Professional Documents
Culture Documents
Lecture Questions - Week 7 - Answers-1
Lecture Questions - Week 7 - Answers-1
Flexed
budget
20,000
15,000
Output (units)
Actual
15,000
Direct labour
46,000
Direct materials
30,000
Fixed overheads
66,000
66,000
67,350
142,000
123,000
125,750
210,000
157,500
153,900
68,000
34,500
28,150
Selling price
Profit
1,760
640
3.4 20,000
68,000
Net adverse variances
(39,850)
Actual profit
28,150
(b) The additional information calls into question the validity and usefulness of the two labour
variances.
Direct labour efficiency variance
In effect this could usefully be divided into two elements, one relating to productive time and the
other to idle (non-productive) time.
The hourly rate taking overtime premium into account was 9.20 per hour. The basic rate is therefore
given by:
0.8H + (0.2H 1.25) = 9.20, where H is the basic hourly rate.
H = 8.76
Of the 4,000 hours worked, only 3,650 were involved in production.
Thus the efficiency variance can be analysed into two elements:
Productive direct labour efficiency variance
[(0.25 15,000) 3,650] 8.76
876 (F)
3,066 (A)
The original direct labour efficiency variance suggested that the labour had not been well managed.
The reassessment indicates that the labour was, in fact, efficiently managed during the production
time. The large adverse variance arose from the fact that not all of the labour time was productive
which was no fault of the person who manages the labour in this case.
Direct labour rate variance
This could usefully be recalculated to take account of the fact that no overtime needed to be worked.
(4,000 8.76) 35,040
zero
Thus the recalculation shows that labour was paid the standard rate and there were no savings here.
The original assessment seems to show very great savings. This was because the original was based
on overtime rates, whereas (because of the low output) no overtime was actually worked.