
16.4
2.5

1272.7

/M3
0.86
0.86
0.86
0.86
0.86
0.86
0.86
0.86

98.6

water

TOTAL
94.0
5.8
22.5
12.9
2.4
22.0
32.8
4.9

/M3
15.2
0.9
3.6
2.1
0.4
3.5
5.3
0.8

197.3

63.6

STEEL
/L

TON

15155
940
3621
2083.6
386.1
3544.9

4.9
1.9
2.63
3.3
0.266
2.63

5292.3

2.77

793.8

1.21

63634.3

19.606

CALCULATION QUANTITIES OF (CEMENT+SAND+C.AGG+WATER) plain concrete


TYPE OF WORK

Quantity

mixture

cement

plain concrete

M3

RATIO

KG

/M3

under footing
under base stone
under ring beam
For the floors

16.938
1.52

1.2.4
1.2.4
1.2.4
1.2.4

317
317
317
317

0.2
0.2
0.2
0.2

4.3525
27.846

sand
NO OF
BAG
112.8
10.1
29.0
185.4
337.2

TOTAL QAUNTITY

caorse agg

water

/M3

TOTAL

/M3

TOTAL

/M3

PER LITTER

0.43
0.43
0.43
0.43

8.7
0.8
2.2
14.4
26.14

0.86
0.86
0.86
0.86

17.5
1.6
4.5
28.7
52.3

3.1
0.3
0.8
5.1
9.3

3100.8
278
796.8
5097.7
9273.6

CALCULATION OF FINSHING QUANTITIES PAINTS


QAUNTITY m2

Gallon

productive

Total Gallon

TYPE OF WORK

m2

23 (kg)

m2

NO

primary layers

1506.219

70

21.5

second layers

1506.219

100

15

Firste layer of putty

950.256

30

31.5

second layers of putty

950.256

45

21.2

firste layer of oil paint

950.256

250

3.8

second layer of oil paint

950.256

250

3.8