Figure 3 below provides a summary of all the generation resources that OPWP expects to have available for
the MIS for the period 2014 to 2020, including contracted capacity, prospective contracts, and contingency
reserves. As described above, contracted capacity in each year considers only current resources up to the end
of their current contracts, while prospective resources include both planned new capacity and expiring
contracts that are expected to be extended. Contingency reserves comprise the non-firm resources, including
the interconnects, industrial surplus generation, and the prospective solar project.

Figure 3

MW

Total Power Generation Resources MIS

Contracted Capacity

12000

Prospective Contracts
Contingency Reserves

10000
8000
6000
4000
2000
0
2014

2015

2016

2017

2014

2015

2018

2016

2019

2017

2020

2018

2019

2020

Net MW
Contracted Capacity
Currently Contracted Capacity

7193

6904

6806

6519

5847

5816

5785

Prospective Contract Extensions

81

173

455

1125

1156

1187

Prospective New IPP a

740

2600

2600

2600

7193

6985

6979

7714

9572

9572

9572

200

200

200

60

60

60

60

60

60

60

200

200

200

400

400

400

400

Sohar Aluminum Co.

300

300

300

300

300

300

300

Oman Mining Co.

20

20

20

20

20

20

20

580
7773

580
7565

580
7559

780
8494

980
10552

980
10552

980
10552

Prospective Contracted Capacity

Total Contracted + Prospective


Contingency Reserves (non-firm)
Solar Project(s)
Reserve-Sharing Agreements
PDO Interconnection
Abu Dhabi Interconnection

Surplus Generation Agreements c

Total Contingency Reserves


ALL RESOURCES

7-Year Statement (2014-2020)