Professional Documents
Culture Documents
ESHA Strategic Study For Development of SHP in EU - 2008
ESHA Strategic Study For Development of SHP in EU - 2008
Contents
INTRODUCTION
4. SUPPORT SYSTEMS
10
12
12
12
13
14
6. ECONOMICS
15
18
8. SHP TECHNOLOGY
19
21
10. CONSTRAINTS
23
24
12. REFERENCES
28
13. ACRONYMS
28
Introduction
This study develops six main subject-areas
pertaining to the possible exploitation of SHP
energy in Europe.
The situation of Small Hydropower (SHP) in
the EU has changed. The enlargement of the
EU along with increasing interest in renewable
energies has led to a new and growing focus
on SHP. As a result, more complex questions
have arisen that require increased knowledge
in order to be resolved.
This study, which is part of the SHERPA-project
(Small Hydropower Energy Efficiency Campaign Action), aims to provide a better understanding of SHP in the EU. It is intended for decision makers and politicians at EU, national,
regional as well as local level in order to facilitate the achievement of the various targets set
out in EU legislation (RES White Paper targets
and the RES-E Directive) but may also be of
general interest. On the basis of the data collection and analysis, new initiatives at EU level
will be developed by the European Small Hydropower Association (ESHA) in close collaboration with the EU Commission. The definition
of SHP used by the European Commission, i.e.
SHP plants up to 10 MW, has also been employed in this study.
The following issues have been dealt with: (i)
Current Status and potential of SHP technology within the 27 EU member states (EU-27)
and recent technological and market development of small hydropower and (ii) review of
policy framework conditions for SHP within the
EU-27 and Candidate Countries (Croatia, the
former Yugoslav Republic of Macedonia and
Turkey). An overview of current policy initiatives within the European Union has been prepared, taking all levels of decision making (EU,
national, regional and local) into account.
The SHERPA project and the work on this report started in September 2006 and finished
in September 2008. The project was financed
by the EU Commission and by the participants.
Intelligent Energy Europe (IEE) commissioned this
project to the European Small Hydropower Association (ESHA). ESHA then co-ordinated the
project, which was subsequently divided into different sub-projects, of which the present one was
performed by the Lithuanian Hydropower Association (LHA) and the Swedish Renewable Energy
Association (SERO).
This study is based on a questionnaire that was
sent to main SHP actors in different EU countries as well as Norway, Switzerland, Bosnia &
Herzegovina and Montenegro. Information
from official databases and existing studies
6
the economic potential indicated an increase
from the previously assumed 10,000 GWh to
20,000 GWh annually, while still taking account
of economic and environmental constraints.
However, developing potential into real electricity generation takes time. According to this
study, the realistic SHP forecast for EU-15 in
2010 is about 13,400 MW with electricity generation of nearly 47,400 GWh annually. This
Figure 5. SHP Capacity 2000-2006 and forecast to 2010 for SHP in EU-15,
EU-12 and EU-27
According to the present study, the 2010 estimations for SHP stated in the White Paper will
not be reached for EU-15, but are likely to be
achieved if EU-12 is included. In order to reach
the White Paper target better conditions such
as less administrative barriers for SHP are required.
It is difficult to make forecast after 2010 due
to the many uncertainties. However by making
some assumptions it is possible to set up scenarios. In this study two scenarios have been
developed:
1. Scenario existing conditions, assuming
the economical situation, license procedure etc is as today.
2. Scenario improved conditions, optimal
conditions for developing SHP (barriers are
not an obstacle, the support system are
well designed for SHP etc) which means
that the growth is depending on how fast
the manufacturing industry can deliver
equipment for new SHPs.
Scenario existing conditions. The development of SHP will expand more slowly after year
2010 due to that the most suitable places for
SHPP already have been used. In this study it
has been estimated that 1/3 of the potential
(i.e. potential still not developed in year 2006)
in EU-27 can be developed with existing conditions until year 2020. Which means a total
capacity for SHP in the EU-27 of more than
16000 MW.
Scenario improved conditions. The yearly
growth is quite the same after year 2010 until
year 2020. In this study it has been estimated
that 2/3 (i.e. potential still not developed in year
2006) of the potential in EU-27 can be developed with existing conditions until year 2020.
Which means a total capacity for SHP in the EU27 of nearly 20,000 MW.
The differences between the two scenarios are
3,300 MW or about 13,000 GWh annually.
(Fig. 7).
Figure 7. SHP Capacity 2000-2006 and forecast to 2010 for SHP in EU-27.
Data for this report have been collected from different sources and in some cases there are significant differences. Capacity and production data have to a great extent been derived from Eurostat, but they appear
to contain some discrepancies. For instance there is a reduction in capacity in the year 2003, while in 2004
there is a return to the 2002 level. It is unlikely that a capacity of almost 500 MW would have been shut down
for one year and taken into operation again the year after. In the chapter Conclusions and Recommendations
we suggest how more accurate data can be obtained from MS.
Figure 8. RES-E share in gross electricity consumption. Observed data in 2006 from
Eurostat
prove the status of aquatic ecosystems and mitigate the effects of floods and droughts.
The fear that SHP plant owners and investors
have about this framework is that the residual
flow may increase and thus investment costs
may also increase. Several MS associations have
reported that they can already feel the effect
of the WFD. In some countries environmental
groups have a very negative attitude towards
hydropower. This is mainly due to the fact that
they are unfamiliar with the new technologies
that benefit the environment and that large and
small-scale hydropower plants are often put in
the same box.
Although the construction of new plants is not
prevented by the WFD, all new licenses and
new or amended restrictions on existing plants
are dealt with by means of the water regulation
laws. The main impacts are likely to be new or
higher residual flows and stricter regulations on
the use of reservoirs.
However, this framework is a great opportunity
for environmentalists and hydro engineers to
work together to create sustainable solutions
where the environment is protected at the same
time as the country produces clean renewable
energy.
10
4 Support Systems
As the choice of promotion instruments has not
been prescribed or harmonised within the EU,
each country has adopted its own unique set.
The main drivers for the specific choices are often the national goals in relation to renewable
energy.
The survey reveals that the most widely adopted
support mechanism within the analysed countries is feed-in tariffs, sometimes accompanied
by a variety of incentives. Some MS prefer the
Quota obligation system, which is usually based
on Tradable Green Certificates (TGC).
Feed-in tariffs are generation based, price
driven incentives, usually in the form of either
a fixed amount of money paid for RES-E generation, or an additional premium on top of the
electricity market price paid to every producer.
It should be noted that fixed feed-in tariffs are
currently used in 18 of the EU-27 MS and Quota
obligations in 7 (Belgium, Italy, Latvia, Poland,
Romania, Sweden and the UK) (Fig. 9).
The biggest advantage of the feed-in system is
the long-term certainty about receiving support,
which considerably lowers investment risks. This
fixed and relatively stable system is much preferred by SHP electricity producers in EU-27 and
even in the candidate countries.
Figure 9 Overview of primary renewable electricity support systems in EU-27 in November 2008.
Source: OPTRES and updated with actual status
Table 1. Advantages and disadvantages of different support systems. Source: Council of the European Union
The support for electricity from renewable energy sources Impact Assessment 2005, {COM(2005) 627 final}
Advantages
Disadvantages
REFIT
(Feed-in tariffs)
Highly effective.
Highly efficient due to the low risk for investors.
Permits strategic support for technology innovation.
Premium
Highly effective.
Efficient due to the medium risk for investors.
Good compatibility with the internal market.
TGCs
(Green certificates)
Tendering
Investment
subsidy
Fiscal measures
Local conditions combined with the goals for each country must be considered when discussing support
systems. Feed-in tariffs is the most common in the EU. It is also preferred by producers, since it results in
a long period with a certain income.
11
12
These issues are normally under the responsibility of different authorities. In this context, the
procedures not only vary from one country to another, but also within a country from one region
to another and even in the same region, from
one project to another.
Co-ordination between different administrative
authorities does not function successfully with
regard to deadlines, reception and treatment of
applications for authorizations. Time limits for
responses from the Administration are usually
not respected. Developers have to undergo successive public consultations on the same project.
There are no real fast track procedures, especially for smaller projects.
These procedures - that are far from being transparent, objective and non discriminatory - are in
some cases supervised by several local administrations that are very sensitive to pressure and
lobby groups, which multiply the number of interlocutors and extend the time required for making
decisions (up to 58 permits from different administrations are necessary in some Italian locations).
In addition, the project has to be made public so
that people can react. As a result, the process in
some MS can last up to 10 years (for new developments), which discourages the potential investor who will switch to another more attractive RES
project or other locations outside the EU.
For the refurbishment and upgrading of plants
the situation is generally easier (but not always2)
although various permits are still required.
Sometimes project developers are requested to
conduct an Environmental Impact Assessment
(EIA) of existing infrastructures.
The cost of permits includes hydrological and
environmental assessment, preliminary designs,
permits and approvals for water and land use
as well as construction, interconnection studies,
power purchase agreements (PPA), and varies
from country to country with an average of between 10,000 to 30,000 per application. This
amount is lost if authorisation is refused.
It seems that MS have not implemented Directive
2001/77/EC to the extent necessary for achieving
SHP targets.
Hagerums Kvarn SHP plant in Sweden. The original SHP plant was shut down in 1996. The new owner wanted to increase
the capacity to 170 kW (an increase of about 40 percent) and a new licence was needed. The procedure took 6 years and cost
45,000 . The main reason was understaffing at the environmental court and that an association opposing the project was
given too many chances to request investigations that proved to be irrelevant. The final permission was granted in 2005.
Ljunga SHP plant in Sweden. The plant is now under construction and will have a capacity of 1,200 kW. It took over 13
years to obtain a license. The final permit was granted/issued in 2006. The site contained a smaller plant that had been
shut down about 40 years ago. The main reasons have been very strong resistance from the regional authority coupled
with a lack of professionalism on the part of the project team.
2
13
14
is forbidden and the criteria used for such classification in a transparent process involving all
stakeholders.
The small hydropower situation clearly highlights how a good support system in terms of
economic revenues or the setting of ambitious
targets is not sufficient to overcome the administrative and environmental barriers that
prevent small hydro power from developing its
untapped potential. Without authorizations no
development is possible and therefore support
schemes are useless, not only for promoting
SHP but also for achieving the 2010 objectives.
It is not easy to state the approval rates for SHP
projects in Europe, and the situation differs a
great deal from one country to another. The
reason for the difficulty is a lack of transparency and information, as most public authorities
rarely publish this kind of information; the majority of installations have to wait for a very long
period before obtaining a response (as the authorisation has neither been refused nor granted it is difficult to establish a rejection rate).
6. Economics
Compared to other RES-E, SHP is competitive,
assuming equal conditions. However, compared
to large-scale hydropower and other forms of
large-scale conventional electricity production,
SHP and other RES-E technologies need supports in order to compete on a deregulated
power market. If subsidies for conventional electrical production were eliminated and the sector
obliged to cover all its external costs, SHP would
most likely be very competitive compared to all
other technologies. For instance according to
the UNEP-report Reforming Energy Subsidies,
there are considerable subsidies available for
fossil energy.
When making an investment in SHP there are at
least two items that are of major importance; the
size of investment and the risk. The economics of
running a SHP plant can be roughly divided into
revenues and costs (Table 2).
The revenues from generated electricity vary
between the markets in the EU. On a deregulated market the price differs a great deal between
years (Fig. 11). As revenues are very dependent
on the agreements with the purchaser they do
not only vary between countries, but also from
one plant to another. As the support systems in
Table 2. Examples on how revenues and costs combined with volatility affect the uncertainty and the
willingness to invest in SHP. The higher the uncertainty and risk the less interest in investing
Revenues
Volatility
Uncertainty
Sales of generated
power
Medium to high.
Support system
Grid compensation
Low if available.
Low
Low
Low if available.
Low
Low
Costs
Volatility
Uncertainty
Capital costs
High
Medium
High
Medium
Low to medium
Low to medium
Administrative costs
Low
Low
Low
15
16
Figure 11. The spot prices for the largest exchange electricity markets in
Europe since 2003, Nord Pool (Nordic countries), EEX (Germany) and PWX
(France). Source: Nordpool Monthly report August 2007.
Table 3. Investment and production costs. Some countries has very high average SHP production costs
which may be explained by that they have included the capital cost.
Range of invest- Average SHP
ment costs
production
costs
Country
Euro/kW
Eurocent/
kWh
Bulgaria
BG
1000 - 1500
0.4 - 0.8
Cyprus
CY
n/ap
n/ap
Czech Republic CZ
1000 - 6000
Estonia
EE
1000 - 4000
2-5
Hungary
HU
n/a
3.8 - 4.6
Latvia
LV
1800 - 2000
Lithuania
LT
2200 - 2500
2.5 - 3
Malta
MT
n/ap
n/ap
Poland
PL
2200 - 2500
3-4
RO
SK
SI
HR
MK
TR
1250
2000
1500 - 3000
1300 - 2500
1200 - 3000
500 - 1100
4
0.6 - 0.8
n/a
1.5
n/a
0.2
Austria
AT
3000 - 5500
8 - 30.9
Belgium
BE
1000 - 8000
6-8
Denmark
DK
n/a
n/a
Finland
FI
1750 - 10000
3 - 3.5
France
FR
1850 - 4000
0.5 - 1.8
Germany
DE
5000 - 12000
0.7 - 1.1
Greece
EL
1500
70
Ireland
IE
1600 - 5000
0.87 - 6.34
Italy
IT
2150 - 4500
10.5 - 17.4
Luxemburg
LU
6000 - 3000
10 - 15
Netherlands
NL
3000 - 6000
10 - 15
Romania
Slovakia
Slovenia
Croatia
Macedonia
Turkey
Portugal
PT
1800 - 2500
0.56 - 0.6
Norway
NO
1000 - 1500
1.5 - 2
Spain
ES
1000 - 1500
3.5 - 7
CH
4000 - 10000
3 - 15
Sweden
United Kingdom
SE
2150 - 3500
2.0 - 2.5
BA
1300 - 1600
1.5
UK
2200 - 6000
5.0 - 15.0
Switzerland
Bosnia & Herzegovina
Montenegro
ME
n/a
n/a
13). In Figure 13 large hydropower has nearly the same costs as SHP, but according to this
study the Long Range Marginal Cost (LRMC) for
SHP is higher than for large scale Hydropower in
almost all cases. Also worth mentioning is that
biomass and biogas are often paid for handling
their fuels.
Figure 13. Compared to other RES-E technologies, electricity generation from SHP is competitive for comparable investments. Source:
OPTRES 2007.
Figure 12. Compared to other RES-E technologies, electricity generation from SHP is competitive for comparable investments. Source:
OPTRES 2007.
Due to scale effects, SHP is not normally competitive compared to large scale electricity generation plants unless external costs have been internalised. Our own findings and those of other
studies (Optres 2007) demonstrate that SHP is
very competitive compared to other RES-E. (Fig.
17
18
Therefore, the positive impact of SHP on the environment outweighs the negative effects. Further information can be found in the SHERPA
environmental report.
A study The application of the ISO 14001 Environmental Management System to Small Hydropower Plants, which is a part of the SHERPA
project, discussed how ISO 14001 can be used
among other things as a tool when working to
reduce the impact of SHP on the environment.
In the study the negative impact of SHP on the
environment is also dealt with.
The ISO 14000 environmental management
standards exist to help organisations minimise
the negative affect of SHP operations on the environment and to comply with applicable laws
and regulations.
An individual example in the spirit of ISO 14001
is that of a small hydropower plant in Sweden,
called the Forsa plant in Rolfsan, situated in the
southwest of the country. A project was launched
to retrieve migratory fish in the Rolfsans water system. For further information see www.rolfsan.se.
Compared to conventional generation, SHP is better for the environment. More research is needed
if and how SHP affects the environment. There are
interesting projects indicating that SHP operators,
environmentalist and researchers can co-operate
to find broad solutions acceptable to all parties.
Figure 14. Environmental Integration Resistance to SHP development EU-27 & CC.
8 SHP Technology
During recent years hydropower development
has focused on the adoption of new technology
from other sectors. Only a few decades ago, a
person responsible for operating a SHP plant
had to live nearby in order to control the operation. Such a system would be impossible today with the current ratio between income from
electricity generation and the cost of labour. The
scene has dramatically changed with the development of electronics. The following describes
some areas where this development has made
SHP operation more efficient.
Automation
Thanks to modern electronics SHP plants nowadays operate automatically and new IT technology has made it possible to introduce remote
monitoring and control. This constitutes a big
step forward and results in less visits to a plant,
more efficient regulation, safer operation and
reduced operating costs. This development is
still in progress.
Frequency conversion
Many SHP turbines are forced to run at a speed
for which they were not designed, due to the
fact that it is too expensive to design and build
a turbine that exactly suits the conditions at a
specific site. Although mechanical gears have
been used in order to overcome this problem,
correct frequency is still not achieved. Electronic
frequency converters have been too expensive,
but technical development and mass production has reduced the price to a level where they
are economically viable for SHP use.
New Material
There are many advantages in using permanent magneto generators, but up to now they
have normally been too expensive for SHP to
compete with standard generators. Development has now led to price reductions and these
generators are becoming economically interesting for installation in new SHP plants.
This is an area with many possibilities. Steel alloys more resistant to cavitations in turbines and
their development is in progress. Finding new
applications for fibreglass and special plastics is
another ongoing development, while aluminium is replacing steel in water structures such
19
20
as trash racks and stop logs in spillways. Aluminium is not as corrosive as steel, which reduces maintenance costs and the time to stop
operations during maintenance. An aluminium
trash rack is also easier to clean. The fisheries requirement for a shorter distance between
the bars in SHP trash racks can result in loss
of head. Aluminium bars can be manufactured
with streamlined profiles to reduce head losses.
Aluminium stop logs are almost maintenance
free and easier to handle as they weigh far less
than traditional wooden stop logs.
Environmental Requirements
The increased environmental requirements on
SHP plants have led to technical development
to adapt the plants to these regulations. Reducing amplitudes in dams is one requirement that
has been fulfilled by means of automatic water
level regulation to keep the amplitude within
acceptable levels.
Turbine Development
Although water turbine technology is considered to be a mature technology, there is still
interesting development taking place to improve efficiency and dynamic characteristics.
During the last two decades the top efficiency
of small turbines has increased from around 88
to 93 percent and the efficiency curve has been
considerably improved. New research on and
development of special turbines for very low
heads has become an interesting area.
The development of SHP technology is far from
complete and new techniques not only bring
down the cost but also emphasise environmental issues. Some areas that deserve mention are
the development of automation, more environmental friendly solutions and more efficient turbines.
The European SHP equipment manufacturers are market leaders. They have successfully
developed hydropower technology and they
have become the main exporters of equipment
worldwide. Indeed, it can be said that Europe
gave light to the world.
Although EU equipment manufacturers are still
world leaders, this position is under threat as
MS have shown little interest in stimulating investments in new SHP and maintaining existing plants. This situation is due to decreasing
profits for energy producers in the deregulated
electricity market and the increasing obstacles
created by environmental and legal constraints.
The introduction of support systems has improved this situation. The margins for producers
are still good in a few countries such as Germany and Spain and consequently the markets for
manufactures in these countries are better, but
have recently been reduced because of the rising cost of materials, which has not been possible to transfer to customers. The non-EU market
is still promising and offers good prospects for
21
22
10 Constraints
From the data collected it appears that the environmental constraints affecting SHP are mainly
related to fishing and water regulations. In almost all countries the fishermens lobby has the
power to influence the decisions of the regional
and national authorities. Moreover, in many European countries, environmental groups are trying to prevent local river areas from being used
by companies for industrial purposes (mainly
electricity generation), claiming it would negatively impact on the river environment (this is
particularly a problem in northern countries).
Another constraint is that in many countries the
long water licensing procedure is a real burden.
This is mainly caused by the complicated and
time-consuming public administration procedures and the number of subjects involved who
can refuse authorisation, which makes it difficult
to set up new SHP plants as well as finding proper financing schemes (this problem is common in
many southern European countries). (Fig. 16).
A report on Realising Hydro Projects by Involving
Stakeholders, carried out by the SHERPA project,
discusses how Social Engineering can be used as
a tool to implement a SHP-project where there
are objections from different groups.
Social Engineering means combining technical and economic aspects with a great variety
of social aspects. It can be seen as methodical
approach to overcoming opposition to a project.
In the report some tools are described as Conceptual strategies, Operational approaches, Involvement, Ownership and identity and presented together with examples of successful use of
the methods.
Figure 16. Social acceptance - Resistance to SHP development EU-27 & CC.
23
24
Gathering data
Statistics for this study were gathered from official sources such as Eurostat, reports, from experts and associations as well as other sources,
e.g. the Internet. The result demonstrates that
there is a great deal of variation between different suppliers and that official sources do not
present an accurate description of SHP.
The Commission should provide MS with more
detailed guidelines for how to report statistics.
The most reliable method is to gather information
on capacity and production from those organisations responsible for measuring the electricity generation to the grid from SHP plants (and
other plants). In most MS this is the responsibility
of grid owners. This is the only reliable way to
an accurate information on capacity and electricity generation. Reliable statistics are important to
precisely follow the development of capacity and
production towards targets, for example the Commissions 2020 targets.
Economics
SHP represents a major investment over an extremely long production period, normally 30-40
years. Other industrial investments have a payback time of around five years. This means that
the SHP sector has a need for a long-term stable
income. SHP also has a higher cost per produced
kWh than large hydro and other large scale electricity generation plants, but offers social advantages such as higher rates of employment, reduced
energy losses and stimulation of Small and Medium-sized Enterprises (SMEs) to support the sector.
Building a SHP plant implies heavy investment and
the capital cost is high, until the loans have been
completely amortized within 15-20 years.
The Commission should require MS to introduce
long sighted rules including a support mechanism
for the SHP sector taking into account the capital
cost over a period of 15-20 years. A differentiated system should be considered. The smaller the
plant, the higher the production cost, but also the
higher the benefit to society. Rules on how to calculate production and investment costs should be
issued by the Commission in order to harmonize
the way of calculating such costs, as the method
employed seems to differ between member states.
This will create an accurate way to compare different electricity generation sources.
Policy framework
Many SHP actors report complicated procedures
for obtaining a license, uncertainty as to whether
an application will result in a license, high costs,
an abnormally long waiting period and too many
authorities involved. The expensive, complicated
and time consuming process reduces the number
of applications as well as the number of applica-
Manufacturing industry
Summary of recommendations
To summarise what is said above about promoting SHP development in the short and medium
term, as well as good policies and best practices for SHP the following is suggested.
Concrete recommendations and policies for
promoting SHP in the short term:
Assure higher quality of the data that is being
reported for SHP to Eurostat. Using data from
the measuring of production delivered to the
grid is the most reliable method.
Evaluate different methods and recommend
the MS a state of the art of how to calculate
a more precise potential for SHP in different
MS. Good examples can be found from Scotland and Norway.
Evaluate different methods and recommend
the MS a state of the art of how to calculate
the costs for SHP investments and production
as well as other sources of electricity generation.
Environment
SHP has both local and global benefits, but is also
the object of criticism from some organizations,
mainly fishery associations, for the negative impact on the local environment. It is often difficult
to evaluate the different arguments, thus making
the debate more emotional than factual.
Give clear recommendations on how to interpret Directive 2001/77/EC and the WFD Directive that appear to be contradictory.
25
Norway &
Switerzland
Candidate
Countries
EU-12
EU-15
2
9
9
13
0
155
0
0
127
682
10574
38
46
152
236
10810
CZ
EE
HU
LV
LT
MT
PO
RO
SK
SI
18
7933
51795
11
1712
12522
CH
BA
ME
74
3290
747
NO
4551
5
0
25
27
0
720
0
0
340
2050
43500
0
18
344
362
43862
503
4401
255
29
1612
6723
7999
166
123
9239
120
4
878
4436
5251
214
41450
430
0
Switerzland
Bosnia &
Herzegovina
Montenegro
Associated
Countries
EU-27, CC,
Associated
Countries
945
142
BG
CY
HR
MK
TR
843
60
10
357
1833
1421
56
34
2197
39
2
307
1567
1100
66
9892
225
0
AT
BE
DK
FI
FR
DE
GR
IE
IT
LU
NL
PG
ES
SE
UK
[GWh]
[MW]
Norway
Austria
Belgium
Denmark
Finland
France
Germany
Greece
Ireland
Italy
Luxemburg
Netherlands
Portugal
Spain
Sweden
UK
EU-15
Bulgaria
Cyprus
Czech
Republic
Estonia
Hungary
Latvia
Lithuania
Malta
Poland
Romania
Slovakia
Slovenia
EU-12
EU-27
Croatia
Macedonia
Turkey
CC
EU-27 + CC
Energy
Capacity
2000
13297
1748
11
755
973
2
9
12
13
0
182
0
0
147
750
11264
38
46
201
285
11549
160
843
60
11
342
2221
1421
60
37
2233
40
2
317
1618
1120
189
10514
225
0
[MW]
Capacity
2001
51826
7344
15
75
3310
3944
7
33
37
41
0
771
0
0
371
2231
43965
91
15
411
517
44482
691
4259
242
28
1412
6887
7634
135
93
9396
133
3
982
4914
5406
210
41734
280
0
[GWh]
Energy
14782
1789
11
763
1006
3
9
18
13
0
210
346
0
156
1218
12749
38
48
158
244
12993
238
1547
60
11
342
2313
1527
62
16
2291
40
2
344
1652
1130
194
11531
225
0
[MW]
Capacity
2002
52511
8077
16
75
3330
4656
6
28
32
36
0
847
436
0
327
2814
43813
96
16
509
621
44434
749
4632
198
49
1070
6751
8594
150
55
9594
113
3
917
4028
4642
203
40999
353
0
[GWh]
Energy
14315
1840
11
771
1049
4
9
26
19
0
227
348
67
151
1327
12236
34
48
157
239
12475
251
1205
59
11
341
1981
1544
69
34
2330
40
2
330
1704
1140
119
10909
225
0
[MW]
Capacity
2003
46429
6835
17
75
3350
3393
13
24
57
41
0
674
470
250
266
2943
39036
72
17
469
558
39594
660
2681
147
21
971
6381
7967
245
83
7187
77
3
1026
5407
3754
143
36093
488
0
[GWh]
Energy
14947
1912
13
777
1113
4
12
25
20
0
261
319
67
143
1327
12780
32
48
175
255
13035
251
1190
60
11
341
2384
1564
82
38
2364
40
2
335
1749
1150
143
11453
225
0
[MW]
Capacity
2004
53068
8189
24
84
3372
4709
22
43
69
61
0
890
774
250
437
3960
44186
124
24
545
693
44879
903
3792
185
27
1562
6710
8378
303
100
8859
100
3
716
5040
4169
282
40226
511
0
[GWh]
Energy
15203
1988
21
794
1164
5
12
25
27
0
246
325
67
143
1352
12959
33
48
175
256
13215
277
1062
62
11
324
2419
1714
89
38
2405
40
2
335
1788
1160
158
11607
225
0
[MW]
Capacity
51176
9461
23
119
3439
5880
22
49
62
66
0
860
752
250
383
4214
41083
107
23
502
632
41715
1071
3593
166
22
1102
5899
7959
324
103
7616
90
3
395
3977
5177
443
36869
699
0
[GWh]
Energy
2005
Table 4. Observed SHP data in EU-27, CC as well as Norway, Switzerland and other countries
22698
1616
19
1043
547
41
34
140
78
0
676
221
202
478
3361
20949
32
25
76
133
21082
1389
2485
80
34
152
1717
8000
61
44
1799
24
10
68
1119
1869
126
17588
102
0
Number
2006
15164
1729
22
757
941
5
12
25
27
0
253
325
68
144
1359
13169
33
48
185
266
13435
275
1099
57
9
317
2473
1714
116
32
2468
40
2
340
1819
1171
153
11810
225
0
[MW]
Capacity
51849
9244
19
125
3300
5800
850
1082
250
283
3646
41384
165
146
910
1221
42605
23
47
54
54
680
3731
209
24
910
6383
7996
388
120
7875
111
3
1048
4006
4457
477
37738
323
[GWh]
Energy
26
27
Table 5 Forecast and Potential of SHP in EU-27, CC as well as Norway, Switzerland and other countries
Potential with Economic & Environmental Constraints
2010
Country
Forecast
Capacity
[MW]
EU-15
EU-12
Candidate
Countries
Norway
Switzerland
and
Associated
Countries
Austria
Belgium
Denmark
Finland
France
Germany
Greece
Ireland
Italy
Luxembourg
Netherlands
Portugal
Spain
Sweden
UK
EU-15
Bulgaria
Cyprus
Czech Republic
Estonia
Hungary
Latvia
Lithuania
Malta
Poland
Romania
Slovakia
Slovenia
EU-12
EU-27
Croatia
Macedonia
Turkey
CC
EU-27 + CC
Norway
Switzerland
Bosnia &
Herzegovina
Montenegro
Norway &
Switzerland
EU-27, CC
and Associated
Countries
Energy
Upgrading
Capacity
[GWh]
New SHP
Energy
MW
GWh
Capacity
Energy
Capacity
Total
Energy
GWh
MW
GWh
740
26
0
238
750
350
100
30
500
19
12
330
000
375
615
085
290
20
387
24
50
95
57
0
520
900
258
194
795
880
123
363
485
971
851
750
650
3 700
156
0
1 200
3 000
2 000
600
100
1 850
67
30
943
3 224
1 500
2 550
20 920
1 000
71
1 300
95
16
334
203
0
2 410
3 193
965
585
10 172
31 092
435
1 090
19 520
21 045
52 137
19 000
2 300
1 015
31
0
288
1 368
450
102
35
640
29
12
350
1 100
675
653
6 748
346
20
467
27
62
101
62
0
588
981
275
230
3 159
9 907
131
375
6 565
7 071
16 978
5 000
848
4 633
192
0
1 413
4 595
2 500
605
120
2 350
94
30
1 000
3 574
2 700
2 669
26 475
1 158
71
1 650
106
19
348
218
0
2 613
3 366
1 029
689
11 267
37 742
463
1 126
19 870
21 459
59 201
20 000
3 160
30
425
1 330
432
1 360
220
600
222
606
457
1 896
6 045
23 230
6 502
25 126
2 584
8 960
20 896
75 367
23 480
84 327
1 449
60
9
360
2 590
1 795
117
32
3 000
42
0
400
2 199
1 200
160
13 413
255
0
300
7
15
32
28
0
305
400
70
160
1 572
14 985
38
80
250
368
15 353
1 700
1 300
5 481
245
24
1 360
7 487
9 379
495
120
9 237
130
0
1 200
6 692
5 000
559
47 410
810
0
970
31
57
70
96
0
924
900
260
452
4 570
51 980
120
240
750
1 110
53 090
8 000
5 000
275
5
0
50
618
100
2
5
140
10
0
20
100
300
38
1 663
56
0
80
3
12
6
5
0
68
81
17
36
364
2 027
8
12
80
100
2 127
250
198
150
500
14
35
3 000
13 000
18 353
66 090
1
5
1
6
7
1
MW
Total
933
36
0
213
595
500
5
20
500
27
0
57
350
200
119
555
158
0
350
11
3
14
15
0
203
173
64
104
095
650
28
36
350
414
064
000
860
2
7
6
6
14
4
28
References
Acronyms
APER
1. http://epp.eurostat.ec.europa.eu
2. http://www.esha.be
3. http://eur-lex.europa.eu/
4. http://ec.europa.eu/energy/res/publications/doc/2007_02_optres_en.pdf
5. www.rolfsan.se
6. http://www.nordpool.com/Docuents/Communications/Publications/Monthlyreports/
2007Aug.pdf
CC
EIA
EREC
ESHA
EU-12
EU-15
EU-27
Literature
1. 2008 World Atlas & Industry Guide. The Intern. Journal on Hydropower & Dams.
2. EUROSTAT. Energy - Yearly statistics 2006,
ISSN 1830-7833.
3. Laguna M., Administrative barriers for small
Hydropower development in Europe, 2007,
Brussels, ESHA
4. ESHA, Lithuanian Hydropower Association.
Small hydropower situation in the new EU
Member States and Candidate countries.
Thematic Network on Small Hydropower
(TNSHP), 2004, ESHA. (Available from http://
www.esha.be/).
5. OPTRES final report. Assessment and optimisation of renewable energy support schemes
in European electricity market, Intelligent
Energy Europe, 2007.
6. San Bruno G., Developing small hydro to its
full economic potential: a European perspective, (2008), Belgium, ESHA
7. Strategic Study for the development of Small
Hydro Power in the European Union, Blue
Energy for a Green Energy (BlueAge), 2000,
ESHA. (Available from http://www.esha.be/)
GoO
GW
GWh
Head
IEA
IEE
kW
kWh
LHA
LRMC
MS
MW
MWh
N/A
N/Ap
O&M
PPA
SERO
SHP
SHPP
SME
UNEP
WFD
soderberg.sero@telia.com
tsem.se
tomas@
tomas@tsem.se
annicka.wann@gmail.com
punys@hidro.lzuu.lt
Acknowledgements
The authors wish to thank ESHA staff for the revision and
other SHERPA partners for their contributions.
We are grateful to the experts for providing data. The
following experts/organisations have answered the
questionnaire or supplied data:
EU-15: Dipl. Ing. Martina Prechtl of the Austrian Small
Hydropower Association, Ms Nomie Laumont of Belgium
Federation of Renewable and Alternative Energy, Mr Jrgen
Krogsgaard of Denmark, Mr Peter Reiter of Finnish Small
Hydropower Association, Dr Anne Penalba of France Hydro
and Mr Geoffroy du Crest of Inovation-Energy-Develop
Inovation-Energy-Develop-ment (France), Mr Gerhard Eckert of RENERTEC GmbH
(Germany), Mr George Babalis of Greece, Mr Fiacc
O'Brolchain of Irish Hydropower Association, Ms Sara
Gollessi of the Association for Renewable Energy (APER,
Italy), Mr Dirk Snikkers of Nuon Energy Sourcing (Nether
(Nether-lands), Dr Antonio Sa Da Costa of Portugal, Mr Manuel de
Delas of the Spanish Renewable Energy Association, MSc
(Eng) Christer Sderberg of Swedish Renewable Energy
Association, Tomas Sderlund of TS Energi & Marknad and
Peter Danielsson of P&C AB (Sweden), Mr Bill MacGregor of
Npower Renewables and Dr Drona Upadhyay of IT Power
(UK)
(UK)..
EU-12 and CCs: MSc (Eng.) Anton Tzenkov of EnergoprojectHydropower Ltd (Bulgaria), MM. Libor Samanek, Mirsolav
Bartusek and Jiri Venos of ELZACO s.r.o. (the Czech
Republic), Prof Dr Peeter Raesaar of Tallinn Technical
University (Estonia), Mr Csaba Kovacs of Sinergy
Energiaszolgaltato Kft, (Hungary), Prof Karlis Silke of Latvia
University of Agriculture (Latvia), Mr Algis Jonas Jakucionis
and MSc (Eng.) Dainius Tirunas of the Lithuanian Hydro
Hydro-power Association (Lithuania), Dr Janusz Steller of the
Institute of Fluid-Flow Machinery of the Polish Academy of
Sciences (Poland), Mr Marko Gospodjinacki of the Asso
Asso-ciation of Small Hydropower Plants Societies (Slovenia), Eng.
Peter Breza of ROTOR Ltd, Slovakia, Prof Dr Bogdan Popa,
University Politehnica of Bucharest (Romania), Mr Almir
Ajanovic of Intrade Energija d.o.o (Bosnia and Herzegovina),
Dr Eng. Kristijan Horvat of KONCAR - Electrical Engineering
Institute, Inc (Croatia), Mr Igor Nikolov of JSC ELEM Macedonian Power Plants, Macedonia, Prof Dr Sretren
Skuletic of the University of Montenegro, Montenegro, Ms
Ayla Tutus of Ickale Group Company (Turkey).
SERO - Sveriges
Energifreningars
RiksOrganisation
SERO, Box 57, S - 731 22 Kping,
Sweden
T: +46 (0)221 824 22
E: info@sero.se
I: www.sero.se
The sole responsibility for the content of this publication lies with the authors. It does not necessarily reflect the opinion of the European Communities. The
European Commission is not responsible for any use that may be made of the information contained therein.