ICML/SOLAR/GUJ/CIVIL/DWG/002
Fencing Layout
LAHMEYER COMMENTS
DATED: 12/05/2011
Approval
Status
A2
REPLY DATED
: _____
LAHMEYER COMMENTS
DATED: 23/05/2011
Approval
Status
i) Noted
Ii) Noted
iii) At angle points /sharp corners, the stay concrete posts are to be provided. One stay post for every 20m in
straight runs has to be provided.
v) The bottom row of barbed wire may be replaced with 300mm or 250mm high pre-cast PCC or brick masonry
kerb wall. This will also prevent entry of rain water from surrounding Area.
vi) Noted but please show the section of pole.
vii) There should be a parity observed in size of dimensioning , texts, sections etc used in the drawing.
Approval Status (This approval status shall not relieve the Contractor from his contractual obligations):
A1: Approved
A2: Approved subject to incorporation of Comments/modifications as noted. Resubmit revised drgs./docs after Incorporating the comments
A3: Not approved. Resubmit revised drgs/ Docs. Incorporating comments/Modifications, as noted, for approval.
I: Information
Page 1 of 1
A2
REPLY
DATED :
_____
LAHMEYER COMMENTS
DATED: 26/05/2011
Approval
Status
A2
REPLY
DATED :
_____
LAHMEYER COMMENTS
DATED: 27/05/2011
Approval
Status
REPLY DATED :
_____
LAHMEYER COMMENTS
DATED: 06/06/2011
Approval
Status
A1
A1