City of Carmel-by-the-Sea

Carmel Beach Restroom


Grant Agreement 13-058
Progress Report #2

Progress Report Narrative


Introduction
This report covers the period of October 1, 2014 through December 31, 2014. This project involves the
construction of a barrier-free permanent restroom that includes two flush toilets, wash basins, janitor
closet, new landscaping, landscaping to screen the building, a green roof, a drinking fountain and the
design and installation of an interpretative sign on the Coastal Trail.

Summary of Work Completed To Date


The restroom was open to the public on December 11, 2014. The Citys Planning Commission approved
a landscape plan on December 10, 2014 and the City is currently receiving bids from contractors for the
landscaping. The work is anticipated to be complete in January 2015. The language for the interpretive
panel and Coastal Conservancy
acknowledgement signage is
being developed with installation
by the end of January 2015.

Summary of Activities

Drinking fountain, green


living roof and the rooftop irrigation
system were installed in early
November and operational.

After slight delay due to


the weather, PG&E met with
th
contractor on site on December 8
to tie to power pole on Santa Lucia
to provide electricity to the site.
The final walk-through with the
contractor occurred on December
th
10 . Restroom opened for public
use on December 11, 2014.

Revised Schedule
Project Component

Original
Duration

Revised
Schedule

Percent
Complete

Mobilization and Site Preparation

May-June 2014

June-July 2014

100%

Construction of Building

June-Sept. 2014

June-Sept. 2014

100%

Finish construction/Drinking fountain/Living roof

Aug.-Oct. 2014

Aug.-Nov 2014

100%

Landscaping

Aug.-Oct. 2014

Nov-January 2015

50%

Signage

Aug.-Oct. 2014

Nov-January 2015

25%