Project

Tree Planting Activity

Location

Maharlika Village, Taguig City

I. Materials for Plant Box


a. 2 x 2 Lumber
= 4 X 0.9 X 32

= 115.2 m

= 6 X 2.2 X 32

= 422.4
Total

= (537.6 m x 3.28)

= 1763.33 x 2 x 2/12

= 537.6 m
= 588

bd.ft

b. Nails
= 588 bd.ft x 8kg/1000bd.ft

kg

II. Costs

1.
2.

Material
2 x 2 Lumber
Nails

Unit
bd.ft
kg

Quantity
588
5

Unit Cost
25
70
Subtotal

Labor
35% of Materials

Total
14,700
350
15,050

5267.5
Total Cost

Php 20,317.50